UK Statutory Instrument SI 2022 United Kingdom

The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022

Enforced by
Environment Agency, Ofgem
Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker119 Any Person5 Contractor1 Client1

Plus 10 duties on the regulator, Crown ministers and public bodies — folded into the section list below.

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts
Any Person — also bound by 2340 other Acts
Contractor — also bound by 173 other Acts
Client — also bound by 62 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

Schedules

Schedules

126 of 201 shown
s.sch002 Site security Regulated
  • Submit and maintain site security scheme before operationAny Person
s.sch002 Fire prevention Regulated
  • Submit and implement fire appliance access plans for approvalStatutory Undertaker
s.sch002 Surface water drainage Regulated
  • Submit and implement approved surface water drainage plansStatutory Undertaker
s.sch002 Foul water drainage Regulated
  • Submit and implement approved foul water drainage plansStatutory Undertaker
s.sch002 Flood risk mitigation Regulated
Other duties (1) — Crown / regulator
  • Submit and implement flood risk mitigation schemes before construction and operationCrown / Minister / Government department
s.sch002 Contaminated land and groundwater Regulated
  • Submit and implement approved contamination remediation schemeStatutory Undertaker
s.sch002 Archaeology Regulated
  • Submit and follow archaeological investigation scheme before constructionContractor
s.sch002 Construction environmental management plan Regulated
  • Submit and follow a construction environmental management planStatutory Undertaker
s.sch002 Protection of highway surfaces Regulated
  • Submit highway condition survey details and carry out repairs as approvedStatutory Undertaker
s.sch002 Temporary haul road (traffic management and protection) Regulated
  • Maintain temporary haul road and implement traffic management for abnormal loadsStatutory Undertaker
s.sch002 Commencement of the authorised development Regulated
  • Commence development within 7 years and notify planning authority 14 days beforeStatutory Undertaker
s.sch002 Temporary haul road (biodiversity protection) Regulated
  • Carry out Work No. 10A with biodiversity measures and submit ecologist's reportStatutory Undertaker
s.sch002 Temporary haul road (removal and restoration) Regulated
  • Remove temporary haul road and restore site after commissioningStatutory Undertaker
s.sch002 Temporary haul road (prior approval of restoration scheme) Regulated
  • Submit road removal and restoration scheme for approvalStatutory Undertaker
s.sch002 Pilfrey laydown (design) Regulated
  • Retain and maintain the Pilfrey laydown area in accordance with the approved plansStatutory Undertaker
s.sch002 Pilfrey laydown (removal and restoration) Regulated
  • Remove Pilfrey laydown and restore land within 3 months after commissioningStatutory Undertaker
s.sch002 Construction traffic management plan Regulated
  • Get construction traffic management plan approved before starting constructionStatutory Undertaker
s.sch002 Construction worker travel plan Regulated
  • Submit and implement construction worker travel planStatutory Undertaker
s.sch002 Construction hours Regulated
  • Comply with construction hours and delivery restrictionsStatutory Undertaker
s.sch002 Control of noise and vibration - construction Regulated
  • Submit and implement a noise and vibration control scheme for constructionStatutory Undertaker
s.sch002 Control of noise - operation Regulated
  • Submit and implement a noise management scheme before commercial operationStatutory Undertaker
s.sch002 Notice of commencement and completion of commissioning Regulated
  • Notify planning authority of commissioning start and completionStatutory Undertaker
s.sch002 Piling and penetrative foundation design Regulated
  • Submit and follow approved piling and foundation design method statementStatutory Undertaker
s.sch002 Restoration of land used temporarily for construction Regulated
  • Submit restoration scheme and restore land used temporarily for constructionStatutory Undertaker
s.sch002 Combined heat and power Regulated
  • Design for and review heat export opportunitiesStatutory Undertaker
s.sch002 Carbon capture and compression plant Regulated
  • Keep land available for carbon capture pipeline and infrastructureStatutory Undertaker
s.sch002 Aviation warning lighting Regulated
  • Submit aviation warning lighting details and obtain approval before constructionStatutory Undertaker
s.sch002 Air safety Regulated
  • Submit site heights and crane details for aviation charting before starting constructionStatutory Undertaker
s.sch002 Employment, skills and training plan Regulated
  • Submit and implement an employment and skills plan for local residentsClient
s.sch002 Decommissioning Regulated
  • Submit decommissioning environmental management plan for approvalStatutory Undertaker
s.sch002 Requirement for written approval Regulated
Other duties (1) — Crown / regulator
  • Relevant planning authority or other person must give approvals in writingLocal authority
s.sch002 Notice of commencement of commercial use Regulated
  • Notify planning authority before or within 14 days of starting commercial useStatutory Undertaker
s.sch002 Amendments agreed by the relevant planning authority Regulated
Other duties (1) — Crown / regulator
  • Relevant planning authority must ensure non-material amendments agreed for Keadby 3 do not cause new environmental effectsLocal authority
s.sch002 Detailed design Regulated
  • Submit detailed design plans for approval before starting constructionStatutory Undertaker
s.sch002 Landscaping and biodiversity protection management and enhancement Regulated
  • Submit and implement landscaping and biodiversity plans for the developmentStatutory Undertaker
s.sch002 Highway accesses Regulated
  • Get highway access designs approved before starting constructionStatutory Undertaker
s.sch002 Means of enclosure Regulated
  • Submit and implement plans for site fencing, keep sites secure, and maintain permanent fencingAny Person
s.sch009 PROCEDURE FOR DISCHARGE OF REQUIREMENTS (opens in a new tab) Regulated
Other duties (1) — Crown / regulator
  • Local planning authority must decide on 'Requirement' applications within 8 weeksLocal authority
s.sch009 Applications made under Requirements Regulated
Other duties (1) — Crown / regulator
  • Local planning authority must decide your application within 8 weeks or it is deemed grantedLocal authority
s.sch009 Further information and consultation Regulated
Other duties (1) — Crown / regulator
  • Planning authority must request further information or consult within statutory deadlinesLocal authority
s.sch009 Appeals Regulated
Other duties (1) — Crown / regulator
  • Planning authority appeals processCrown / Minister / Government department
s.sch010 Retained apparatus: protection of gas undertaker Regulated
  • Submit plans to National Grid before starting gas pipeline worksStatutory Undertaker
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason... Regulated
  • Pay costs and indemnify Northern Powergrid for damage caused by your worksStatutory Undertaker
s.sch010 Where in consequence of the proposed construction of any of... Regulated
  • Co-ordinate works safely and co-operate with Northern PowergridStatutory Undertaker
s.sch010 If in consequence of an agreement reached in accordance with... Regulated
  • Provide alternative access to Northern Powergrid's apparatus if obstructedStatutory Undertaker
s.sch010 The plans submitted to Northern Powergrid by the undertaker pursuant... Regulated
  • Submit plans to Northern Powergrid at the correct addressStatutory Undertaker
s.sch010 Indemnity Regulated
  • Indemnify National Grid and provide security before constructionStatutory Undertaker
s.sch010 Co-operation Regulated
  • Co-ordinate construction works with National Grid for safety and efficiencyStatutory Undertaker
s.sch010 Access Regulated
  • Provide alternative access to National Grid apparatus if obstructedStatutory Undertaker
s.sch010 Notices Regulated
  • Send plans to National Grid via specified email addressStatutory Undertaker
s.sch010 Powers requiring the Canal and River Trust’s consent Regulated
  • Obtain Canal and River Trust consent before interfering with the waterwayStatutory Undertaker
s.sch010 Fencing Regulated
  • Install fencing where the engineer requires itStatutory Undertaker
s.sch010 Survey of waterway Regulated
  • Undertaker must survey waterway before and after constructionStatutory Undertaker
s.sch010 Approval of plans, protective works etc. Regulated
  • Get Canal and River Trust approval for construction plans before starting workStatutory Undertaker
s.sch010 Design of works Regulated
  • Consult and collaborate with Canal and River Trust on design and environmental effectsStatutory Undertaker
s.sch010 Notice of works Regulated
  • Give 30 days' notice of works to the engineerStatutory Undertaker
s.sch010 Lighting Regulated
  • Provide temporary and signal lighting for navigation safety during worksStatutory Undertaker
s.sch010 Prevention of pollution Regulated
  • Prevent pollution of the waterway during constructionStatutory Undertaker
s.sch010 Access to work – provision of information Regulated
  • Allow engineer access to works and provide construction informationStatutory Undertaker
s.sch010 Alterations to the waterway Regulated
  • Pay costs of waterway alterations required due to constructionStatutory Undertaker
s.sch010 Maintenance of works Regulated
  • Maintain works to prevent detriment on notice from Canal and River TrustStatutory Undertaker
s.sch010 Repayment of the Canal and River Trust’s fees, etc. Regulated
  • Repay Canal and River Trust’s fees for protective works and supervisionStatutory Undertaker
s.sch010 Regardless of any provision in this Order or anything shown... Regulated
  • Do not acquire apparatus without reaching agreementStatutory Undertaker
s.sch010 (1) If, in the exercise of the powers conferred by... Regulated
  • Do not remove utility apparatus until alternative is provided and operationalStatutory Undertaker
s.sch010 Apparatus of National Grid in stopped up streets Regulated
  • Grant legal easements to National Grid before permanently stopping up a streetStatutory Undertaker
s.sch010 (1) Where, in accordance with the provisions of this Part,... Regulated
  • Provide alternative apparatus facilities on agreed or arbitrated termsStatutory Undertaker
s.sch010 (1) Not less than twenty-eight days before starting the execution... Regulated
  • Submit works plans to utility companies before starting construction near their apparatusStatutory Undertaker
s.sch010 (1) Subject to the following provisions of this paragraph, the... Regulated
  • Pay utility companies for work caused by your constructionStatutory Undertaker
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason... Regulated
  • Pay utility costs for damage or interruption caused by your construction workStatutory Undertaker
s.sch010 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay compensation for damage to electronic communications apparatusStatutory Undertaker
s.sch010 Protective works to buildings Regulated
  • Do not obstruct National Grid's apparatus and pay for any damage causedStatutory Undertaker
s.sch010 (1) Where under this Part of this Schedule Network Rail... Regulated
  • Network Rail must co-operate to avoid delays and resolve procedure conflictsAny Person
s.sch010 (1) The undertaker must not exercise the powers conferred by—... Regulated
  • Do not exercise powers over railway property without Network Rail's consentStatutory Undertaker
s.sch010 (1) The undertaker must, before commencing construction of any specified... Regulated
  • Submit construction plans to Network Rail for approval before starting workStatutory Undertaker
s.sch010 The undertaker must— (a) at all times afford reasonable facilities... Regulated
  • Provide access and information to the engineer during constructionStatutory Undertaker
s.sch010 Network Rail must at all times afford reasonable facilities to... Regulated
Other duties (1) — Crown / regulator
  • Network Rail must provide access and information to the undertakerStatutory regulator
s.sch010 (1) If any permanent or temporary alterations or additions to... Regulated
  • Pay Network Rail for alterations needed to protect railway safetyStatutory Undertaker
s.sch010 The undertaker must repay to Network Rail all reasonable fees,... Regulated
  • Repay Network Rail's reasonable costs for specified works and protective measuresStatutory Undertaker
s.sch010 If at any time after the completion of a specified... Regulated
  • Maintain specified works to avoid adversely affecting railway propertyStatutory Undertaker
s.sch010 The undertaker must not provide any illumination or illuminated sign... Regulated
  • Consult Network Rail before installing any illumination or sign near their railwayStatutory Undertaker
s.sch010 Any additional expenses which Network Rail may reasonably incur in... Regulated
  • Repay Network Rail's reasonable additional expenses for railway property alterationsStatutory Undertaker
s.sch010 Network Rail must, on receipt of a request from the... Regulated
Other duties (1) — Crown / regulator
  • Network Rail must provide cost estimates on requestStatutory regulator
s.sch010 In the assessment of any sums payable to Network Rail... Regulated
  • Ignore inflated Network Rail claims caused by unnecessary actionsStatutory Undertaker
s.sch010 The undertaker must give written notice to Network Rail if... Regulated
  • Notify Network Rail before transferring the Order’s benefitsStatutory Undertaker
s.sch010 Removal of apparatus Regulated
  • Do not remove National Grid apparatus until replacement is liveStatutory Undertaker
s.sch010 The undertaker must no later than 28 days from the... Regulated
  • Provide certified plans to Network Rail within 28 daysStatutory Undertaker
s.sch010 The undertaker hereby agrees not to exercise its powers under... Regulated
  • Do not exercise Order powers without full compliance with this PartStatutory Undertaker
s.sch010 Interaction with the NGC Pipeline Network Regulated
  • Use reasonable endeavours to avoid conflict with the NGC Pipeline NetworkStatutory Undertaker
s.sch010 Carbon dioxide export connections works Regulated
  • Do not carry out Work No.7B without National Grid's agreementStatutory Undertaker
s.sch010 Without limiting any other provision of this Order, where NGC... Regulated
  • Use reasonable endeavours to coordinate NGC's Work No.7B with the authorised developmentStatutory Undertaker
s.sch010 (1) Before beginning to construct any carbon dioxide export connection... Regulated
  • Submit plans to NGC before building CO2 export connectionStatutory Undertaker
s.sch010 Facilities and rights for alternative apparatus Regulated
  • Provide alternative apparatus rights no less favourable to National GridStatutory Undertaker
s.sch010 (1) Any approval of NGC required under this Schedule— Regulated
  • NGC must respond to approval requests within 56 days and not unreasonably withholdAny Person
s.sch010 (1) The undertaker must give to NGC not less than... Regulated
  • Notify NGC before and after starting CO₂ export connection constructionStatutory Undertaker
s.sch010 Acquisition of land Regulated
  • You must not take NGC's land rights without their agreementStatutory Undertaker
s.sch010 Protective works to buildings Regulated
  • Do not obstruct access to NGC apparatus or pipeline sitesStatutory Undertaker
s.sch010 Removal of NGC apparatus Regulated
  • Do not remove NGC apparatus until alternative supply is operationalStatutory Undertaker
s.sch010 Specified works plan approval Regulated
  • Submit and follow approved plans for works near NGC pipelinesStatutory Undertaker
s.sch010 (1) Subject to sub-paragraph (5), any specified work, and all... Regulated
  • Construct specified works to NGC's satisfaction and in accordance with approved plansStatutory Undertaker
s.sch010 Expenses and costs Regulated
  • Repay NGC's reasonable expenses for apparatus protection and carbon dioxide export worksStatutory Undertaker
s.sch010 Retained apparatus: protection of electricity undertaker Regulated
  • Get National Grid approval for construction near their apparatusStatutory Undertaker
s.sch010 Indemnity Regulated
  • Indemnify NGC for damage or supply interruptions caused by construction worksStatutory Undertaker
s.sch010 Co-operation Regulated
  • Coordinate works with NGC for safety and efficiencyStatutory Undertaker
s.sch010 Regardless of any provision in this Order or anything shown... Regulated
  • Obtain Northern Powergrid's agreement before acquiring their apparatus or overriding their interestsStatutory Undertaker
s.sch010 (1) If, in the exercise of the powers conferred by... Regulated
  • Ensure alternative apparatus for Northern Powergrid before removing existing cablesStatutory Undertaker
s.sch010 (1) Where, in accordance with the provisions of this Part... Regulated
  • Grant alternative apparatus facilities to Northern Powergrid on agreed termsStatutory Undertaker
s.sch010 (1) Not less than 48 days before starting the execution... Regulated
  • Submit works plans to Northern Powergrid before starting near their apparatusStatutory Undertaker
s.sch011 DESIGN PARAMETERS (opens in a new tab) Regulated
  • Comply with maximum building and structure dimensionsStatutory Undertaker
s.sch013 The undertaker must complete pre-works bathymetry of the areas specified... Regulated
  • Complete pre-works bathymetry surveys and share resultsStatutory Undertaker
s.sch013 The undertaker must notify the MMO in writing of any... Regulated
  • Notify MMO of agents, contractors or subcontractors carrying out licensed activitiesStatutory Undertaker
s.sch013 The undertaker must notify the MMO in writing of any... Regulated
  • Notify MMO of vessels carrying out licensed activitiesStatutory Undertaker
s.sch013 During Construction, Operation and Maintenance Regulated
  • Ensure marine-suitable coatings and treatments used per HSE or EA guidelinesStatutory Undertaker
s.sch013 The undertaker must not discharge waste concrete slurry or wash... Regulated
  • Prevent concrete and cement pollution entering the riverStatutory Undertaker
s.sch013 During licensed activities all wastes must be stored in designated... Regulated
  • Store all wastes in designated, isolated, bunded areas during licensed activitiesStatutory Undertaker
s.sch013 (1) Vibratory piling must be used as standard, with percussive... Regulated
  • Use vibratory piling as standard with soft-start for percussive pilingStatutory Undertaker
s.sch013 Piling must not be undertaken between 01 September and 31... Regulated
  • Do not carry out piling during salmon migration season and only between 7am and 7pmStatutory Undertaker
s.sch013 The undertaker must comply with the lighting, hazard marking and... Regulated
  • Comply with ABP Humber’s lighting and hazard marking requirementsStatutory Undertaker
s.sch013 The undertaker must ensure any rock material used in the... Regulated
  • Use only clean, sourced rock material in constructionStatutory Undertaker
s.sch013 In the event that any rock or stone material is... Regulated
  • Report lost rock or stone material below mean high water springsStatutory Undertaker
s.sch013 (1) The undertaker must report all dropped objects to the... Regulated
  • Report dropped objects to MMO within 24 hoursStatutory Undertaker
s.sch013 Post Construction Regulated
  • Clear site equipment and waste within six weeks of completionStatutory Undertaker
s.sch013 The undertaker must ensure that the MMO Local Enforcement Office... Regulated
  • Notify MMO of completion of licensed activities within 10 daysStatutory Undertaker
s.sch013 The undertaker must complete post-works bathymetry of the areas specified... Regulated
  • Complete post-works bathymetry survey and share results with navigational authoritiesStatutory Undertaker
s.sch013 General Regulated
  • Report oil, fuel or chemical spills in marine environment to MMO within 12 hoursStatutory Undertaker
s.sch013 Notifications and Inspections Regulated
  • Distribute and display marine licence, allow inspections, and notify marinersStatutory Undertaker
s.sch013 Pre-construction Regulated
  • Submit construction environmental management plan for approval before work startsStatutory Undertaker
75 other schedules
s.sch002 Interpretation
s.sch002 Local liaison committee
s.sch002 Approved details and amendments to them
s.sch002 External lighting
s.sch006 Interpretation
s.sch007 Compensation enactments
s.sch007 (1) Without limitation on the scope of paragraph 1, the...
s.sch007 (1) Without limitation on the scope of paragraph 1, the...
s.sch007 Application of Part 1 of the 1965 Act
s.sch007 (1) The modifications referred to in paragraph 4(a) are as...
s.sch009 In this Schedule— “business day” means a day other than...
s.sch009 Fees
s.sch010 Application
s.sch010 (1) Subject to the following provisions of this paragraph, the...
s.sch010 Nothing in this Part of this Schedule affects the provisions...
s.sch010 Expenses
s.sch010 Enactments and agreements
s.sch010 Arbitration
s.sch010 Interpretation
s.sch010 Interpretation
s.sch010 Construction of specified works
s.sch010 On Street Apparatus
s.sch010 Making good of detriment; compensation and indemnity, etc.
s.sch010 Arbitration
s.sch010 Capitalised sums
s.sch010 For the protection of the utility undertakers referred to in...
s.sch010 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch010 This Part does not apply to apparatus in respect of...
s.sch010 Nothing in this Part affects the provisions of any enactment...
s.sch010 (1) For the protection of any operator, the following provisions...
s.sch010 The exercise of the powers of article 29 (statutory undertakers)...
s.sch010 This Part of this Schedule does not apply to—
s.sch010 Nothing in this Part affects the provisions of any enactment...
s.sch010 The provisions of this Part of this Schedule have effect,...
s.sch010 In this Schedule— “asset protection agreement” means an agreement to...
s.sch010 (1) Any specified work and any protective works to be...
s.sch010 Acquisition of land
s.sch010 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch010 (1) The undertaker must pay to Network Rail all reasonable...
s.sch010 The undertaker and Network Rail may, subject in the case...
s.sch010 In Nothing in this Order, or in any enactment incorporated...
s.sch010 In relation to any dispute arising under this part of...
s.sch010 Application
s.sch010 Section A and paragraph 88 of Section B of this...
s.sch010 Interpretation
s.sch010 On street apparatus
s.sch010 Facilities and rights for alternative apparatus
s.sch010 Disputes
s.sch010 For the protection of Northern Powergrid the following provisions have...
s.sch010 In this Part of this Schedule— “1991 Act” means the...
s.sch010 This Part of this Schedule does not apply to apparatus...
s.sch011 Maximum parameters for buildings and structures are set out at...
s.sch011 The finished ground level in respect of Work No. 1A,...
s.sch011 Maximum parameters of the A18 Gatehouse building (Work No. 8B)...
s.sch011 Maximum parameters for length (m), width (m) or diameter (m)...
s.sch013 (1) In this licence the definitions in article 2 must...
s.sch013 (1) The undertaker must submit a marine method statement (MMS)...
s.sch013 The storage, handling, transport and use of fuels, lubricants, chemicals...
s.sch013 Subject to the conditions, this licence authorises the undertaker to...
s.sch013 Conditions Discharge
s.sch013 Licensed activities are authorised in relation to the construction, maintenance...
s.sch013 The substances or articles authorised for deposit associated with the...
s.sch013 The undertaker may engage in the licensed activities in the...
s.sch013 The coordinates in Table 9 are defined in accordance with...
s.007 Consent to transfer benefit of the Order Regulated
  • Notify the Secretary of State before transferring project benefitsStatutory Undertaker
s.011 Construction and maintenance of new or altered means of access Regulated
  • Maintain new or altered road access for 12 monthsStatutory Undertaker
s.014 Discharge of water Regulated
  • Obtain consent and follow safety protocols for discharging waterStatutory Undertaker
s.015 Authority to survey and investigate the land Regulated
  • Give 14 days' notice before surveying land and compensate for damageStatutory Undertaker
s.019 Statutory authority to override easements and other rights Regulated
  • Pay compensation for interfering with land rights or contract restrictionsStatutory Undertaker
s.036 Restoration works Regulated
  • Restore site land and infrastructure if construction does not startStatutory Undertaker
s.041 Certification of plans etc. Regulated
  • Submit project plans and documents for certificationStatutory Undertaker
s.042 Service of notices Regulated
  • Follow specific rules when sending or receiving formal noticesAny Person
s.043 Procedure in relation to certain approvals etc. Regulated
Other duties (1) — Crown / regulator
  • Authorities must provide written decisions without unreasonable delayStatutory regulator
s.045 Guarantees in respect of payment of compensation Regulated
  • Secure compensation guarantees before exercising land and street powersStatutory Undertaker
35 other provisions
s.001 Citation and commencement
s.002 Interpretation
s.003 Development consent etc. granted by the Order
s.004 Maintenance of authorised development
s.005 Operation of authorised development
s.006 Benefit of the Order
s.008 Application and modification of statutory provisions
s.009 Street works
s.010 Power to alter layout, etc., of streets
s.012 Access to works
s.013 Agreements with street authorities
s.016 Temporary interference with canal and public rights of navigation
s.017 Use of private roads for construction
s.018 Compulsory acquisition of land
s.020 Time limit for exercise of authority to acquire land compulsorily
s.021 Compulsory acquisition of rights etc.
s.022 Private rights
s.023 Application of the 1981 Act and Part 1 of the 1961 Act
s.024 Acquisition of subsoil or airspace only
s.025 Modification of Part 1 of the 1965 Act
s.026 Rights under or over streets
s.027 Temporary use of land for carrying out the authorised development
s.028 Temporary use of land for maintaining the authorised development
s.029 Statutory undertakers
s.030 Apparatus and rights of statutory undertakers in streets
s.031 Recovery of costs of new connections
s.032 Crown Rights
s.033 Felling or lopping of trees and removal of hedgerows
s.034 Protective works to buildings
s.035 Protective provision
s.037 Application of landlord and tenant law
s.038 Operational land for purposes of the 1990 Act
s.039 Deemed marine licence under the Marine and Coast Access Act 2009
s.040 Defence to proceedings in respect of statutory nuisance
s.044 Arbitration