UK Statutory Instrument SI 2017/766 United Kingdom

The Wrexham Gas Fired Generating Station Order 2017

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker2 Operator1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts
Operator — also bound by 746 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art016 Authority to survey and investigate the land Regulated
  • Give 14 days’ notice and obtain consents before surveying landStatutory Undertaker
38 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Maintenance of authorised development
s.art005 Operation of authorised development
s.art006 Benefit of this Order
s.art007 Consent to transfer benefit of this Order
s.art008 Defence to proceedings in respect of statutory nuisance
s.art009 Power to alter layout, etc. of streets
s.art010 Street works
s.art011 Temporary prohibition or restriction of use of streets
s.art012 Access to works
s.art013 Agreements with street authorities
s.art014 Traffic Regulation
s.art015 Discharge of water
s.art017 Compulsory acquisition of land
s.art018 Compulsory acquisition of rights etc
s.art019 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art020 Time limit for exercise of authority to acquire land compulsorily
s.art021 Statutory authority to override easements and other rights
s.art022 Acquisition of subsoil only
s.art023 Application of Part 1 of the Compulsory Purchase Act 1965
s.art024 Private rights
s.art025 Rights under or over streets
s.art026 Temporary use of land for carrying out the authorised development
s.art027 Temporary use of land for maintaining the authorised development
s.art028 Statutory Undertakers
s.art029 Apparatus and rights of statutory undertakers in streets
s.art030 Recovery of costs of new connection
s.art031 Felling or lopping of trees and removal of hedgerows
s.art032 Application of landlord and tenant law
s.art033 Operational land for purposes of the 1990 Act
s.art034 Protective provisions
s.art035 Certification of plans etc.
s.art036 Service of notices
s.art037 Procedure in relation to certain approvals
s.art038 Arbitration
s.art039 Funding
Schedules

Schedules

2 of 108 shown
s.sch009 Protection of DCC apparatus Regulated
  • Notify DCC and get approval before working near their apparatusStatutory Undertaker
s.sch009 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Notify undertaker of claims and do not settle without consentOperator
106 other schedules
s.sch003 Time limits
s.sch003 Travel plan during operational phase
s.sch003 Construction hours
s.sch003 Foul and surface water drainage
s.sch003 Artificial lighting
s.sch003 Local economic benefit
s.sch003 Amendments to approved details
s.sch003 Combined heat and power
s.sch003 Decommissioning strategy
s.sch003 Requirements for written approval, etc.
s.sch003 Date of final commissioning and cessation
s.sch003 Detailed design approval
s.sch003 Provision of and implementation and maintenance of landscaping and ecological mitigation
s.sch003 Construction and Environment Management Plan
s.sch003 Ground investigation
s.sch003 Piling
s.sch003 Fencing and other means of enclosure
s.sch003 Archaeology
s.sch003 Construction traffic management plan
s.sch007 The enactments for the time being in force with respect...
s.sch007 (1) Without prejudice to the generality of paragraph 1, the...
s.sch007 (1) Without limitation on the scope of paragraph 1, the...
s.sch007 (1) For the purposes of Article 18 only the 1965...
s.sch007 The following provisions of the 1965 Act (which state the...
s.sch007 Section 11 of the 1965 Act (powers of entry) is...
s.sch007 Section 20 of the 1965 Act (protection for interests of...
s.sch007 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch007 For Schedule 2A to the 1965 Act substitute— SCHEDULE2A COUNTER-NOTICE...
s.sch009 Application
s.sch009 Enactments and agreements
s.sch009 Co-operation
s.sch009 Access
s.sch009 Arbitration
s.sch009 (1) For the protection of BT Group Plc the following...
s.sch009 (1) Subject to sub-paragraphs (2) to (4), if as the...
s.sch009 This part of this Schedule does not apply to—
s.sch009 Nothing in this part of this Schedule affects the provisions...
s.sch009 The undertaker must not enter into any underground structures owned...
s.sch009 The undertaker must confirm the location and nature of works...
s.sch009 Interpretation
s.sch009 Prior to any works commencing or the moving of heavy...
s.sch009 In the event that any BT apparatus within or immediately...
s.sch009 In the event that works undertaken by the undertaker pursuant...
s.sch009 Where the BT apparatus map(s) show(s) BT apparatus within or...
s.sch009 Protection measures for BT apparatus within or immediately adjacent to...
s.sch009 Prior written notice must be provided to Click Before You...
s.sch009 All excavation works undertaken by the undertaker immediately adjacent to...
s.sch009 To prevent any movement of BT apparatus within or immediately...
s.sch009 The undertaker must notify Click Before You Dig in advance...
s.sch009 The undertaker will keep clear and unobstructed access to BT...
s.sch009 Apparatus of National Grid in streets subject to temporary prohibition or restriction
s.sch009 In the event of any damage to BT apparatus, the...
s.sch009 For the protection of DCC referred to in this Part...
s.sch009 In this Part of this Schedule— “acceptable insurance” means a...
s.sch009 (1) Regardless of any provision in this Order or anything...
s.sch009 Precedence of the WIA 1991
s.sch009 Suspension of works
s.sch009 (1) In the event that either the undertaker or DCC...
s.sch009 Emergency Works
s.sch009 Insurance
s.sch009 Acquisition of land
s.sch009 Damage to DCC apparatus
s.sch009 (1) For the protection of any operator referred to in...
s.sch009 This part of this Schedule does not apply to—
s.sch009 Nothing in this part of this Schedule affects the provisions...
s.sch009 Application
s.sch009 Interpretation
s.sch009 Precedence of 1991 Act in respect of apparatus in streets
s.sch009 Apparatus in streets subject to temporary prohibition or restriction
s.sch009 No acquisition etc. except by agreement
s.sch009 Removal of apparatus
s.sch009 Removal of apparatus
s.sch009 Facilities and rights for alternative apparatus
s.sch009 (1) Not less than 28 days before starting the execution...
s.sch009 (1) Subject to the following provisions of this paragraph, the...
s.sch009 Expenses and costs
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 Application
s.sch009 Interpretation
s.sch009 Precedence of 1991 Act in respect of apparatus in streets
s.sch009 Apparatus in streets subject to temporary prohibition or restriction
s.sch009 Facilities and rights for alternative apparatus
s.sch009 No acquisition etc. except by agreement
s.sch009 Removal of apparatus
s.sch009 Facilities and rights for alternative apparatus
s.sch009 Retained apparatus
s.sch009 Expenses and costs
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 Enactments and agreements
s.sch009 Application
s.sch009 Interpretation
s.sch009 Removal of apparatus
s.sch009 Retained apparatus: protection of National Grid as Gas Undertaker
s.sch009 Retained apparatus
s.sch009 Expenses and costs
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 Co-operation
s.sch009 Arbitration
s.sch009 Enactments and agreements
s.sch009 Compulsory acquisition and temporary use
s.sch009 Expenses
s.sch009 Indemnity
s.sch010 (1) Where an application has been made to the relevant...
s.sch010 Further information
s.sch010 Appeals
s.sch010 In this Schedule “relevant authority” means the relevant planning authority,...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.