UK Statutory Instrument SI 2016/987 United Kingdom

The Brechfa Forest Wind Farm Connection Order 2016

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1 Occupier1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts
Occupier — also bound by 235 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

sch. 9 para. 5 Protection of DCC apparatus Regulated
  • Notify DCC and agree protection works before starting near their apparatusStatutory Undertaker
s.art017 Authority to survey and investigate the land Regulated
  • Grant access for land surveys with 14 days' noticeOccupier
47 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent granted by the Order
s.art004 Maintenance of the authorised development
s.art005 Limits of deviation
s.art006 Benefit of Order
s.art007 Consent to transfer benefit of Order
s.art008 Application of the New Roads and Street Works Act 1991
s.art009 Street works
s.art010 Construction and maintenance of new or altered means of access
s.art011 Temporary closure of streets and public rights of way
s.art012 Traffic regulation
s.art013 Access to works
s.art014 Agreements with street authorities
s.art015 Discharge of water
s.art016 Defence to proceedings in respect of statutory nuisance
s.art018 Application and modification of legislative provisions
s.art019 Compulsory acquisition of rights in, under or over land
s.art020 Statutory authority to override easements and other rights
s.art021 Compulsory acquisition of land – incorporation of the mineral code
s.art022 Time limit for exercise of authority to acquire rights in land compulsorily
s.art023 Suspension of private rights
s.art024 Extinguishment of private rights and restrictive covenants relating to Western Power Distribution (South Wales) Plc’s apparatus removed from land subject to temporary possession
s.art025 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art026 Rights under or over streets
s.art027 Temporary use of land by the undertaker
s.art028 Temporary use of land for maintaining the authorised development
s.art029 Statutory undertakers
s.art030 Recovery of costs of new connections
s.art031 Operational land for purposes of the
s.art032 Felling or lopping of trees and removal of hedgerows
s.art033 Certification of plans
s.art034 Service of notices
s.art035 Arbitration
s.art036 Procedure regarding certain approvals
s.art037 Crown rights
Schedules

Schedules

0 of 46 shown
46 other schedules
s.sch003 Interpretation
s.sch003 Public rights of way
s.sch003 Fencing and other means of enclosure
s.sch003 Contaminated land and groundwater
s.sch003 Archaeology
s.sch003 Plans
s.sch003 Habitat management plan
s.sch003 Trees to be affected
s.sch003 Lighting
s.sch003 Construction traffic management plan
s.sch003 Temporary bridge
s.sch003 Time limits
s.sch003 Construction hours
s.sch003 Construction environmental management plan
s.sch003 Restoration of land used temporarily for construction
s.sch003 Requirement for written approval
s.sch003 Frac-out contingency plan
s.sch003 Decommissioning
s.sch003 Flooding
s.sch003 Foundation Depths
s.sch003 Hedgerows
s.sch003 Otter Surveys
s.sch003 Compliance with approved details
s.sch003 Marsh Fritillary Study
s.sch003 Approved plans and amendments to approved plans
s.sch003 Stages of authorised development
s.sch003 Restrictions on the limits of deviation
s.sch003 Restrictions on the limits of deviation near hedgerows and watercourses
s.sch003 Protection of private water supplies
s.sch003 HDD drill depths and construction periods
s.sch003 Highway accesses
s.sch004 Compensation enactments
s.sch004 Modification of the Land Compensation Act 1973
s.sch004 Application of the 1965 Act
s.sch004 For section 7 of the 1965 Act (measure of compensation...
s.sch004 For section 8 of the 1965 Act (other provisions as...
s.sch004 The following provisions of the 1965 Act (which state the...
s.sch004 Section 11 of the 1965 Act (powers of entry) is...
s.sch004 Section 20 of the 1965 Act (protection for interests of...
s.sch004 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch009 Arbitration
s.sch010 Applications made under Requirement
s.sch010 Further information
s.sch010 Appeals
s.sch010 Appeal process
s.sch010 Fees

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.