UK Statutory Instrument SI 2026/138 United Kingdom

The Outer Dowsing Offshore Wind Farm Order 2026

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

48 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Power to maintain the authorised project
s.art005 Benefit of the Order
s.art006 Application and modification of legislative provisions
s.art007 Defence to proceedings in respect of statutory nuisance
s.art008 Street works
s.art009 Application of the 1991 Act
s.art010 Temporary closure of public rights of way
s.art011 Temporary closure of streets
s.art012 Access to works
s.art013 Agreements with street authorities
s.art014 Power to alter layout etc. of streets
s.art015 Traffic Regulation
s.art016 Discharge of water
s.art017 Authority to survey and investigate the land onshore
s.art018 Compulsory acquisition of land
s.art019 Time limit for exercise of authority to acquire land compulsorily
s.art020 Compulsory acquisition of rights
s.art021 Private rights
s.art022 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art023 Modification of Part 1 of the Compulsory Purchase Act 1965
s.art024 Acquisition of subsoil or airspace only
s.art025 Rights under or over streets
s.art026 Temporary use of land for carrying out the authorised project
s.art027 Temporary use of land for maintaining authorised project
s.art028 Statutory undertakers
s.art029 Recovery of costs of new connections
s.art030 Operation of generating station
s.art031 Deemed marine licences under the 2009 Act
s.art032 Application of landlord and tenant law
s.art033 Amendment of local legislation
s.art034 Operational land for purposes of the 1990 Act
s.art035 Felling or lopping of trees and removal of hedgerows
s.art036 Trees subject to tree preservation orders
s.art037 Protective provisions
s.art038 Arbitration
s.art039 Requirements, appeals, etc.
s.art040 Certification of plans etc.
s.art041 Abatement of works abandoned or decayed
s.art042 Saving provisions for Trinity House
s.art043 Crown rights
s.art044 Funding
s.art045 Compensation provisions
s.art046 Service of notices
s.art047 Transfer of functions of the relevant local planning authority
s.art048 No double recovery
Schedules

Schedules

1 of 434 shown
s.sch018 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Compensate telecoms operators for damage or service interruption caused by the wind farm worksStatutory Undertaker
433 other schedules
s.sch001 A nationally significant infrastructure project as defined in sections 14...
s.sch001 Offshore decommissioning
s.sch001 Stages of authorised project onshore
s.sch001 Detailed onshore design parameters
s.sch001 Provision of landscaping
s.sch001 Implementation and maintenance of landscaping
s.sch001 Ecological management plan
s.sch001 Fencing and other means of permanent enclosure
s.sch001 Temporary fencing and other temporary means of enclosure
s.sch001 Operational drainage management and emergency flood response
s.sch001 Contaminated land and groundwater
s.sch001 The grid coordinates for that part of the authorised project...
s.sch001 Onshore archaeology
s.sch001 Code of construction practice
s.sch001 Construction hours
s.sch001 Highway accesses
s.sch001 Traffic
s.sch001 Public rights of way
s.sch001 Restoration of land used temporarily for construction
s.sch001 Onshore decommissioning
s.sch001 Control of noise during operational phase
s.sch001 Control of artificial light emissions during operational phase
s.sch001 Works within the Order limits which have been subject to...
s.sch001 Aviation Lighting
s.sch001 Requirement for written approval
s.sch001 Amendments to approved details
s.sch001 Skills, supply chain and employment
s.sch001 Cromer and Claxby Radar Mitigation
s.sch001 Ministry of Defence Surveillance Operation
s.sch001 Biodiversity Net Gain
s.sch001 Wake Effects
s.sch001 Time limits
s.sch001 Detailed offshore design parameters
s.sch001 (1) The total number of offshore electrical installations and offshore...
s.sch001 (1) The maximum number of gravity base structure foundations must...
s.sch001 The total volume of scour protection for wind turbine generators,...
s.sch001 (1) In respect of the offshore export cables comprised within...
s.sch008 Compensation enactments
s.sch008 For Schedule 2A to the 1965 Act substitute— SCHEDULE2A Counter-notice...
s.sch008 (1) Without prejudice to the generality of paragraph 1, the...
s.sch008 (1) Without limitation on the scope of paragraph 1, the...
s.sch008 Application of the 1965 Act
s.sch008 For section 7 of the 1965 Act (measure of compensation...
s.sch008 The following provisions of the 1965 Act (which state the...
s.sch008 are so modified as to secure that, as against persons...
s.sch008 Section 20 of the 1965 Act (tenants at will, etc.)...
s.sch008 Section 22 of the 1965 Act (interests omitted from purchase)...
s.sch010 (1) In this licence— “the 2004 Act” means the Energy...
s.sch010 Design parameters
s.sch010 (1) The total number of offshore accommodation platforms forming part...
s.sch010 (1) The total length of the cables forming part of...
s.sch010 Maintenance of the authorised scheme
s.sch010 Vessels under the undertaker’s control
s.sch010 Extension of time periods
s.sch010 Notification and Inspection
s.sch010 Aids to navigation
s.sch010 Colouring of structures
s.sch010 Aviation safety
s.sch010 Subject to the licence conditions at Part 2, this licence...
s.sch010 Chemicals, drilling and debris
s.sch010 Notification of unauthorised deposits
s.sch010 Pre-construction plans and documentation
s.sch010 (1) Any archaeological reports produced in accordance with condition 22(1)(g)(iii)...
s.sch010 Offshore safety management
s.sch010 Reporting of engaged agents, contractors and vessels
s.sch010 Pre-construction monitoring and surveys
s.sch010 Construction monitoring
s.sch010 Post construction
s.sch010 Reporting of impact pile driving
s.sch010 Such activities are authorised in relation to the construction, maintenance...
s.sch010 Deployment of cable protection
s.sch010 Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch010 Completion of construction
s.sch010 Maintenance reporting
s.sch010 Piling restriction for spawning herring
s.sch010 The substances or articles authorised for deposit at sea are—...
s.sch010 The grid coordinates for the authorised scheme are specified below—...
s.sch010 This licence remains in force until the authorised scheme has...
s.sch010 The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch010 With respect to any condition which requires the licensed activities...
s.sch010 Any amendments to the details, plan or scheme must be...
s.sch011 (1) In this licence— “the 2004 Act” means the Energy...
s.sch011 Design parameters
s.sch011 (1) Offshore accommodation platform foundation structures forming part of the...
s.sch011 (1) The total length of the cables forming part of...
s.sch011 Maintenance of the authorised scheme
s.sch011 Vessels under the undertaker’s control
s.sch011 Extension of time periods
s.sch011 Notification and Inspection
s.sch011 Aids to navigation
s.sch011 Colouring of structures
s.sch011 Aviation safety
s.sch011 Subject to the licence conditions at Part 2, this licence...
s.sch011 Chemicals, drilling and debris
s.sch011 Notification of unauthorised deposits
s.sch011 Pre-construction plans and documentation
s.sch011 (1) Any archaeological reports produced in accordance with condition 22(1)(g)(iii)...
s.sch011 Offshore safety management
s.sch011 Reporting of engaged agents, contractors and vessels
s.sch011 Pre-construction monitoring and surveys
s.sch011 Construction monitoring
s.sch011 Post construction
s.sch011 Reporting of impact pile driving
s.sch011 Such activities are authorised in relation to the construction, maintenance...
s.sch011 Deployment of cable protection
s.sch011 Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch011 Completion of construction
s.sch011 Maintenance reporting
s.sch011 Seasonal restriction
s.sch011 The substances or articles authorised for deposit at sea are—...
s.sch011 The grid coordinates for the authorised scheme are specified below—...
s.sch011 This licence remains in force until the authorised scheme has...
s.sch011 The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch011 With respect to any condition which requires the licensed activities...
s.sch011 Any amendments to the details, plan or scheme must be...
s.sch012 (1) In this licence— “the 2008 Act” means the Planning...
s.sch012 Design parameters
s.sch012 Maintenance of the authorised scheme
s.sch012 Vessels under the undertaker’s control
s.sch012 Extension of time periods
s.sch012 Notification and Inspection
s.sch012 Aids to navigation
s.sch012 Colouring of structures
s.sch012 Chemicals, drilling and debris
s.sch012 Notification of unauthorised deposits
s.sch012 Aviation safety
s.sch012 Subject to the licence conditions at Part 2, this licence...
s.sch012 Pre-construction plans and documents
s.sch012 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch012 Reporting of engaged agents, contractors and vessels
s.sch012 Reporting of impact pile driving
s.sch012 Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch012 Maintenance reporting
s.sch012 Piling restriction for spawning herring
s.sch012 Such activities are authorised in relation to the construction, maintenance...
s.sch012 The substances or articles authorised for deposit at sea are—...
s.sch012 The grid coordinates for the authorised scheme are specified below—...
s.sch012 This licence remains in force until the authorised scheme has...
s.sch012 The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch012 With respect to any condition which requires the licensed activities...
s.sch012 Any amendments to the details, plan or scheme must be...
s.sch013 (1) In this licence— “the 2008 Act” means the Planning...
s.sch013 Design parameters
s.sch013 Maintenance of the authorised scheme
s.sch013 Vessels under the undertaker’s control
s.sch013 Extension of time periods
s.sch013 Notification and Inspection
s.sch013 Aids to navigation
s.sch013 Colouring of structures
s.sch013 Chemicals, drilling and debris
s.sch013 Notification of unauthorised deposits
s.sch013 Aviation safety
s.sch013 Subject to the licence conditions at Part 2, this licence...
s.sch013 Pre-construction plans and documents
s.sch013 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch013 Reporting of engaged agents, contractors and vessels
s.sch013 Reporting of impact pile driving
s.sch013 Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch013 Maintenance reporting
s.sch013 Piling restriction for spawning herring
s.sch013 Such activities are authorised in relation to the construction, maintenance...
s.sch013 The substances or articles authorised for deposit at sea are—...
s.sch013 The grid coordinates for the authorised scheme are specified below—...
s.sch013 This licence remains in force until the authorised scheme has...
s.sch013 The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch013 With respect to any condition which requires the licensed activities...
s.sch013 Any amendments to the details, plan or scheme must be...
s.sch014 (1) In this licence— “the 2008 Act” means the Planning...
s.sch014 Design parameters
s.sch014 Maintenance of the authorised scheme
s.sch014 Vessels under the undertaker’s control
s.sch014 Extension of time periods
s.sch014 Notification and Inspection
s.sch014 Aids to navigation
s.sch014 Colouring of structures
s.sch014 Chemicals, drilling and debris
s.sch014 Notification of unauthorised deposits
s.sch014 Aviation safety
s.sch014 Subject to the licence conditions at Part 2, this licence...
s.sch014 Pre-construction plans and documents
s.sch014 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch014 Reporting of engaged agents, contractors and vessels
s.sch014 Reporting of impact pile driving
s.sch014 Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch014 Maintenance reporting
s.sch014 Such activities are authorised in relation to the construction, maintenance...
s.sch014 The substances or articles authorised for deposit at sea are—...
s.sch014 The grid coordinates for the authorised scheme are specified below—...
s.sch014 This licence remains in force until the authorised scheme has...
s.sch014 The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch014 With respect to any condition which requires the licensed activities...
s.sch014 Any amendments to the details, plan or scheme must be...
s.sch015 (1) In this licence— “the 2008 Act” means the Planning...
s.sch015 Design parameters
s.sch015 Maintenance of the authorised scheme
s.sch015 Vessels under the undertaker’s control
s.sch015 Extension of time periods
s.sch015 Notification and Inspection
s.sch015 Aids to navigation
s.sch015 Colouring of structures
s.sch015 Chemicals, drilling and debris
s.sch015 Notification of unauthorised deposits
s.sch015 Aviation safety
s.sch015 Subject to the licence conditions at Part 2, this licence...
s.sch015 Pre-construction plans and documents
s.sch015 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch015 Reporting of engaged agents, contractors and vessels
s.sch015 Reporting of impact pile driving
s.sch015 Southern North Sea Special Area of Conservation Site Integrity Plan (Piling)
s.sch015 Maintenance reporting
s.sch015 Such activities are authorised in relation to the construction, maintenance...
s.sch015 The substances or articles authorised for deposit at sea are—...
s.sch015 The grid coordinates for the authorised scheme are specified below—...
s.sch015 This licence remains in force until the authorised scheme has...
s.sch015 The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch015 With respect to any condition which requires the licensed activities...
s.sch015 Any amendments to the details, plan or scheme must be...
s.sch016 Not used.
s.sch018 Application
s.sch018 Miscellaneous
s.sch018 Acquisition of land
s.sch018 Removal of apparatus
s.sch018 Facilities and rights for alternative apparatus
s.sch018 Retained apparatus: protection of Cadent
s.sch018 Expenses
s.sch018 Indemnity
s.sch018 Enactments and agreements
s.sch018 Co-operation
s.sch018 Access
s.sch018 Arbitration
s.sch018 Any difference or dispute arising between the undertaker and the...
s.sch018 Notices
s.sch018 The provisions of this Part of this Schedule have effect,...
s.sch018 In this Part of this Schedule— “asset protection agreement” means...
s.sch018 (1) Where under this Part of this Schedule Network Rail...
s.sch018 (1) The undertaker must not exercise the powers conferred by—...
s.sch018 (1) The undertaker must before commencing construction of any specified...
s.sch018 (1) Any specified work and any protective works to be...
s.sch018 The undertaker must— (a) at all times afford reasonable facilities...
s.sch018 Network Rail must at all times afford reasonable facilities to...
s.sch018 (1) If any permanent or temporary alterations or additions to...
s.sch018 For the protection of any operator, the following provisions, unless...
s.sch018 The undertaker must repay to Network Rail all reasonable fees,...
s.sch018 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch018 If at any time after the completion of a specified...
s.sch018 The undertaker must not provide any illumination or illuminated sign...
s.sch018 Any additional expenses which Network Rail may reasonably incur in...
s.sch018 (1) The undertaker must pay to Network Rail all reasonable...
s.sch018 Network Rail must, on receipt of a request from the...
s.sch018 In the assessment of any sums payable to Network Rail...
s.sch018 The undertaker and Network Rail may, subject in the case...
s.sch018 Nothing in this Order, or in any enactment incorporated with...
s.sch018 In this Part— “electronic communications apparatus” has the same meaning...
s.sch018 The undertaker must give written notice to Network Rail if...
s.sch018 The undertaker must no later than 28 days from the...
s.sch018 In relation to any dispute arising under this part of...
s.sch018 Application
s.sch018 Interpretation
s.sch018 Restriction on authorised development
s.sch018 Submission and approval of plans
s.sch018 Co-existence and proximity agreement
s.sch018 Provision of information
s.sch018 Arbitration
s.sch018 The exercise of the powers of article 28 (statutory undertakers)...
s.sch018 Application
s.sch018 Interpretation
s.sch018 Restriction on authorised development
s.sch018 Coexistence and proximity agreement
s.sch018 Provision of information
s.sch018 Arbitration
s.sch018 Application
s.sch018 Interpretation
s.sch018 Control of works within the Lincs control area
s.sch018 Arbitration
s.sch018 Application
s.sch018 Interpretation
s.sch018 Control of works within the Race Bank control area
s.sch018 Arbitration
s.sch018 Application
s.sch018 Interpretation
s.sch018 Control of works within the DEP control area
s.sch018 Arbitration
s.sch018 Application
s.sch018 In this Part of this Schedule— “acceptable credit provider” means...
s.sch018 This Part of this Schedule does not apply to—
s.sch018 On Street Apparatus
s.sch018 Apparatus of Spalding Energy in closed streets
s.sch018 Acquisition of land
s.sch018 Removal of apparatus
s.sch018 Facilities and rights for alternative apparatus
s.sch018 Retained apparatus: protection
s.sch018 Expenses
s.sch018 Indemnity
s.sch018 Enactments and agreements
s.sch018 Co-operation
s.sch018 Nothing in this part of this Schedule affects the provisions...
s.sch018 Access
s.sch018 Arbitration
s.sch018 Notices
s.sch018 Application
s.sch018 Interpretation
s.sch018 In this Part of this Schedule— “affected undertaker” means— any...
s.sch018 On street apparatus
s.sch018 Apparatus in closed streets
s.sch018 Acquisition of land
s.sch018 Removal of apparatus
s.sch018 Facilities and rights for alternative apparatus
s.sch018 Retained apparatus
s.sch018 Expenses and costs
s.sch018 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch018 Cooperation
s.sch018 Where the undertaker identifies any apparatus which may belong to...
s.sch018 Precedence of the 1991 Act in respect of apparatus in the street
s.sch018 Nothing in this Part of this Schedule affects the provisions...
s.sch018 The undertaker and Anglian Water may by written agreement substitute...
s.sch018 For the avoidance of doubt whenever Anglian Water’s consent, agreement...
s.sch018 Any difference or dispute arising between the undertaker and Anglian...
s.sch018 (1) The following provisions apply for the protection of the...
s.sch018 Submission and approval of plans
s.sch018 Construction of protective works
s.sch018 Timing of works and service of notices
s.sch018 Works not in accordance with this Part of Schedule 18
s.sch018 Maintenance of works
s.sch018 No acquisition etc. except by agreement
s.sch018 Remediating impaired drainage work
s.sch018 Agency access
s.sch018 Free passage of fish
s.sch018 Indemnity
s.sch018 (1) The undertaker is responsible for and indemnifies the Agency...
s.sch018 Disputes
s.sch018 The provisions of this Part of this Schedule have effect...
s.sch018 In this Part of this Schedule— “construction” includes execution, placing,...
s.sch018 (1) Before beginning to construct any specified work, the undertaker...
s.sch018 Without limiting paragraph 3, the requirements which the relevant drainage...
s.sch018 Removal of apparatus
s.sch018 (1) Subject to sub–paragraph (2), any specified work, and all...
s.sch018 (1) Subject to sub-paragraph (5) the undertaker must from the...
s.sch018 If by reason of the construction of any specified work...
s.sch018 If by reason of construction of the specified work the...
s.sch018 The undertaker must indemnify the relevant drainage authority in respect...
s.sch018 (1) Without limiting the other provisions of this Part of...
s.sch018 Any dispute arising between the undertaker and the relevant drainage...
s.sch018 For the protection of the Harbour Authority as referred to...
s.sch018 Interpretation
s.sch018 Submission and approval of plans
s.sch018 Facilities and rights for alternative apparatus
s.sch018 Construction of specified works and service of notices
s.sch018 The undertaker must give to the Harbour Authority not less...
s.sch018 Harbour legislation
s.sch018 The undertaker shall not require any further approval or licence...
s.sch018 Application
s.sch018 Interpretation
s.sch018 Interaction with the Proposed NGET Projects
s.sch018 On Street Apparatus
s.sch018 Apparatus of National Grid Electricity Transmission Plc in closed streets
s.sch018 Acquisition of land
s.sch018 Retained apparatus
s.sch018 Removal of apparatus
s.sch018 Facilities and rights for alternative apparatus
s.sch018 Retained apparatus: protection
s.sch018 Expenses
s.sch018 Indemnity
s.sch018 Enactments and agreements
s.sch018 Co-operation
s.sch018 Access
s.sch018 Arbitration
s.sch018 Notices
s.sch018 Expenses and costs
s.sch018 Restriction on authorised development
s.sch018 Application
s.sch018 Interpretation
s.sch018 On Street Apparatus
s.sch018 Apparatus of National Gas in closed streets
s.sch018 Acquisition of land
s.sch018 Removal of apparatus
s.sch018 Facilities and rights for alternative apparatus
s.sch018 Retained apparatus: protection
s.sch018 Expenses
s.sch018 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch018 Indemnity
s.sch018 Enactments and agreements
s.sch018 Co-operation
s.sch018 Access
s.sch018 Arbitration
s.sch018 Notices
s.sch018 Application
s.sch018 Interpretation
s.sch018 On street apparatus
s.sch018 Apparatus of Cadent in closed streets
s.sch019 Primary objective
s.sch019 Time periods
s.sch019 Timetable
s.sch019 Procedure
s.sch019 Arbitrator’s powers
s.sch019 Costs
s.sch019 Confidentiality
s.sch019 Conservatory and Interim Measures
s.sch020 Applications made for certain approvals
s.sch020 Further information
s.sch020 Appeals
s.sch020 Fees
s.sch020 Interpretation of this Schedule
s.sch022 In this Part— “the artificial nesting measure” means up to...
s.sch022 The artificial nesting measure must not be decommissioned without written...
s.sch022 Results from the monitoring and reporting scheme referred to in...
s.sch022 The Kittiwake CIMP approved under this Schedule includes any amendments...
s.sch022 In this Part— “the artificial nesting measure” means up to...
s.sch022 (1) No offshore works are to commence until the undertaker has confirmed...
s.sch022 Marine Recovery Fund
s.sch022 Guillemot CIMP
s.sch022 Following consultation with the GCSG, the Guillemot CIMP must be...
s.sch022 The Guillemot CIMP (if required) must be based on the...
s.sch022 The undertaker must implement the measures set out in the...
s.sch022 (1) No offshore works are to commence until the undertaker has confirmed...
s.sch022 In the event that one or more of the guillemot...
s.sch022 No operation of any turbine forming part of the authorised...
s.sch022 The undertaker must notify the Secretary of State of—
s.sch022 The artificial nesting measure must not be decommissioned without written...
s.sch022 Results from the monitoring and reporting scheme referred to in...
s.sch022 The Guillemot CIMP approved under this Schedule includes any amendments...
s.sch022 In this Part— “Marine Recovery Fund” means the fund established...
s.sch022 No offshore works within the IDRBNR SAC are to commence...
s.sch022 Following receipt of the approvals under paragraph 2 the undertaker...
s.sch022 In this Part— “Marine Recovery Fund” means the fund established...
s.sch022 Marine Recovery Fund
s.sch022 No offshore works within the IDRBNR SAC are to commence...
s.sch022 Following receipt of the approvals under paragraph 2 the undertaker...
s.sch022 Kittiwake CIMP
s.sch022 Following consultation with the KCSG, the Kittiwake CIMP must be...
s.sch022 The Kittiwake CIMP (if required) must be based on the...
s.sch022 The undertaker must implement the measures set out in the...
s.sch022 No operation of any turbine forming part of the authorised...
s.sch022 The undertaker must notify the Secretary of State of—

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.