Business-side roles with duties under this instrument.
Trader18
Statutory Undertaker2
Any Person1
Plus 4 duties on the regulator, Crown ministers and public bodies — folded into the section list below.
Other Acts binding the same actors
If a role above is yours, these are the other instruments that most often bind it.
Trader — also bound by 825 other Acts
Value Added Tax Regulations 1995
416 duties
Companies Act 2006
243 duties
Companies Act 1985
85 duties
Statutory Undertaker — also bound by 179 other Acts
The Cory Decarbonisation Project Order 2025
120 duties
Water Industry Act 1991
53 duties
Any Person — also bound by 2340 other Acts
Human Medicines Regulations 2012
184 duties
Merchant Shipping Act 1995
144 duties
Insolvency (England and Wales) Rules 2016
104 duties
Communications Act 2003
92 duties
Road Traffic Act 1988
92 duties
What it requires
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
s.art008
Stopping up of streets
Regulated
Other duties (1) — Crown / regulator
- Pay compensation for loss of private right of wayLocal authority
s.art014
Protective works to buildings
Regulated
- Company may enter buildings and carry out protective works for Victoria Station upgradeTrader
s.art025
Temporary use of land for maintenance of works
Regulated
- Comply with conditions for temporary land possession during maintenanceTrader
s.art028
Acquisition of part of certain properties
Regulated
- Serve counter-notice if you object to selling part of your propertyAny Person
s.art034
Traffic regulation
Regulated
- Notify police and traffic authority before imposing traffic restrictions for construction worksTrader
s.art039
Certification of plans, etc.
Regulated
- Submit plans and book of reference to Secretary of State for certificationTrader
36 other provisions — procedural and definitional
s.art001
Citation and commencement
s.art002
Interpretation
s.art003
Application of the
s.art004
Power to construct and maintain works
s.art005
Power to deviate
s.art006
Power to alter layout,
s.art007
Power to execute street works
s.art009
Temporary stopping up and diversion of streets
s.art010
Access to works
s.art011
Construction and maintenance of altered or diverted streets
s.art012
Agreements with street authorities
s.art013
Discharge of water
s.art015
Planning permission: supplementary matters
s.art016
Power to survey and investigate land, etc.
s.art017
Power to acquire land
s.art018
Application of Part 1 of the Compulsory Purchase Act 1965
s.art019
Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art020
Power to acquire new rights
s.art021
Powers to acquire subsoil only
s.art022
Power to acquire land limited to subsoil lying more than 4.5 metres beneath surface
s.art023
Rights under or over streets
s.art024
Temporary use of land for construction of works
s.art026
Disregard of certain interests and improvements
s.art027
Set-off for enhancement in value of retained land
s.art029
Extinction or suspension of private rights of way
s.art030
Time limit for exercise of powers of acquisition
s.art031
Statutory undertakers, etc.
s.art032
For protection of Network Rail
s.art033
For protection of specified undertakers
s.art035
Street traders
s.art036
Obstruction of construction of authorised works
s.art037
Disclosure of confidential information
s.art038
Defence to proceedings in respect of statutory nuisance
s.art040
Service of notices
s.art041
No double recovery
s.art042
Arbitration
Schedules
Schedules
19 of 72 shown
s.sch008
(1) Where a street is stopped up under article 8...
Regulated
- London Underground Company must pay utility relocation costs when streets are stopped upTrader
s.sch009
(1) The Company shall pay to Network Rail all reasonable...
Regulated
- Pay Network Rail for costs caused by construction or maintenance worksTrader
s.sch009
(1) The Company shall before commencing construction of any specified...
Regulated
- Submit construction plans for approval before starting workTrader
s.sch009
(1) Any specified work and any protective works to be...
Regulated
Other duties (1) — Crown / regulator
- The Company must construct works with due dispatch and compensate for damage to railway propertyLocal authority
s.sch009
The Company shall— (a) at all times afford reasonable facilities...
Regulated
- Provide engineer with access and information during constructionTrader
s.sch009
(1) If any permanent or temporary alterations or additions to...
Regulated
- Pay Network Rail for necessary alterations to railway property during constructionTrader
s.sch010
If the facilities and rights to be afforded by the...
Regulated
Other duties (1) — Crown / regulator
- Arbitrator must order compensation for alternative apparatus if rights differTribunal / Court
s.sch010
Not less than 56 days before commencing to construct or...
Regulated
- Submit plans for specified works at least 56 days before startingTrader
s.sch010
Where any street is stopped up under article 8 (stopping...
Regulated
- Grant legal easements to utility companies when streets are stopped upTrader
s.sch010
Where in consequence of the proposed construction of any of...
Regulated
- Cooperate with the Company on works coordinationStatutory Undertaker
s.sch010
If in consequence of the exercise of the powers conferred...
Regulated
- Provide alternative access to utilities if obstructed by worksTrader
s.sch010
Subject to the provisions of the following paragraphs of this...
Regulated
- Repay specified undertaker's reasonable expenses from worksTrader
s.sch010
If, by reason or in consequence of the construction, maintenance...
Regulated
- Repay utility damage costs and indemnify the utility companyTrader
s.sch010
The Company shall give not less than 28 days’ notice...
Regulated
- Notify utility companies 28 days before stopping up a streetTrader
s.sch010
The specified undertaker shall give to the Company reasonable notice...
Regulated
- Notify company of claims and get consent before settlingStatutory Undertaker
s.sch010
The Company shall, so far as is reasonably practicable, so...
Regulated
- Do not obstruct access to utility apparatus when carrying out protective worksTrader
s.sch010
The Company shall not, in the exercise of the powers...
Regulated
- Do not drill trial holes into utility apparatus without consentTrader
s.sch010
The Company shall not acquire any apparatus from a specified...
Regulated
Other duties (1) — Crown / regulator
- Acquire specified apparatus only by agreement, not unreasonably withheldStatutory regulator
s.sch010
The Company shall, if it is practicable to do so,...
Regulated
- Provide rights and facilities for alternative apparatus to specified undertakerTrader
53 other schedules
s.sch005
The enactments for the time being in force with respect...
s.sch005
(1) Without prejudice to the generality of paragraph 1, the...
s.sch005
(1) The 1965 Act shall have effect with the modifications...
s.sch005
For section 7 of the 1965 Act (measure of compensation)...
s.sch005
For section 8 of the 1965 Act (provisions as to...
s.sch005
The following provisions of the 1965 Act (which state the...
s.sch005
Section 11 of the 1965 Act (powers of entry) shall...
s.sch005
Section 20 of the 1965 Act (protection for interests of...
s.sch005
Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch008
(1) Subject to the following provisions of this paragraph, sections...
s.sch009
The following provisions of this Schedule shall have effect, unless...
s.sch009
The Company shall repay to Network Rail all reasonable fees,...
s.sch009
If at any time after the completion of a specified...
s.sch009
Any additional expenses which Network Rail may reasonably incur in...
s.sch009
Network Rail shall, on receipt of a request from the...
s.sch009
In the assessment of any sums payable to Network Rail...
s.sch009
The Company and Network Rail may, subject in the case...
s.sch009
The Company shall no later than 28 days from the...
s.sch009
In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
s.sch009
(1) Where under this Schedule Network Rail is required to...
s.sch009
(1) The Company shall not exercise the powers conferred by...
s.sch009
Network Rail shall at all times afford reasonable facilities to...
s.sch010
In this Schedule— “apparatus” means— in the case of a...
s.sch010
The obligation imposed upon the specified undertaker by paragraph 9...
s.sch010
Any alternative apparatus to be constructed by the specified undertaker...
s.sch010
The specified undertaker shall, after the manner of construction and...
s.sch010
Paragraphs 14 to 16 apply to so much of the...
s.sch010
If the Company gives notice in writing to the specified...
s.sch010
In carrying out any work under paragraph 14 the Company...
s.sch010
Nothing in paragraph 14 shall authorise the Company to carry...
s.sch010
Where, in accordance with the provisions of this Schedule, the...
s.sch010
In determining the terms and conditions mentioned in paragraph 17...
s.sch010
Paragraphs 1(1) and 2 of Schedule 8 (provisions relating to...
s.sch010
In relation to a work which is a specified work...
s.sch010
The Company shall not commence the construction or renewal of...
s.sch010
Any approval of the specified undertaker required under paragraph 22—...
s.sch010
In relation to a work to which paragraph 21 applies,...
s.sch010
A specified work shall be constructed (and in the case...
s.sch010
If within 42 days after the submission to it of...
s.sch010
Nothing in paragraph 20 or 26 shall preclude the Company...
s.sch010
The Company shall not be required to comply with paragraph...
s.sch010
Nothing in paragraph 28 shall entitle the Company to carry...
s.sch010
There shall be deducted from any sum payable under paragraph...
s.sch010
If in pursuance of the provisions of this Schedule—
s.sch010
For the purposes of paragraph 34— (a) an extension of...
s.sch010
An amount which apart from this paragraph would be payable...
s.sch010
In any case where work is carried out by the...
s.sch010
Nothing in paragraph 38 shall impose any liability on the...
s.sch010
Any difference arising between the Company and a specified undertaker...
s.sch010
Any notice in writing to be given by the Company...
s.sch010
This Schedule shall not apply to anything done or proposed...
s.sch010
The Company may in exercise of the powers conferred by...
s.sch010
Paragraphs 9 to 12 apply where— (a) the Company requires...
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.