Welsh Statutory Instrument 2004 United Kingdom

The Scarweather Sands Offshore Wind Farm Order 2004

At a glance

What's here

1 compliance obligation

Who this Act binds

Business-side actors with duties under this Act, ranked by how often they appear.

  • Statutory Undertaker 1

Other Acts binding the same actors

For each actor bound by this Act, the other UK Acts that bind them most often. Useful for understanding the full compliance landscape facing each role.

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

Browse 32 other Schedules — structural / supplementary
s.sch001

The works which the undertaker is authorised to construct and...

s.sch001

In this Schedule, references to the locations of a wind...

s.sch003

The enactments for the time being in force with respect...

s.sch003

(1) Without prejudice to the generality of paragraph 1, the...

s.sch003

Adaptation of the 1965 Act

s.sch003

For section 7 of the 1965 Act (measure of compensation),...

s.sch003

For section 8 of the 1965 Act (which relates to...

s.sch003

The following provisions of the 1965 Act (which state the...

s.sch003

Section 11 of the 1965 Act (powers of entry) is...

s.sch003

Section 20 of the 1965 Act (protection for interests of...

s.sch003

Section 22 of the 1965 Act (interests omitted from purchase)...

s.sch004

(1) Sections 271 to 274 of the 1990 Act (power...

s.sch004

The powers conferred by this Order do not extend to...

s.sch005

(1) For the protection of the Environment Agency (in this...

s.sch006

(1) The following provisions of this Schedule have effect unless...

s.sch006

The undertaker must secure that any relevant work, other than...

s.sch006

If— (a) any alterations or additions, either permanent or temporary,...

s.sch006

The undertaker must pay to Network Rail a sum equivalent...

s.sch006

(1) As soon as reasonably practicable following completion of the...

s.sch006

(1) Subject to sub-paragraph (2), the undertaker must pay to...

s.sch006

(1) The undertaker must pay to Network Rail a sum...

s.sch006

(1) The sums payable by the undertaker under paragraph 15...

s.sch006

In the assessment of any sums payable under this Schedule,...

s.sch006

(1) Where, under this Schedule, Network Rail is required to...

s.sch006

(1) The undertaker must not, in the exercise of the...

s.sch006

(1) The undertaker must, before commencing construction of any relevant...

s.sch006

(1) If Network Rail reasonably considers that any relevant work...

s.sch006

(1) When signifying approval of the plans of any relevant...

s.sch006

(1) Any relevant work must, when commenced, be constructed—

s.sch006

The undertaker must— (a) at all times afford reasonable facilities...

s.sch006

Network Rail must— (a) at all times afford reasonable facilities...

s.sch006

Where so required by the engineer the undertaker must, to...

s.art007

Power to survey and investigate land

  • Notify landowners before entering land for surveys or trial holes Statutory Undertaker
Browse 38 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Power to construct and maintain works

s.art004

Power to deviate

s.art005

Power to execute street works

s.art006

Temporary stopping up of streets

s.art008

Tidal works not to be executed without approval of the Secretary of State

s.art009

Provision against danger to navigation

s.art010

Abatement of works abandoned or decayed

s.art011

Survey of tidal works

s.art012

Permanent lights, navigational safety aids and colour

s.art013

Lights on tidal works during construction

s.art014

Active safety management system

s.art015

Construction and operational noise

s.art016

Execution by Secretary of State of works in default

s.art017

Offences

s.art018

Power to acquire land

s.art019

Application of Part I of the Compulsory Purchase Act 1965

s.art020

Power to acquire new rights

s.art021

Temporary use of land for construction of works

s.art022

Disregard of certain interests and improvements

s.art023

Extinction or suspension of private rights of way

s.art024

Time limit for exercise of powers of acquisition

s.art025

Power to operate and use works

s.art026

Dis-application of sections 36 and 37 of the Electricity Act 1989

s.art027

Obstruction and misuse of authorised works

s.art028

Safety zones for navigation, trawling and anchoring

s.art029

Certain land to be treated as operational land

s.art030

Statutory undertakers, etc.

s.art031

For protection of Environment Agency

s.art032

For protection of Network Rail

s.art033

Compensation for fishermen

s.art034

Certification of plans, etc.

s.art035

Service of notices

s.art036

No double recovery

s.art037

Transfer of powers

s.art038

Crown rights

s.art039

Arbitration

Explore more

Browse legislation

Find other UK business legislation with related guidance.