UK Statutory Instrument 2025 United Kingdom

The North Lincolnshire Green Energy Park Order 2025

At a glance

What's here

2 compliance obligations

Who this Act binds

Business-side actors with duties under this Act, ranked by how often they appear.

  • Statutory Undertaker 1
  • Operator 1

Other Acts binding the same actors

For each actor bound by this Act, the other UK Acts that bind them most often. Useful for understanding the full compliance landscape facing each role.

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch014

(1) Subject to sub-paragraphs (2) to (4), if as the...

  • Notify the undertaker of claims and do not settle without consent Operator
Browse 129 other Schedules — structural / supplementary
s.sch002

Interpretation

s.sch002

Foul water drainage

s.sch002

Construction traffic management and travel planning

s.sch002

Archaeology

s.sch002

Flood risk

s.sch002

Operational travel plan

s.sch002

New highway access

s.sch002

Fuel Type

s.sch002

Decommissioning

s.sch002

Combined heat and power

s.sch002

Commissioning

s.sch002

Commencement and phasing of the authorised development and notices

s.sch002

Carbon Capture

s.sch002

Rail

s.sch002

Local employment and skills

s.sch002

Noise

s.sch002

PRF

s.sch002

Where a requirement requires the authorised development to be constructed...

s.sch002

Amendments agreed by the relevant planning authority

s.sch002

Requirement for written approval

s.sch002

Anticipatory steps towards compliance with any requirement

s.sch002

Applications made under requirements

s.sch002

Detailed design

s.sch002

Fees

s.sch002

Further information

s.sch002

Appeals

s.sch002

Interpretation

s.sch002

Environmental management

s.sch002

Lighting scheme

s.sch002

Landscape design

s.sch002

Landscape and ecology management

s.sch002

Water Resources Assessment

s.sch002

Surface water drainage

s.sch011

Compensation enactments

s.sch011

Section 22 of the 1965 Act (interests omitted from purchase)...

s.sch011

(1) Without prejudice to the generality of paragraph 1, the...

s.sch011

(1) Without limitation on the scope of paragraph (1), the...

s.sch011

Application of the 1965 Act

s.sch011

For section 7 of the 1965 Act (measure of compensation)...

s.sch011

Section 8(1) of the 1965 Act has effect as if...

s.sch011

The following provisions of the 1965 Act (which state the...

s.sch011

Section 11 of the 1965 Act (powers of entry) is...

s.sch011

Section 20 of the 1965 Act (tenants at will, etc..)...

s.sch014

For the protection of the utility undertakers referred to in...

s.sch014

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch014

Nothing in this Part of this Schedule affects the provisions...

s.sch014

(1) For the protection of any operator, the following provisions...

s.sch014

The exercise of the powers of article 34 (statutory undertakers)...

s.sch014

This Part of this Schedule does not apply to—

s.sch014

Nothing in this Part of this Schedule affects the provisions...

s.sch014

Application

s.sch014

Interpretation

s.sch014

Apparatus in stopped up streets

s.sch014

In this Part of this Schedule— “alternative apparatus” means alternative...

s.sch014

Acquisition of land

s.sch014

Removal of apparatus

s.sch014

Facilities and rights for alternative apparatus

s.sch014

Retained apparatus

s.sch014

Expenses and costs

s.sch014

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch014

Anglian Water must use its reasonable endeavours to mitigate losses...

s.sch014

Cooperation

s.sch014

Unmapped Apparatus

s.sch014

Miscellaneous

s.sch014

This Part of this Schedule does not apply to apparatus...

s.sch014

The undertaker and Anglian Water may by written agreement substitute...

s.sch014

Disputes

s.sch014

For the protection of Northern Powergrid the following provisions have...

s.sch014

In this Part of this Schedule— “alternative apparatus” means alternative...

s.sch014

This Part of this Schedule does not apply to apparatus...

s.sch014

Regardless of any provision in this Order or anything shown...

s.sch014

(1) If, in the exercise of the powers conferred by...

s.sch014

(1) Where, in accordance with the provisions of this Part...

s.sch014

(1) Not less than 35 days before starting the execution...

s.sch014

(1) Subject to the following provisions of this paragraph, the...

s.sch014

(1) Where any street is stopped up under article 14...

s.sch014

(1) Subject to sub-paragraphs (2) to (4), if by reason...

s.sch014

Nothing in this Part of this Schedule affects the provisions...

s.sch014

Where in consequence of the proposed construction of any of...

s.sch014

If in consequence of an agreement reached in accordance with...

s.sch014

The plans submitted to Northern Powergrid by the undertaker pursuant...

s.sch014

Where practicable, the Undertaker and Northern Powergrid will make reasonable...

s.sch014

The provisions of this Part of this Schedule have effect,...

s.sch014

In this Part of this Schedule— “asset protection agreement” means...

s.sch014

(1) Where under this Part of this Schedule Network Rail...

s.sch014

(1) The undertaker must not exercise the powers conferred by—...

s.sch014

Regardless of any provision in this Order or anything shown...

s.sch014

(1) The undertaker must before commencing construction of any specified...

s.sch014

(1) Any specified work and any protective works to be...

s.sch014

The undertaker must— (a) at all times afford reasonable facilities...

s.sch014

Network Rail must at all times afford reasonable facilities to...

s.sch014

(1) If any permanent or temporary alterations or additions to...

s.sch014

The undertaker must repay to Network Rail all reasonable fees,...

s.sch014

(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

s.sch014

If at any time after the completion of a specified...

s.sch014

The undertaker must not provide any illumination or illuminated sign...

s.sch014

Any additional expenses which Network Rail may reasonably incur in...

s.sch014

(1) If, in the exercise of the powers conferred by...

s.sch014

(1) The undertaker must pay to Network Rail all reasonable...

s.sch014

Network Rail must, on receipt of a request from the...

s.sch014

In the assessment of any sums payable to Network Rail...

s.sch014

The undertaker and Network Rail may, subject in the case...

s.sch014

Nothing in this Order, or in any enactment incorporated with...

s.sch014

The undertaker must give written notice to Network Rail if...

s.sch014

The undertaker must no later than 28 days from the...

s.sch014

In relation to any dispute arising under this Part of...

s.sch014

For the protection of Cadent the following provisions will, unless...

s.sch014

In this Part of the Schedule— “acceptable credit provider” means...

s.sch014

(1) Where, in accordance with the provisions of this Part...

s.sch014

(1) This Part of this Schedule does not apply to...

s.sch014

(1) Where any street is stopped up under article 14...

s.sch014

(1) Regardless of any provision in this Order or anything...

s.sch014

(1) If, in the exercise of the powers conferred by...

s.sch014

(1) Where, in accordance with the provisions of this Part...

s.sch014

(1) Not less than 56 days before the commencement of...

s.sch014

(1) Subject to the following provisions of this paragraph, the...

s.sch014

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch014

Except where this Part of this Schedule provides otherwise, nothing...

s.sch014

(1) Where in consequence of the proposed construction of any...

s.sch014

(1) Not less than 28 days before starting the execution...

s.sch014

If in consequence of any agreement reached in accordance with...

s.sch014

Save for differences or disputes arising under sub-paragraph 73 any...

s.sch014

Notwithstanding article 47 (service of notices) any plans submitted to...

s.sch014

(1) Subject to the following provisions of this paragraph, the...

s.schedule/1/part/1/paragraph/1n2

Energy park: ERF infrastructure

s.schedule/1/part/1/paragraph/1n3

Rail infrastructure

s.schedule/1/part/1/paragraph/1n4

Energy park: supporting infrastructure

s.schedule/1/part/1/paragraph/1n5

DHPWN

s.schedule/1/part/1/paragraph/1n6

Landscaping, mitigation and utility works

s.art038

Authority to survey and investigate the land

  • Notify landowners, obtain consents, and compensate before surveying land Statutory Undertaker
Browse 49 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Electronic Communications

s.art004

Development consent etc. granted by the Order

s.art005

Limits of deviation

s.art006

Maintenance of authorised development

s.art007

Operation of authorised development

s.art008

Planning permission

s.art009

Benefit of the Order

s.art010

Consent to transfer the benefit of the Order

s.art011

Application and modification of legislative provisions

s.art012

Street works

s.art013

Power to alter layout, etc., of streets

s.art014

Permanent stopping up of streets

s.art015

Temporary stopping up of streets

s.art016

Public rights of way – creation and temporary stopping up

s.art017

Accesses

s.art018

Clearways, prohibitions and restrictions

s.art019

Classification of highways

s.art020

Speed limits

s.art021

Traffic regulation

s.art022

Agreements with street authorities

s.art023

Funding

s.art024

Compulsory acquisition of land

s.art025

Time limit for exercise of authority to acquire land and rights compulsorily

s.art026

Compulsory acquisition of rights

s.art027

Private rights

s.art028

Application of the 1981 Act

s.art029

Application of Part 1 of the 1965 Act

s.art030

Acquisition of subsoil or airspace only

s.art031

Rights under or over streets

s.art032

Temporary use of land for carrying out the authorised development

s.art033

Temporary use of land for maintaining the authorised development

s.art034

Statutory undertakers

s.art035

Apparatus and rights of statutory undertakers in stopped up streets

s.art036

Recovery of costs of new connections

s.art037

Discharge of water

s.art039

Felling or lopping of trees

s.art040

Removal of hedgerows

s.art041

Removal of human remains

s.art042

Protective provisions

s.art043

Application of landlord and tenant law

s.art044

Operational land for purposes of the 1990 Act

s.art045

Defence to proceedings in respect of statutory nuisance

s.art046

Certification of plans, etc.

s.art047

Service of notices

s.art048

Procedure in relation to certain approvals, etc.

s.art049

Arbitration

Explore more

Browse legislation

Find other UK business legislation with related guidance.