Business-side roles with duties under this instrument.
Statutory Undertaker1
Other Acts binding the same actors
If a role above is yours, these are the other instruments that most often bind it.
Statutory Undertaker — also bound by 179 other Acts
The Cory Decarbonisation Project Order 2025
120 duties
Water Industry Act 1991
53 duties
What it requires
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
48 other provisions — procedural and definitional
s.art001
Citation and commencement
s.art002
Interpretation
s.art003
Development consent etc. granted by the Order
s.art004
Power to maintain the authorised project
s.art005
Benefit of the Order
s.art006
Application and modification of legislative provisions
s.art007
Defence to proceedings in respect of statutory nuisance
s.art008
Street works
s.art009
Application of the 1991 Act
s.art010
Temporary closure of public rights of way
s.art011
Temporary closure of streets
s.art012
Access to works
s.art013
Agreements with street authorities
s.art014
Power to alter layout etc. of streets
s.art015
Traffic Regulation
s.art016
Discharge of water
s.art017
Authority to survey and investigate the land onshore
s.art018
Compulsory acquisition of land
s.art019
Time limit for exercise of authority to acquire land compulsorily
s.art020
Compulsory acquisition of rights
s.art021
Private rights
s.art022
Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art023
Modification of Part 1 of the Compulsory Purchase Act 1965
s.art024
Acquisition of subsoil or airspace only
s.art025
Rights under or over streets
s.art026
Temporary use of land for carrying out the authorised project
s.art027
Temporary use of land for maintaining authorised project
s.art028
Statutory undertakers
s.art029
Recovery of costs of new connections
s.art030
Operation of generating station
s.art031
Deemed marine licences under the 2009 Act
s.art032
Application of landlord and tenant law
s.art033
Amendment of local legislation
s.art034
Operational land for purposes of the 1990 Act
s.art035
Felling or lopping of trees and removal of hedgerows
s.art036
Trees subject to tree preservation orders
s.art037
Protective provisions
s.art038
Arbitration
s.art039
Requirements, appeals, etc.
s.art040
Certification of plans etc.
s.art041
Abatement of works abandoned or decayed
s.art042
Saving provisions for Trinity House
s.art043
Crown rights
s.art044
Funding
s.art045
Compensation provisions
s.art046
Service of notices
s.art047
Transfer of functions of the relevant local planning authority
s.art048
No double recovery
Schedules
Schedules
1 of 434 shown
s.sch018
(1) Subject to sub-paragraphs (2) to (4), if as the...
Regulated
- Compensate telecoms operators for damage or service interruption caused by the wind farm worksStatutory Undertaker
433 other schedules
s.sch001
A nationally significant infrastructure project as defined in sections 14...
s.sch001
Offshore decommissioning
s.sch001
Stages of authorised project onshore
s.sch001
Detailed onshore design parameters
s.sch001
Provision of landscaping
s.sch001
Implementation and maintenance of landscaping
s.sch001
Ecological management plan
s.sch001
Fencing and other means of permanent enclosure
s.sch001
Temporary fencing and other temporary means of enclosure
s.sch001
Operational drainage management and emergency flood response
s.sch001
Contaminated land and groundwater
s.sch001
The grid coordinates for that part of the authorised project...
s.sch001
Onshore archaeology
s.sch001
Code of construction practice
s.sch001
Construction hours
s.sch001
Highway accesses
s.sch001
Traffic
s.sch001
Public rights of way
s.sch001
Restoration of land used temporarily for construction
s.sch001
Onshore decommissioning
s.sch001
Control of noise during operational phase
s.sch001
Control of artificial light emissions during operational phase
s.sch001
Works within the Order limits which have been subject to...
s.sch001
Aviation Lighting
s.sch001
Requirement for written approval
s.sch001
Amendments to approved details
s.sch001
Skills, supply chain and employment
s.sch001
Cromer and Claxby Radar Mitigation
s.sch001
Ministry of Defence Surveillance Operation
s.sch001
Biodiversity Net Gain
s.sch001
Wake Effects
s.sch001
Time limits
s.sch001
Detailed offshore design parameters
s.sch001
(1) The total number of offshore electrical installations and offshore...
s.sch001
(1) The maximum number of gravity base structure foundations must...
s.sch001
The total volume of scour protection for wind turbine generators,...
s.sch001
(1) In respect of the offshore export cables comprised within...
s.sch008
Compensation enactments
s.sch008
For Schedule 2A to the 1965 Act substitute— SCHEDULE2A Counter-notice...
s.sch008
(1) Without prejudice to the generality of paragraph 1, the...
s.sch008
(1) Without limitation on the scope of paragraph 1, the...
s.sch008
Application of the 1965 Act
s.sch008
For section 7 of the 1965 Act (measure of compensation...
s.sch008
The following provisions of the 1965 Act (which state the...
s.sch008
are so modified as to secure that, as against persons...
s.sch008
Section 20 of the 1965 Act (tenants at will, etc.)...
s.sch008
Section 22 of the 1965 Act (interests omitted from purchase)...
s.sch010
(1) In this licence— “the 2004 Act” means the Energy...
s.sch010
Design parameters
s.sch010
(1) The total number of offshore accommodation platforms forming part...
s.sch010
(1) The total length of the cables forming part of...
s.sch010
Maintenance of the authorised scheme
s.sch010
Vessels under the undertaker’s control
s.sch010
Extension of time periods
s.sch010
Notification and Inspection
s.sch010
Aids to navigation
s.sch010
Colouring of structures
s.sch010
Aviation safety
s.sch010
Subject to the licence conditions at Part 2, this licence...
s.sch010
Chemicals, drilling and debris
s.sch010
Notification of unauthorised deposits
s.sch010
Pre-construction plans and documentation
s.sch010
(1) Any archaeological reports produced in accordance with condition 22(1)(g)(iii)...
s.sch010
Offshore safety management
s.sch010
Reporting of engaged agents, contractors and vessels
s.sch010
Pre-construction monitoring and surveys
s.sch010
Construction monitoring
s.sch010
Post construction
s.sch010
Reporting of impact pile driving
s.sch010
Such activities are authorised in relation to the construction, maintenance...
s.sch010
Deployment of cable protection
s.sch010
Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch010
Completion of construction
s.sch010
Maintenance reporting
s.sch010
Piling restriction for spawning herring
s.sch010
The substances or articles authorised for deposit at sea are—...
s.sch010
The grid coordinates for the authorised scheme are specified below—...
s.sch010
This licence remains in force until the authorised scheme has...
s.sch010
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch010
With respect to any condition which requires the licensed activities...
s.sch010
Any amendments to the details, plan or scheme must be...
s.sch011
(1) In this licence— “the 2004 Act” means the Energy...
s.sch011
Design parameters
s.sch011
(1) Offshore accommodation platform foundation structures forming part of the...
s.sch011
(1) The total length of the cables forming part of...
s.sch011
Maintenance of the authorised scheme
s.sch011
Vessels under the undertaker’s control
s.sch011
Extension of time periods
s.sch011
Notification and Inspection
s.sch011
Aids to navigation
s.sch011
Colouring of structures
s.sch011
Aviation safety
s.sch011
Subject to the licence conditions at Part 2, this licence...
s.sch011
Chemicals, drilling and debris
s.sch011
Notification of unauthorised deposits
s.sch011
Pre-construction plans and documentation
s.sch011
(1) Any archaeological reports produced in accordance with condition 22(1)(g)(iii)...
s.sch011
Offshore safety management
s.sch011
Reporting of engaged agents, contractors and vessels
s.sch011
Pre-construction monitoring and surveys
s.sch011
Construction monitoring
s.sch011
Post construction
s.sch011
Reporting of impact pile driving
s.sch011
Such activities are authorised in relation to the construction, maintenance...
s.sch011
Deployment of cable protection
s.sch011
Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch011
Completion of construction
s.sch011
Maintenance reporting
s.sch011
Seasonal restriction
s.sch011
The substances or articles authorised for deposit at sea are—...
s.sch011
The grid coordinates for the authorised scheme are specified below—...
s.sch011
This licence remains in force until the authorised scheme has...
s.sch011
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch011
With respect to any condition which requires the licensed activities...
s.sch011
Any amendments to the details, plan or scheme must be...
s.sch012
(1) In this licence— “the 2008 Act” means the Planning...
s.sch012
Design parameters
s.sch012
Maintenance of the authorised scheme
s.sch012
Vessels under the undertaker’s control
s.sch012
Extension of time periods
s.sch012
Notification and Inspection
s.sch012
Aids to navigation
s.sch012
Colouring of structures
s.sch012
Chemicals, drilling and debris
s.sch012
Notification of unauthorised deposits
s.sch012
Aviation safety
s.sch012
Subject to the licence conditions at Part 2, this licence...
s.sch012
Pre-construction plans and documents
s.sch012
(1) Each programme, statement, plan, protocol or scheme required to...
s.sch012
Reporting of engaged agents, contractors and vessels
s.sch012
Reporting of impact pile driving
s.sch012
Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch012
Maintenance reporting
s.sch012
Piling restriction for spawning herring
s.sch012
Such activities are authorised in relation to the construction, maintenance...
s.sch012
The substances or articles authorised for deposit at sea are—...
s.sch012
The grid coordinates for the authorised scheme are specified below—...
s.sch012
This licence remains in force until the authorised scheme has...
s.sch012
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch012
With respect to any condition which requires the licensed activities...
s.sch012
Any amendments to the details, plan or scheme must be...
s.sch013
(1) In this licence— “the 2008 Act” means the Planning...
s.sch013
Design parameters
s.sch013
Maintenance of the authorised scheme
s.sch013
Vessels under the undertaker’s control
s.sch013
Extension of time periods
s.sch013
Notification and Inspection
s.sch013
Aids to navigation
s.sch013
Colouring of structures
s.sch013
Chemicals, drilling and debris
s.sch013
Notification of unauthorised deposits
s.sch013
Aviation safety
s.sch013
Subject to the licence conditions at Part 2, this licence...
s.sch013
Pre-construction plans and documents
s.sch013
(1) Each programme, statement, plan, protocol or scheme required to...
s.sch013
Reporting of engaged agents, contractors and vessels
s.sch013
Reporting of impact pile driving
s.sch013
Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch013
Maintenance reporting
s.sch013
Piling restriction for spawning herring
s.sch013
Such activities are authorised in relation to the construction, maintenance...
s.sch013
The substances or articles authorised for deposit at sea are—...
s.sch013
The grid coordinates for the authorised scheme are specified below—...
s.sch013
This licence remains in force until the authorised scheme has...
s.sch013
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch013
With respect to any condition which requires the licensed activities...
s.sch013
Any amendments to the details, plan or scheme must be...
s.sch014
(1) In this licence— “the 2008 Act” means the Planning...
s.sch014
Design parameters
s.sch014
Maintenance of the authorised scheme
s.sch014
Vessels under the undertaker’s control
s.sch014
Extension of time periods
s.sch014
Notification and Inspection
s.sch014
Aids to navigation
s.sch014
Colouring of structures
s.sch014
Chemicals, drilling and debris
s.sch014
Notification of unauthorised deposits
s.sch014
Aviation safety
s.sch014
Subject to the licence conditions at Part 2, this licence...
s.sch014
Pre-construction plans and documents
s.sch014
(1) Each programme, statement, plan, protocol or scheme required to...
s.sch014
Reporting of engaged agents, contractors and vessels
s.sch014
Reporting of impact pile driving
s.sch014
Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch014
Maintenance reporting
s.sch014
Such activities are authorised in relation to the construction, maintenance...
s.sch014
The substances or articles authorised for deposit at sea are—...
s.sch014
The grid coordinates for the authorised scheme are specified below—...
s.sch014
This licence remains in force until the authorised scheme has...
s.sch014
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch014
With respect to any condition which requires the licensed activities...
s.sch014
Any amendments to the details, plan or scheme must be...
s.sch015
(1) In this licence— “the 2008 Act” means the Planning...
s.sch015
Design parameters
s.sch015
Maintenance of the authorised scheme
s.sch015
Vessels under the undertaker’s control
s.sch015
Extension of time periods
s.sch015
Notification and Inspection
s.sch015
Aids to navigation
s.sch015
Colouring of structures
s.sch015
Chemicals, drilling and debris
s.sch015
Notification of unauthorised deposits
s.sch015
Aviation safety
s.sch015
Subject to the licence conditions at Part 2, this licence...
s.sch015
Pre-construction plans and documents
s.sch015
(1) Each programme, statement, plan, protocol or scheme required to...
s.sch015
Reporting of engaged agents, contractors and vessels
s.sch015
Reporting of impact pile driving
s.sch015
Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch015
Maintenance reporting
s.sch015
Such activities are authorised in relation to the construction, maintenance...
s.sch015
The substances or articles authorised for deposit at sea are—...
s.sch015
The grid coordinates for the authorised scheme are specified below—...
s.sch015
This licence remains in force until the authorised scheme has...
s.sch015
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch015
With respect to any condition which requires the licensed activities...
s.sch015
Any amendments to the details, plan or scheme must be...
s.sch016
Not used.
s.sch018
Application
s.sch018
Miscellaneous
s.sch018
Acquisition of land
s.sch018
Removal of apparatus
s.sch018
Facilities and rights for alternative apparatus
s.sch018
Retained apparatus: protection of Cadent
s.sch018
Expenses
s.sch018
Indemnity
s.sch018
Enactments and agreements
s.sch018
Co-operation
s.sch018
Access
s.sch018
Arbitration
s.sch018
Any difference or dispute arising between the undertaker and the...
s.sch018
Notices
s.sch018
The provisions of this Part of this Schedule have effect,...
s.sch018
In this Part of this Schedule— “asset protection agreement” means...
s.sch018
(1) Where under this Part of this Schedule Network Rail...
s.sch018
(1) The undertaker must not exercise the powers conferred by—...
s.sch018
(1) The undertaker must before commencing construction of any specified...
s.sch018
(1) Any specified work and any protective works to be...
s.sch018
The undertaker must— (a) at all times afford reasonable facilities...
s.sch018
Network Rail must at all times afford reasonable facilities to...
s.sch018
(1) If any permanent or temporary alterations or additions to...
s.sch018
For the protection of any operator, the following provisions, unless...
s.sch018
The undertaker must repay to Network Rail all reasonable fees,...
s.sch018
(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch018
If at any time after the completion of a specified...
s.sch018
The undertaker must not provide any illumination or illuminated sign...
s.sch018
Any additional expenses which Network Rail may reasonably incur in...
s.sch018
(1) The undertaker must pay to Network Rail all reasonable...
s.sch018
Network Rail must, on receipt of a request from the...
s.sch018
In the assessment of any sums payable to Network Rail...
s.sch018
The undertaker and Network Rail may, subject in the case...
s.sch018
Nothing in this Order, or in any enactment incorporated with...
s.sch018
In this Part— “electronic communications apparatus” has the same meaning...
s.sch018
The undertaker must give written notice to Network Rail if...
s.sch018
The undertaker must no later than 28 days from the...
s.sch018
In relation to any dispute arising under this part of...
s.sch018
Application
s.sch018
Interpretation
s.sch018
Restriction on authorised development
s.sch018
Submission and approval of plans
s.sch018
Co-existence and proximity agreement
s.sch018
Provision of information
s.sch018
Arbitration
s.sch018
The exercise of the powers of article 28 (statutory undertakers)...
s.sch018
Application
s.sch018
Interpretation
s.sch018
Restriction on authorised development
s.sch018
Coexistence and proximity agreement
s.sch018
Provision of information
s.sch018
Arbitration
s.sch018
Application
s.sch018
Interpretation
s.sch018
Control of works within the Lincs control area
s.sch018
Arbitration
s.sch018
Application
s.sch018
Interpretation
s.sch018
Control of works within the Race Bank control area
s.sch018
Arbitration
s.sch018
Application
s.sch018
Interpretation
s.sch018
Control of works within the DEP control area
s.sch018
Arbitration
s.sch018
Application
s.sch018
In this Part of this Schedule— “acceptable credit provider” means...
s.sch018
This Part of this Schedule does not apply to—
s.sch018
On Street Apparatus
s.sch018
Apparatus of Spalding Energy in closed streets
s.sch018
Acquisition of land
s.sch018
Removal of apparatus
s.sch018
Facilities and rights for alternative apparatus
s.sch018
Retained apparatus: protection
s.sch018
Expenses
s.sch018
Indemnity
s.sch018
Enactments and agreements
s.sch018
Co-operation
s.sch018
Nothing in this part of this Schedule affects the provisions...
s.sch018
Access
s.sch018
Arbitration
s.sch018
Notices
s.sch018
Application
s.sch018
Interpretation
s.sch018
In this Part of this Schedule— “affected undertaker” means— any...
s.sch018
On street apparatus
s.sch018
Apparatus in closed streets
s.sch018
Acquisition of land
s.sch018
Removal of apparatus
s.sch018
Facilities and rights for alternative apparatus
s.sch018
Retained apparatus
s.sch018
Expenses and costs
s.sch018
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch018
Cooperation
s.sch018
Where the undertaker identifies any apparatus which may belong to...
s.sch018
Precedence of the 1991 Act in respect of apparatus in the street
s.sch018
Nothing in this Part of this Schedule affects the provisions...
s.sch018
The undertaker and Anglian Water may by written agreement substitute...
s.sch018
For the avoidance of doubt whenever Anglian Water’s consent, agreement...
s.sch018
Any difference or dispute arising between the undertaker and Anglian...
s.sch018
(1) The following provisions apply for the protection of the...
s.sch018
Submission and approval of plans
s.sch018
Construction of protective works
s.sch018
Timing of works and service of notices
s.sch018
Works not in accordance with this Part of Schedule 18
s.sch018
Maintenance of works
s.sch018
No acquisition etc. except by agreement
s.sch018
Remediating impaired drainage work
s.sch018
Agency access
s.sch018
Free passage of fish
s.sch018
Indemnity
s.sch018
(1) The undertaker is responsible for and indemnifies the Agency...
s.sch018
Disputes
s.sch018
The provisions of this Part of this Schedule have effect...
s.sch018
In this Part of this Schedule— “construction” includes execution, placing,...
s.sch018
(1) Before beginning to construct any specified work, the undertaker...
s.sch018
Without limiting paragraph 3, the requirements which the relevant drainage...
s.sch018
Removal of apparatus
s.sch018
(1) Subject to sub–paragraph (2), any specified work, and all...
s.sch018
(1) Subject to sub-paragraph (5) the undertaker must from the...
s.sch018
If by reason of the construction of any specified work...
s.sch018
If by reason of construction of the specified work the...
s.sch018
The undertaker must indemnify the relevant drainage authority in respect...
s.sch018
(1) Without limiting the other provisions of this Part of...
s.sch018
Any dispute arising between the undertaker and the relevant drainage...
s.sch018
For the protection of the Harbour Authority as referred to...
s.sch018
Interpretation
s.sch018
Submission and approval of plans
s.sch018
Facilities and rights for alternative apparatus
s.sch018
Construction of specified works and service of notices
s.sch018
The undertaker must give to the Harbour Authority not less...
s.sch018
Harbour legislation
s.sch018
The undertaker shall not require any further approval or licence...
s.sch018
Application
s.sch018
Interpretation
s.sch018
Interaction with the Proposed NGET Projects
s.sch018
On Street Apparatus
s.sch018
Apparatus of National Grid Electricity Transmission Plc in closed streets
s.sch018
Acquisition of land
s.sch018
Retained apparatus
s.sch018
Removal of apparatus
s.sch018
Facilities and rights for alternative apparatus
s.sch018
Retained apparatus: protection
s.sch018
Expenses
s.sch018
Indemnity
s.sch018
Enactments and agreements
s.sch018
Co-operation
s.sch018
Access
s.sch018
Arbitration
s.sch018
Notices
s.sch018
Expenses and costs
s.sch018
Restriction on authorised development
s.sch018
Application
s.sch018
Interpretation
s.sch018
On Street Apparatus
s.sch018
Apparatus of National Gas in closed streets
s.sch018
Acquisition of land
s.sch018
Removal of apparatus
s.sch018
Facilities and rights for alternative apparatus
s.sch018
Retained apparatus: protection
s.sch018
Expenses
s.sch018
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch018
Indemnity
s.sch018
Enactments and agreements
s.sch018
Co-operation
s.sch018
Access
s.sch018
Arbitration
s.sch018
Notices
s.sch018
Application
s.sch018
Interpretation
s.sch018
On street apparatus
s.sch018
Apparatus of Cadent in closed streets
s.sch019
Primary objective
s.sch019
Time periods
s.sch019
Timetable
s.sch019
Procedure
s.sch019
Arbitrator’s powers
s.sch019
Costs
s.sch019
Confidentiality
s.sch019
Conservatory and Interim Measures
s.sch020
Applications made for certain approvals
s.sch020
Further information
s.sch020
Appeals
s.sch020
Fees
s.sch020
Interpretation of this Schedule
s.sch022
In this Part— “the artificial nesting measure” means up to...
s.sch022
The artificial nesting measure must not be decommissioned without written...
s.sch022
Results from the monitoring and reporting scheme referred to in...
s.sch022
The Kittiwake CIMP approved under this Schedule includes any amendments...
s.sch022
In this Part— “the artificial nesting measure” means up to...
s.sch022
(1) No offshore works are to commence until the undertaker has confirmed...
s.sch022
Marine Recovery Fund
s.sch022
Guillemot CIMP
s.sch022
Following consultation with the GCSG, the Guillemot CIMP must be...
s.sch022
The Guillemot CIMP (if required) must be based on the...
s.sch022
The undertaker must implement the measures set out in the...
s.sch022
(1) No offshore works are to commence until the undertaker has confirmed...
s.sch022
In the event that one or more of the guillemot...
s.sch022
No operation of any turbine forming part of the authorised...
s.sch022
The undertaker must notify the Secretary of State of—
s.sch022
The artificial nesting measure must not be decommissioned without written...
s.sch022
Results from the monitoring and reporting scheme referred to in...
s.sch022
The Guillemot CIMP approved under this Schedule includes any amendments...
s.sch022
In this Part— “Marine Recovery Fund” means the fund established...
s.sch022
No offshore works within the IDRBNR SAC are to commence...
s.sch022
Following receipt of the approvals under paragraph 2 the undertaker...
s.sch022
In this Part— “Marine Recovery Fund” means the fund established...
s.sch022
Marine Recovery Fund
s.sch022
No offshore works within the IDRBNR SAC are to commence...
s.sch022
Following receipt of the approvals under paragraph 2 the undertaker...
s.sch022
Kittiwake CIMP
s.sch022
Following consultation with the KCSG, the Kittiwake CIMP must be...
s.sch022
The Kittiwake CIMP (if required) must be based on the...
s.sch022
The undertaker must implement the measures set out in the...
s.sch022
No operation of any turbine forming part of the authorised...
s.sch022
The undertaker must notify the Secretary of State of—
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.