UK Statutory Instrument SI 2024/958 United Kingdom

The National Grid (Bramford to Twinstead Reinforcement) Order 2024

Status
In Force

What it defines

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

58 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Maintenance of authorised development
s.art005 Limits of deviation
s.art006 Benefit of Order
s.art007 Consent to transfer benefit of Order
s.art008 Application of the 1990 Act
s.art009 Application of the Community Infrastructure Levy Regulations 2010
s.art010 Planning Permission
s.art011 Street works
s.art012 Application of the permit schemes
s.art013 Application of the 1991 Act
s.art014 Power to alter layout, etc. of streets
s.art015 Temporary closure of streets and public rights of way
s.art016 Access to works
s.art017 Construction, alteration and maintenance of streets
s.art018 Agreements with street authorities
s.art019 Discharge of water
s.art020 Protective works
s.art021 Authority to survey and investigate the land
s.art022 Compulsory acquisition of land
s.art023 Compulsory acquisition of rights
s.art024 Acquisition of subsoil or airspace only
s.art025 Temporary use of land by National Grid
s.art026 Temporary use of land by UKPN
s.art027 Temporary use of land for maintaining the authorised development
s.art028 Use of subsoil under or airspace over streets
s.art029 Disregard of certain interests and improvements
s.art030 Set-off for enhancement in value of retained land
s.art031 Compulsory acquisition of land – incorporation of the mineral code
s.art032 Time limit for exercise of authority to acquire land and rights compulsorily
s.art033 Acquisition of part of certain properties
s.art034 Application of the 1981 Act
s.art035 Application of Part 1 of the 1965 Act
s.art036 Extinguishment and suspension of private rights
s.art037 Power to override easements and other rights
s.art038 Statutory authority to override easements and other rights
s.art039 Extinguishment of private rights and restrictive covenants relating to apparatus belonging to National Grid or UKPN removed from land subject to temporary possession
s.art040 Crown rights
s.art041 Special category land
s.art042 Statutory undertakers
s.art043 Recovery of costs of new connections
s.art044 Application of landlord and tenant law
s.art045 Defence to proceedings in respect of statutory nuisance
s.art046 Traffic regulation
s.art047 Felling or lopping
s.art048 Trees subject to Tree Preservation Orders
s.art049 Temporary closure of, and works in, the River Stour
s.art050 Protection of interests
s.art051 Procedure regarding certain approvals etc.
s.art052 Safeguarding
s.art053 No double recovery
s.art054 Application, disapplication and modification of legislative provisions
s.art055 Amendment of local legislation
s.art056 Certification of documents
s.art057 Service of notices
s.art058 Arbitration
Schedules

Schedules

0 of 105 shown
105 other schedules
s.sch003 (1) In this Schedule unless the context requires otherwise— “biodiversity...
s.sch003 (1) Unless otherwise agreed with the relevant planning authority, all...
s.sch003 (1) No work to construct, alter or temporarily alter any...
s.sch003 (1) In the event that, at some future date, the...
s.sch003 Unless otherwise agreed with the relevant planning authority, written evidence...
s.sch003 (1) Unless otherwise agreed with the relevant planning authority, no...
s.sch003 (1) The authorised development must commence no later than the...
s.sch003 (1) Unless otherwise agreed with the relevant planning authority, written...
s.sch003 (1) No stage of the authorised development may commence until,...
s.sch003 (1) No stage of the authorised development may be brought...
s.sch003 (1) The authorised development must be undertaken in accordance with...
s.sch003 (1) Subject to sub-paragraphs (2) to (5), work may only...
s.sch003 (1) Unless otherwise agreed with the relevant planning authority, no...
s.sch003 (1) Unless otherwise agreed with the relevant planning authority, no...
s.sch004 (1) Where an application has been made to a relevant...
s.sch004 (1) Where an application has been made under paragraph 1...
s.sch004 (1) Where an application is made to a relevant authority...
s.sch004 (1) The undertaker may appeal if— (a) the relevant authority...
s.sch004 (1) On an appeal under paragraph 4, the appointed person...
s.sch004 In this Schedule— “the appeal parties” means the relevant authority,...
s.sch009 Compensation enactments
s.sch009 Section 22 of the 1965 Act (interests omitted from purchase)...
s.sch009 In section 22(2) (expiry of time limit for exercise of...
s.sch009 For Schedule 2A of the 1965 Act substitute— SCHEDULE 2A...
s.sch009 In this Schedule, references to entering on and taking possession...
s.sch009 (1) Without limitation on the scope of paragraph 1, the...
s.sch009 (1) Without limitation on the scope of paragraph 1, the...
s.sch009 Application of the 1965 Act
s.sch009 For section 7 of the 1965 Act (measure of compensation...
s.sch009 For section8 of the 1965 Act (provisions as to divided...
s.sch009 The following provisions of the 1965 Act (which state the...
s.sch009 Section 11 of the 1965 Act (powers of entry) is...
s.sch009 Section 20 of the 1965 Act (protection for interests of...
s.sch014 For the protection of the statutory undertakers referred to in...
s.sch014 (1) Subject to sub-paragraphs (2) to (3), if as the...
s.sch014 This Part of this Schedule does not apply to—
s.sch014 Nothing in this Part of this Schedule affects the provisions...
s.sch014 Application
s.sch014 Interpretation
s.sch014 Apparatus in closed streets
s.sch014 Protective works
s.sch014 Acquisition of land
s.sch014 Removal of apparatus
s.sch014 Facilities and rights for alternative apparatus
s.sch014 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch014 Retained apparatus
s.sch014 Expenses and costs
s.sch014 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch014 Cooperation
s.sch014 Where the undertaker identifies any apparatus which may belong to...
s.sch014 Nothing in this Part of this Schedule affects the provisions...
s.sch014 The undertaker and Anglian Water may by written agreement substitute...
s.sch014 The provisions of this Part of this Schedule have effect,...
s.sch014 In this Part of this Schedule— “asset protection agreement” means...
s.sch014 (1) Where under this Part of this Schedule Network Rail...
s.sch014 This Part of this Schedule does not apply to apparatus...
s.sch014 (1) The undertaker must not exercise the powers conferred by—...
s.sch014 (1) The undertaker must before commencing construction of any specified...
s.sch014 (1) Any specified work and any protective works to be...
s.sch014 The undertaker must— (a) at all times afford reasonable facilities...
s.sch014 Network Rail must at all times afford reasonable facilities to...
s.sch014 (1) If any permanent or temporary alterations or additions to...
s.sch014 The undertaker must repay to Network Rail all reasonable fees,...
s.sch014 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch014 If at any time after the completion of a specified...
s.sch014 The undertaker must not provide any illumination or illuminated sign...
s.sch014 Regardless of any provision in this Order or anything shown...
s.sch014 Any additional expenses which Network Rail may reasonably incur in...
s.sch014 (1) The undertaker must pay to Network Rail all reasonable...
s.sch014 Network Rail must, on receipt of a request from the...
s.sch014 In the assessment of any sums payable to Network Rail...
s.sch014 The undertaker and Network Rail may, subject in the case...
s.sch014 Nothing in this Order, or in any enactment incorporated with...
s.sch014 The undertaker must give written notice to Network Rail if...
s.sch014 The undertaker must no later than 28 days from the...
s.sch014 In relation to any dispute arising under this part of...
s.sch014 Application
s.sch014 (1) If, in the exercise of the powers conferred by...
s.sch014 Interpretation
s.sch014 On Street Apparatus
s.sch014 Apparatus of Cadent in stopped up streets
s.sch014 Protective works to buildings
s.sch014 Acquisition of land
s.sch014 Removal of apparatus
s.sch014 Facilities and rights for alternative apparatus
s.sch014 Retained apparatus: protection of Cadent
s.sch014 Expenses
s.sch014 Indemnity
s.sch014 (1) Not less than 28 days before starting the execution...
s.sch014 Enactments and agreements
s.sch014 Co-operation
s.sch014 Access
s.sch014 Arbitration
s.sch014 Notices
s.sch014 (1) Subject to the following provisions of this paragraph, the...
s.sch014 (1) For the protection of any operator, the following provisions,...
s.sch014 The exercise of the powers of article 42 (statutory undertakers)...
s.sch015 Hedgerow Regulations 1997
s.sch015 Local Government (Miscellaneous Provisions) Act 1976
s.sch015 Neighbourhood Planning Act 2017
s.sch015 Building Act 1984
s.schedule/1/crossheading/construction/maintenance/a Work No. 12 — Temporary Site Compounds
s.schedule/1/crossheading/distribution/electric/line Work No. 8 — removal of existing overhead distribution electric line (Route PCB) between Burstall Bridge and the Twinstead Tee
s.schedule/1/crossheading/grid/supply/point/substati Work No. 9 — Grid Supply Point Substation to the east of Wickham St. Paul
s.schedule/1/crossheading/transmission/electric/line Work No. 1 — Bramford Substation line entries and Route 4YL