Business-side roles with duties under this instrument.
Statutory Undertaker5
Contractor2
Other Acts binding the same actors
If a role above is yours, these are the other instruments that most often bind it.
Statutory Undertaker — also bound by 179 other Acts
The Cory Decarbonisation Project Order 2025
120 duties
Water Industry Act 1991
53 duties
Contractor — also bound by 173 other Acts
What it requires
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
50 other provisions — procedural and definitional
s.art001
Citation and commencement
s.art002
Interpretation
s.art003
Electronic communications
s.art004
Development consent etc. granted by this Order
s.art005
Maintenance of authorised development
s.art006
Operation of authorised development
s.art007
Benefit of this Order
s.art008
Consent to transfer benefit of this Order
s.art009
Amendment and modification of statutory provisions
s.art010
Power to alter layout etc. of streets
s.art011
Street works
s.art012
Construction and maintenance of new or altered means of access
s.art013
Temporary stopping up of streets, public rights of way and access land
s.art014
Access to works
s.art015
Agreements with streets authorities
s.art016
Traffic regulation
s.art017
Discharge of water
s.art018
Felling or lopping of trees and removal of hedgerows
s.art019
Protective works to buildings
s.art020
Authority to survey and investigate the land
s.art021
Removal of human remains
s.art021
Supplemental land
s.art022
Compulsory acquisition of land
s.art023
Power to override easements and other rights
s.art024
Time limit for exercise of authority to acquire land compulsorily
s.art025
Compulsory acquisition of rights etc.
s.art026
Private rights
s.art027
Application of the 1981 Act
s.art028
Acquisition of subsoil and airspace only
s.art029
Modification of Part 1 of the 1965 Act
s.art030
Rights under or over streets
s.art031
Temporary use of land for carrying out the authorised development
s.art032
Temporary use of land for maintaining the authorised development
s.art033
Statutory undertakers
s.art034
Apparatus and rights of statutory undertakers in streets
s.art035
Recovery of costs of new connections
s.art036
Compulsory acquisition of land – incorporation of the mineral code
s.art037
Deemed marine licence
s.art038
Application of landlord and tenant law
s.art039
Operational land for purposes of the 1990 Act
s.art040
Defence to proceedings in respect of statutory nuisance
s.art041
Protection of interests
s.art042
Saving for Trinity House
s.art043
Crown Rights
s.art044
Procedure in relation to certain approvals
s.art045
Certification of plans etc.
s.art046
Service of notices
s.art047
Arbitration
s.art048
Funding for compulsory acquisition compensation
Schedules
Schedules
7 of 520 shown
s.sch011
(1) A marine method statement must be submitted to the...
Regulated
- Submit marine method statement and obtain MMO approval before starting licensed worksStatutory Undertaker
s.sch012
(1) Subject to sub-paragraphs (2) to (4), if as the...
Regulated
- Pay costs and compensation for damage to operator's electronic communications apparatusStatutory Undertaker
s.sch012
Insurance
Regulated
- Obtain and maintain insurance for works affecting SABICContractor
s.sch012
Removal of apparatus
Regulated
- Do not remove existing apparatus until alternative is operational (Net Zero Teesside)Statutory Undertaker
s.sch012
Insurance
Regulated
- Obtain and maintain insurance for works on the Sembcorp Protection CorridorContractor
s.sch012
Expenses
Regulated
- Pay reasonable expenses incurred by apparatus owners and SembcorpStatutory Undertaker
s.sch012
Insurance
Regulated
- Obtain and maintain insurance for works affecting HPUStatutory Undertaker
513 other schedules
s.sch002
Commencement of the authorised development
s.sch002
Fire prevention
s.sch002
Surface and foul water drainage
s.sch002
Flood risk mitigation
s.sch002
Contaminated land and groundwater
s.sch002
Archaeology
s.sch002
Protected species
s.sch002
Construction environmental management plan
s.sch002
Protection of highway surfaces
s.sch002
Construction traffic management plan
s.sch002
Construction workers travel plan
s.sch002
Notice of start and completion of commissioning
s.sch002
Construction hours
s.sch002
Control of noise - construction
s.sch002
Control of noise - operation
s.sch002
Piling and penetrative foundation design
s.sch002
Waste management on site - construction wastes
s.sch002
Restoration of land used temporarily for construction
s.sch002
Combined heat and power
s.sch002
Aviation warning lighting
s.sch002
Air safety
s.sch002
Local liaison group
s.sch002
Detailed design
s.sch002
Employment, skills and training plan
s.sch002
Carbon dioxide capture transfer and storage
s.sch002
Decommissioning
s.sch002
Requirement for written approval
s.sch002
Approved details and amendments to them
s.sch002
Amendments agreed by the relevant planning authority
s.sch002
Consultation with South Tees Development Corporation
s.sch002
Effluent nutrient nitrogen safeguarding scheme
s.sch002
Consultation with Sembcorp and TG entities
s.sch002
Landscape and biodiversity protection management and enhancement
s.sch002
Public rights of way and access land management
s.sch002
External lighting
s.sch002
Highway accesses
s.sch002
Means of enclosure
s.sch002
Site security
s.sch003
The York Potash Harbour Facilities Order 2016 is amended as...
s.sch003
In article 34 (protection of interests), for “11” substitute “12”....
s.sch003
After Schedule 11 insert new Schedule 12— SCHEDULE 12 FOR...
s.sch007
Interpretation
s.sch008
The enactments for the time being in force with respect...
s.sch008
(1) Without limitation to the scope of paragraph 1, the...
s.sch008
(1) Without limitation on the scope of paragraph 1, the...
s.sch008
Part 1 (compulsory purchase under Acquisition of Land Act 1946)...
s.sch008
(1) The modifications referred to in paragraph 4(a) are as...
s.sch010
(1) In this licence— “the 2004 Act” means the Energy...
s.sch010
Notifications and Inspections
s.sch010
Pre-construction
s.sch010
(1) The relevant undertaker must submit a CEMP covering the...
s.sch010
(1) A marine method statement must be submitted to the...
s.sch010
Reporting of engaged agents, contractors and vessels
s.sch010
Written scheme of archaeological investigation
s.sch010
Construction, Operation and Maintenance
s.sch010
The storage, handling, transport and use of fuels, lubricants, chemicals...
s.sch010
The relevant undertaker must— (a) not discharge waste concrete slurry...
s.sch010
During licensed activities all wastes must be stored in designated...
s.sch010
Details of licensed activities
s.sch010
(1) Vibratory or drilled “pin” piling must be used as...
s.sch010
(1) In the event that any rock material is misplaced...
s.sch010
UXO Clearance
s.sch010
Post Construction
s.sch010
Disposal
s.sch010
The relevant undertaker must ensure dredge arisings are disposed of...
s.sch010
The material to be disposed of within the disposal site...
s.sch010
The combined total volume of material for disposal at each...
s.sch010
Provision of Information
s.sch010
Amendments to plans etc.
s.sch010
The relevant undertaker may engage in the licensed activities related...
s.sch010
Maximum parameters
s.sch010
Safety Management
s.sch010
Provision of Information
s.sch010
The coordinates for the disposal sites notified to the MMO...
s.sch010
The coordinates in Table 9 and Table 10 are defined...
s.sch010
This licence remains in force until the authorised development has...
s.sch010
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch010
With respect to any condition which requires the licensed activities...
s.sch010
General
s.sch011
(1) In this licence— “the 2004 Act” means the Energy...
s.sch011
Notifications and Inspections
s.sch011
Pre-construction
s.sch011
(1) The relevant undertaker must submit a CEMP covering the...
s.sch011
Reporting of engaged agents, contractors and vessels
s.sch011
Written scheme of archaeological investigation
s.sch011
Construction, Operation and Maintenance
s.sch011
The storage, handling, transport and use of fuels, lubricants, chemicals...
s.sch011
The relevant undertaker must— (a) not discharge waste concrete slurry...
s.sch011
During licensed activities all wastes must be stored in designated...
s.sch011
Details of licensed activities
s.sch011
(1) Vibratory or drilled “pin” piling must be used as...
s.sch011
(1) In the event that any rock material is misplaced...
s.sch011
UXO Clearance
s.sch011
Post Construction
s.sch011
Disposal
s.sch011
The relevant undertaker must ensure that only inert material of...
s.sch011
The material to be disposed of within the disposal site...
s.sch011
The volume of material for disposal at each of the...
s.sch011
Provision of Information
s.sch011
Amendments to plans etc.
s.sch011
The relevant undertaker may engage in the licensed activities related...
s.sch011
Maximum parameters
s.sch011
Safety Management
s.sch011
Provision of Information
s.sch011
The coordinates for the disposal sites notified to the MMO...
s.sch011
The coordinates in Table 11 and Table 12 are defined...
s.sch011
This licence remains in force until the authorised development has...
s.sch011
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch011
With respect to any condition which requires the licensed activities...
s.sch011
General
s.sch012
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch012
(1) Any approval of INEOS required under paragraph 99 must...
s.sch012
Compliance with requirements, etc. applying to the INEOS operations
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
For the protection of Marlow Foods, the following provisions have...
s.sch012
In this Part of this Schedule— “Marlow Foods” means Marlow...
s.sch012
Regulation of powers
s.sch012
The undertaker must give to Marlow Foods not less than...
s.sch012
Co-operation
s.sch012
Indemnity
s.sch012
Enactments and agreements
s.sch012
Arbitration
s.sch012
The provisions of this Part of this Schedule have effect,...
s.sch012
(1) In this Part of this Schedule— “construction” includes execution,...
s.sch012
(1) Where under this Part of this Schedule Network Rail...
s.sch012
The undertaker must not under the powers of this Order...
s.sch012
(1) The undertaker must before commencing construction of any specified...
s.sch012
(1) Any specified work and any protective works to be...
s.sch012
The undertaker must— (a) at all times afford reasonable facilities...
s.sch012
Network Rail must at all times afford reasonable facilities to...
s.sch012
(1) If any permanent or temporary alterations or additions to...
s.sch012
(1) For the protection of any operator, the following provisions...
s.sch012
The undertaker must repay to Network Rail all reasonable fees,...
s.sch012
(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch012
(1) If at any time after the completion of a...
s.sch012
The undertaker must not provide any illumination or illuminated sign...
s.sch012
Any additional expenses which Network Rail may reasonably incur in...
s.sch012
(1) The undertaker must pay to Network Rail all reasonable...
s.sch012
Network Rail must, on receipt of a request from the...
s.sch012
In the assessment of any sums payable to Network Rail...
s.sch012
The undertaker and Network Rail may, subject in the case...
s.sch012
Nothing in this Order, or in any enactment incorporated with...
s.sch012
The exercise of the powers of article 33 (statutory undertakers)...
s.sch012
The undertaker must give written notice to Network Rail if...
s.sch012
The undertaker must no later than 28 days from the...
s.sch012
For the protection of Northern Powergrid (Northeast) Plc the following...
s.sch012
In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch012
This Part of this Schedule does not apply to apparatus...
s.sch012
Regardless of the temporary prohibition or restriction of use of...
s.sch012
Regardless of any provision in this Order or anything shown...
s.sch012
(1) If, in the exercise of the powers conferred by...
s.sch012
(1) Where, in accordance with the provisions of this Part...
s.sch012
(1) Not less than ninety days before starting the execution...
s.sch012
(1) Subject to the following provisions of this paragraph, the...
s.sch012
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch012
Nothing in this Part of this Schedule affects the provisions...
s.sch012
Without prejudice to the generality of the protective provisions in...
s.sch012
Northern Powergrid and the undertaker must use their reasonable endeavours...
s.sch012
Work in relation to which an estimate is submitted must...
s.sch012
If Northern Powergrid at any time becomes aware that an...
s.sch012
Northern Powergrid may from time to time and at least...
s.sch012
The undertaker is not responsible for meeting costs or expenses...
s.sch012
Any difference under the provisions of this Part of this...
s.sch012
This Part of this Schedule does not apply to—
s.sch012
Prior to carrying out any works within the Order limits...
s.sch012
For the protection of NPL, the following provisions have effect,...
s.sch012
In this Part of this Schedule— “NPL” means NPL Waste...
s.sch012
Consent under this Part
s.sch012
No works comprising any part of the authorised development which...
s.sch012
Any approval of NPL required under paragraph 153 must not...
s.sch012
(1) The authorised development must be carried out in accordance...
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
For the protection of PD Teesport, the following provisions have...
s.sch012
Nothing in this Part affects the provisions of any enactment...
s.sch012
In this Part of this Schedule— “PD Teesport” means PD...
s.sch012
Regulation of powers
s.sch012
Any approval of PD Teesport required under paragraph 160 must...
s.sch012
Regulation of powers in relation to Seal Sands Road
s.sch012
Regulation of powers in relation to South Gare Road
s.sch012
Consent under this Part
s.sch012
No works comprising any part of the authorised development which...
s.sch012
Any approval of PD Teesport required under paragraph 165 must...
s.sch012
The authorised development must be carried out in accordance with...
s.sch012
Where there has been a reference to an arbitrator in...
s.sch012
Application
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
For the protection of RBT, the following provisions have effect,...
s.sch012
In this Part of this Schedule— “apparatus” means any mains,...
s.sch012
Regulation of powers
s.sch012
Any approval of RBT required under paragraph 173 must not...
s.sch012
Without limiting paragraph 174, it is not reasonable for RBT...
s.sch012
Interference with Apparatus and Access
s.sch012
Consent under this Part
s.sch012
No— (a) works comprising any part of the authorised development...
s.sch012
Interpretation
s.sch012
Any approval of RBT required under paragraph 178 must not...
s.sch012
Without limiting paragraph 179, it is not reasonable for RBT...
s.sch012
(1) The authorised development and activities on the wharf and...
s.sch012
Co-operation
s.sch012
The undertaker must pay to RBT— (a) a cost agreed...
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
Benefit of protective provisions
s.sch012
Interpretation
s.sch012
Pipeline survey
s.sch012
On Street Apparatus
s.sch012
Authorisation of works details affecting pipelines or protected crossing
s.sch012
No part of a relevant work is to be commenced...
s.sch012
(1) Any authorisation by SABIC required under paragraph 190(a) must...
s.sch012
(1) In the event that— (a) no response has been...
s.sch012
Notice of works
s.sch012
Further provisions about works
s.sch012
(1) All piling within 1.5 metres of the centreline of...
s.sch012
(1) Where excavation of trenches (including excavation by dredging) adjacent...
s.sch012
(1) Where a trench is excavated across or parallel to...
s.sch012
(1) A minimum clearance of 1500 millimetres must be maintained...
s.sch012
In this Part— “alternative apparatus” means alternative apparatus adequate to...
s.sch012
Apparatus of National Grid in streets subject to temporary stopping up
s.sch012
Monitoring for damage to pipelines
s.sch012
(1) If any damage occurs to a pipeline causing a...
s.sch012
Compliance with requirements, etc. applying to the protected land
s.sch012
Access for construction and maintenance
s.sch012
(1) In preparing a construction access plan under paragraph 202...
s.sch012
(1) No works affecting access rights over the access roads...
s.sch012
(1) If SABIC has a dispute about the proposed insurance...
s.sch012
Costs
s.sch012
Further protection in relation to the exercise of powers under the Order
s.sch012
Protective works to buildings
s.sch012
The undertaker, must when requested to do so by SABIC,...
s.sch012
Prior to the commencement of the authorised development the undertaker...
s.sch012
Arbitration
s.sch012
Extent of this Part
s.sch012
Interpretation of this Part
s.sch012
Separate approvals by third party owners or operators
s.sch012
Alternative apparatus
s.sch012
Consent under this Part in connection with Sembcorp operations
s.sch012
The works referred to in paragraph 217 must not be...
s.sch012
Removal of apparatus
s.sch012
Any approval of Sembcorp required under paragraph 218 must not...
s.sch012
(1) The authorised development must be carried out in accordance...
s.sch012
Indemnity
s.sch012
Participation in community groups
s.sch012
Notice of start and completion of commissioning
s.sch012
Arbitration
s.sch012
Additional Agreement
s.sch012
Interpretation
s.sch012
Facilities and rights for alternative apparatus
s.sch012
The following definitions apply in this Part of this Schedule—...
s.sch012
Consent to works in the shared area
s.sch012
Co-operation
s.sch012
Regulation of works within the shared area
s.sch012
Regulation of powers over the shared area
s.sch012
Constructability Principles
s.sch012
Interface Design Process
s.sch012
Design Principles
s.sch012
Maintenance and Operational Principles
s.sch012
Miscellaneous provisions
s.sch012
Retained apparatus
s.sch012
Indemnity
s.sch012
Dispute Resolution
s.sch012
Any difference in relation to the provisions in this Part...
s.sch012
The fees of the expert appointed pursuant to paragraph 241(b)...
s.sch012
Where appointed pursuant to paragraph 241(b), the expert must—
s.sch012
The expert must consider where relevant— (a) the development outcomes...
s.sch012
Any determination by the expert is final and binding which...
s.sch012
For the protection of Suez, the following provisions have effect,...
s.sch012
In this Part of this Schedule— “the respective authorised developments”...
s.sch012
Consent under this Part
s.sch012
Expenses
s.sch012
Before commencing any part of the authorised development which would...
s.sch012
No works comprising any part of the authorised development which...
s.sch012
Any approval of Suez required under paragraph 250 must not...
s.sch012
(1) The authorised development must be carried out in accordance...
s.sch012
Co-operation
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
For the protection of South Tees Development Corporation, Teesworks Limited...
s.sch012
(1) In this Part of this Schedule— “AIL access route...
s.sch012
Consent for works
s.sch012
Indemnity
s.sch012
No works comprising any part of the authorised development including...
s.sch012
Any approval of the Teesworks entity required under paragraph 260...
s.sch012
The authorised development must be carried out in accordance with...
s.sch012
The undertaker must not exercise the powers under Article 14...
s.sch012
Co-operation
s.sch012
The undertaker must provide the Teesworks entity with information the...
s.sch012
(1) This paragraph applies insofar as— (a) the construction of...
s.sch012
Expenses
s.sch012
Indemnity
s.sch012
Provision for diversion works
s.sch012
Enactments and agreements
s.sch012
If the undertaker intends to change the timing of the...
s.sch012
The Teesworks entity may issue a notice (a “diversion notice”)...
s.sch012
A diversion notice must set out— (a) the diversion work...
s.sch012
If a diversion notice is issued to the undertaker before...
s.sch012
In making the decision under paragraph 272 the undertaker must...
s.sch012
Where the undertaker gives an information notice to the Teesworks...
s.sch012
Where the undertaker notifies the Teesworks entity under paragraph 272(b)...
s.sch012
If the undertaker issues an information notice to the Teesworks...
s.sch012
If the Teesworks entity submits further information to the undertaker...
s.sch012
If the undertaker issues notice to the Teesworks entity under...
s.sch012
Co-operation
s.sch012
If the undertaker issues a notice under paragraph 272(a) the...
s.sch012
(1) Subject to sub-paragraphs (2) and (3), if a diversion...
s.sch012
If a reference is made to arbitration under paragraph 285...
s.sch012
Where the arbitrator determines that the terms of the diversion...
s.sch012
If— (a) a diversion works agreement is entered into within...
s.sch012
(1) If— (a) no diversion notice is issued by the...
s.sch012
Arbitration
s.sch012
Interpretation
s.sch012
Where a notice or information is provided by the undertaker...
s.sch012
For the protection of the Breagh Pipeline Owners, the following...
s.sch012
Access
s.sch012
In this Part of this Schedule— “Breagh Pipeline” means the...
s.sch012
Consent under this Part
s.sch012
No works comprising any part of the authorised development which...
s.sch012
(1) Any approval of the Breagh Pipeline Owners required under...
s.sch012
Compliance with requirements, etc. applying to the Breagh Pipeline and the Breagh Pipeline Operations
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
For the protection of Teesside Windfarm, the following provisions have...
s.sch012
In this Part of this Schedule— “restricted works” means works...
s.sch012
Consent under this Part
s.sch012
Precedence of the 1991 Act in respect of apparatus in the streets
s.sch012
Arbitration
s.sch012
Particularly in respect of the restricted works, the undertaker must...
s.sch012
No works comprising any part of the authorised development which...
s.sch012
Any approval of Teesside Windfarm required under paragraph 300 must...
s.sch012
(1) The authorised development must be carried out in accordance...
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
Benefit of protective provisions
s.sch012
Interpretation
s.sch012
Pipeline survey
s.sch012
Authorisation of works details affecting pipelines or protected crossing
s.sch012
Notices
s.sch012
No part of a relevant work is to be commenced...
s.sch012
(1) Any authorisation by HPU required under paragraph 309(a) must...
s.sch012
(1) In the event that— (a) no response has been...
s.sch012
Notice of works
s.sch012
Further provisions about works
s.sch012
(1) All piling within 1.5 metres of the centreline of...
s.sch012
(1) Where excavation of trenches (including excavation by dredging) adjacent...
s.sch012
(1) Where a trench is excavated across or parallel to...
s.sch012
(1) A minimum clearance of 1500 millimetres must be maintained...
s.sch012
Monitoring for damage to pipelines
s.sch012
Application
s.sch012
(1) If any damage occurs to a pipeline causing a...
s.sch012
Compliance with requirements, etc. applying to the protected land
s.sch012
Access for construction and maintenance
s.sch012
(1) In preparing a construction access plan under paragraph 321...
s.sch012
(1) No works affecting access rights over the access roads...
s.sch012
If HPU has a dispute about the proposed insurance (including...
s.sch012
Costs
s.sch012
Further protection in relation to the exercise of powers under the Order
s.sch012
The undertaker, must when requested to do so by HPU,...
s.sch012
Interpretation
s.sch012
Prior to the commencement of the authorised development the undertaker...
s.sch012
Arbitration
s.sch012
For the protection of Navigator Terminals, the following provisions have...
s.sch012
In this Part of this Schedule— “Navigator Terminals” means Navigator...
s.sch012
Consent under this Part
s.sch012
No works comprising any part of the authorised development which...
s.sch012
Any approval of Navigator Terminals required under paragraph 334 must...
s.sch012
(1) The authorised development must be carried out with good...
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
On Street Apparatus
s.sch012
For the protection of NW, the following provisions, unless otherwise...
s.sch012
In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch012
The undertaker must not within the standard protection strips interfere...
s.sch012
The alteration, extension, removal or re-location of any apparatus shall...
s.sch012
In the situation, where in exercise of the powers conferred...
s.sch012
Regardless of any provision in this Order or anything shown...
s.sch012
If in consequence of the exercise of the powers conferred...
s.sch012
If in consequence of the exercise of the powers conferred...
s.sch012
(1) Subject to sub-paragraphs (2) and (3), if for any...
s.sch012
Any dispute arising between the undertaker and NW under this...
s.sch012
Apparatus of National Gas in streets subject to temporary stopping up
s.sch012
(1) Where in consequence of the proposed construction of any...
s.sch012
Prior to carrying out any works within the Order Limits...
s.sch012
Application
s.sch012
Interpretation
s.sch012
Except for paragraphs 354 (apparatus of statutory undertaker in stopped...
s.sch012
Apparatus of statutory undertaker in stopped up streets
s.sch012
Acquisition of land
s.sch012
Removal or diversion of apparatus
s.sch012
Facilities and rights for alternative apparatus
s.sch012
Retained apparatus: protection
s.sch012
Protective works to buildings
s.sch012
Expenses
s.sch012
Indemnity
s.sch012
Enactments and agreements
s.sch012
Co-operation
s.sch012
Access
s.sch012
Arbitration
s.sch012
Works falling outside of development authorised by the Order
s.sch012
Cathodic protection testing
s.sch012
For the protection of the NT Group (as defined below),...
s.sch012
In this Part of this Schedule— “NTL” means North Tees...
s.sch012
Removal of apparatus
s.sch012
Consent under this Part
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
Apparatus
s.sch012
For the protection of TGLP, TGPP and NGPL, the following...
s.sch012
In this Part of this Schedule— “alternate access agreement” means...
s.sch012
No relevant works are to be commenced until the design...
s.sch012
Following approval or deemed approval of the design package, the...
s.sch012
The undertaker will design and carry out or will procure...
s.sch012
Facilities and rights for alternative apparatus
s.sch012
Retained apparatus
s.sch012
Approval Principles: Relevant Works Package A
s.sch012
Subject to paragraph 393, below, it shall be reasonable for...
s.sch012
It will be unreasonable for the NSMP entity to withhold...
s.sch012
The undertaker and the NSMP entity must, in carrying out...
s.sch012
Approval Principles: Relevant Works Package B
s.sch012
The undertaker and the NSMP entity must, in carrying out...
s.sch012
Compliance with requirements, etc. applying to the NSMP operations
s.sch012
In undertaking any works in relation to the NSMP operations...
s.sch012
For the benefit of NSMP, the undertaker must not exercise...
s.sch012
Regardless of the temporary prohibition or restriction of use of...
s.sch012
Expenses
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
Access to plots 110, 112, 113 or 114
s.sch012
The undertaker must not use plots 103 or 108 to...
s.sch012
Where an alternate access agreement has been concluded, reference to...
s.sch012
Indemnity
s.sch012
Enactments and agreements
s.sch012
Co-operation
s.sch012
Access
s.sch012
Arbitration
s.sch012
Notices
s.sch012
For the protection of Air Products the following provisions have...
s.sch012
In this Part— “Air Products” means Air Products Public Limited...
s.sch012
Precedence of the 1991 Act in respect of apparatus in streets
s.sch012
No acquisition etc. except by agreement
s.sch012
Regardless of the temporary prohibition or restriction of use of...
s.sch012
No acquisition etc. except by agreement
s.sch012
Removal of apparatus
s.sch012
Facilities and rights for alternative apparatus
s.sch012
Retained Apparatus
s.sch012
Expenses and costs
s.sch012
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch012
Enactments and agreements
s.sch012
For the protection of CATS, the following provisions have effect,...
s.sch012
In this Part of this Schedule— “CATS” means CATS North...
s.sch012
Removal of apparatus
s.sch012
Consent under this Part
s.sch012
No works comprising any part of the authorised development within...
s.sch012
(1) Any approval of CATS required under paragraph 61 must...
s.sch012
Where formal consent is required under the CATS requirements for...
s.sch012
Compliance with the CATS requirements
s.sch012
No explosives for blasting are to be used within 400...
s.sch012
Monitoring for damage to pipelines
s.sch012
(1) If any damage occurs to a CATS pipeline causing...
s.sch012
Indemnity
s.sch012
Costs
s.sch012
Facilities and rights for alternative apparatus
s.sch012
Arbitration
s.sch012
For the protection of CF Fertilisers, the following provisions have...
s.sch012
In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch012
Precedence of the 1991 Act in respect of apparatus in streets
s.sch012
Regardless of the temporary prohibition or restriction of use of...
s.sch012
Removal of apparatus/access
s.sch012
Facilities and rights for alternative apparatus
s.sch012
Retained Apparatus
s.sch012
Consent under this Part
s.sch012
Before commencing any part of the authorised development which would...
s.sch012
Retained Apparatus
s.sch012
No works comprising any part of the authorised development which...
s.sch012
Any approval of CF Fertilisers required under paragraph 80 must...
s.sch012
(1) The authorised development must be carried out in accordance...
s.sch012
Notices
s.sch012
Co-operation
s.sch012
Expenses and costs
s.sch012
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch012
Arbitration
s.sch012
For the protection of Exolum, the following provisions have effect,...
s.sch012
In this Part of this Schedule— “Exolum” means Exolum Seal...
s.sch012
Expenses and costs
s.sch012
Consent of restricted works under this Part
s.sch012
Prohibition of acquisition and interference
s.sch012
Cathodic protection testing
s.sch012
Expenses
s.sch012
Indemnity
s.sch012
Arbitration
s.sch012
For the protection of INEOS, the following provisions have effect,...
s.sch012
In this Part of this Schedule— “INEOS” means INEOS Nitriles...
s.sch012
Consent under this Part
s.sch012
No works comprising any part of the authorised development which...
s.sch012
This Part A sets out the approval process to be...
s.sch012
The undertaker shall submit the design package to the NSMP...
s.sch012
Following submission of the design package to the NSMP entity,...
s.sch012
In the event the NSMP entity does not provide any...
s.sch012
Once approved, the undertaker shall issue one paper copy and...
s.sch012
With respect to the relevant works package A, the undertaker...
s.sch012
This Part B sets out the approval process to be...
s.sch012
The undertaker shall submit any such change required to the...
s.sch012
Following submission of the change request to the NSMP entity,...
s.sch012
In the event the NSMP entity does not provide a...
s.sch012
Once approved, the undertaker shall issue one (1) paper copy...
s.sch012
Any approval of the NSMP entity required under Part A...
s.sch013
In this Schedule— “requirement consultee” means any body named in...
s.sch013
Applications made under a Requirement
s.sch013
Further information and consultation
s.sch013
Fees
s.sch013
Appeals
s.schedule/12/part/28/paragraph/1
Approval Process
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.