UK Statutory Instrument 2025 United Kingdom

The Tillbridge Solar Order 2025

At a glance

What's here

4 compliance obligations

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch015

(1) Subject to sub-paragraphs (2) to (4), if as the...

  • Pay for damage to or interruption of communications equipment
s.sch015

The undertaker must not under the powers of this Order...

  • Obtain Cottam's consent before interfering with its apparatus or work area rights
s.sch015

The undertaker and Cottam must each act in good faith...

  • Each party must cooperate and provide assistance to the other
Browse 336 other Schedules — structural / supplementary
s.sch001

Interpretation

s.sch001

Authorised Development

s.sch002

Interpretation

s.sch002

Surface and foul water drainage

s.sch002

Archaeology

s.sch002

Construction environmental management plan

s.sch002

Operational environmental management plan

s.sch002

Waste management plan

s.sch002

Construction traffic management plan

s.sch002

Permissive path

s.sch002

Public rights of way

s.sch002

Operational noise

s.sch002

Soil management

s.sch002

Commencement of the authorised development

s.sch002

Skills, supply chain and employment

s.sch002

Decommissioning and restoration

s.sch002

Approved details and amendments to them

s.sch002

Community liaison group

s.sch002

Detailed design approval

s.sch002

Battery safety management

s.sch002

Landscape and ecological management plan

s.sch002

Biodiversity net gain

s.sch002

Fencing and other means of enclosure

s.sch003

The following provisions do not apply in so far as...

s.sch009

Interpretation

s.sch010

Compensation enactments

s.sch010

(1) Without limitation on the scope of paragraph 1, the...

s.sch010

(1) Without limitation on the scope of paragraph 1, the...

s.sch010

Application of Part 1 of the 1965 Act

s.sch010

(1) The modifications referred to in paragraph 4(a) are as...

s.sch014

Commencing an arbitration

s.sch014

Time periods

s.sch014

Timetable

s.sch014

Procedure

s.sch014

Arbitrator’s powers

s.sch014

Costs

s.sch014

Confidentiality

s.sch015

For the protection of the utility undertakers referred to in...

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Acquisition of land

s.sch015

Removal of apparatus

s.sch015

Facilities and rights for alternative apparatus

s.sch015

Retained apparatus: protection of Cadent

s.sch015

Expenses

s.sch015

Indemnity

s.sch015

Enactment and agreements

s.sch015

Co-operation

s.sch015

Access

s.sch015

Arbitration

s.sch015

Nothing in this Part of this Schedule affects the provisions...

s.sch015

Notices

s.sch015

(1) The following provisions apply for the protection of the...

s.sch015

Submission and approval of plans

s.sch015

Construction of protective works

s.sch015

Timing of works and service of notices

s.sch015

Works not in accordance with this Schedule

s.sch015

Maintenance of works

s.sch015

Remediating impaired drainage work

s.sch015

Agency access

s.sch015

Free passage of fish

s.sch015

For the protection of any operator, the following provisions have...

s.sch015

Indemnity

s.sch015

(1) The undertaker indemnifies the Agency against all costs and...

s.sch015

Disputes

s.sch015

For the protection of Northern Powergrid (Yorkshire) Plc the following...

s.sch015

In this Part of this Schedule— “alternative apparatus” means alternative...

s.sch015

This Part of this Schedule does not apply to apparatus...

s.sch015

Regardless of the temporary prohibition or restriction of use of...

s.sch015

Regardless of any provision in the Order or anything shown...

s.sch015

Regardless of any provision in the Order or anything shown...

s.sch015

(1) If, in the exercise of the powers conferred by...

s.sch015

In this Part of this Schedule— “the 2003 Act” means...

s.sch015

(1) Where, in accordance with the provisions of this Part...

s.sch015

(1) Not less than forty-eight days before starting the execution...

s.sch015

(1) Subject to the following provisions of this paragraph, the...

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Nothing in this Part of this Schedule affects the provisions...

s.sch015

Any difference under the provisions of this Part of this...

s.sch015

Where in consequence of the proposed construction of any of...

s.sch015

The plans submitted to Northern Powergrid by the undertaker pursuant...

s.sch015

Prior to carrying out any works within the Order limits,...

s.sch015

Where practicable the undertaker and Northern Powergrid will make reasonable...

s.sch015

The exercise of the powers of article 32 (statutory undertakers)...

s.sch015

The provisions of this Part of this Schedule have effect,...

s.sch015

(1) In this Part of this Schedule— “asset protection agreement”...

s.sch015

(1) Where under this Part of this Schedule Network Rail...

s.sch015

(1) The undertaker must not exercise the powers conferred by—...

s.sch015

(1) The undertaker must before commencing construction of any specified...

s.sch015

(1) Any specified work and any protective works to be...

s.sch015

The undertaker must— (a) at all times afford reasonable facilities...

s.sch015

Network Rail must at all times afford reasonable facilities to...

s.sch015

(1) If any permanent or temporary alterations or additions to...

s.sch015

The undertaker must repay to Network Rail all reasonable fees,...

s.sch015

(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

s.sch015

If at any time after the completion of a specified...

s.sch015

The undertaker must not provide any illumination or illuminated sign...

s.sch015

Any additional expenses which Network Rail may reasonably incur in...

s.sch015

(1) The undertaker must pay to Network Rail all reasonable...

s.sch015

Network Rail must, on receipt of a request from the...

s.sch015

In the assessment of any sums payable to Network Rail...

s.sch015

The undertaker and Network Rail may, subject in the case...

s.sch015

Nothing in this Order, or in any enactment incorporated with...

s.sch015

The undertaker must give written notice to Network Rail if...

s.sch015

This Part of this Schedule does not apply to—

s.sch015

The undertaker must no later than 28 days from the...

s.sch015

Any dispute arising under this Part of this Schedule (except...

s.sch015

Application

s.sch015

Interpretation

s.sch015

On street apparatus

s.sch015

Apparatus in streets subject to temporary prohibitions or restrictions

s.sch015

Protective works to buildings

s.sch015

Acquisition of apparatus

s.sch015

Removal of apparatus

s.sch015

Facilities and rights for alternative apparatus

s.sch015

Nothing in this Part of this Schedule affects the provisions...

s.sch015

Retained apparatus

s.sch015

Expenses and costs

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Cooperation

s.sch015

Where the undertaker identifies any apparatus which may belong to...

s.sch015

Nothing in this Part of this Schedule affects the provisions...

s.sch015

The undertaker and Anglian Water may by written agreement substitute...

s.sch015

For the protection of Uniper as referred to in this...

s.sch015

In this Part of this Schedule— “acceptable credit provider” means...

s.sch015

Except for paragraphs 180 (apparatus of Uniper in streets and...

s.sch015

The provisions of this Part of this Schedule have effect...

s.sch015

Apparatus of Uniper in streets and public rights of way

s.sch015

Protective works to buildings

s.sch015

Acquisition of land

s.sch015

Retained apparatus

s.sch015

Removal or replacement of apparatus

s.sch015

Expenses

s.sch015

Indemnity

s.sch015

Co-operation

s.sch015

Access

s.sch015

Confidentiality

s.sch015

In this Part of this Schedule— “authorised development” has the...

s.sch015

Arbitration

s.sch015

Notices

s.sch015

Application

s.sch015

Interpretation

s.sch015

Acquisition of apparatus

s.sch015

Prior to the carrying out of any restricted works or...

s.sch015

Where the undertaker acquires land which is subject to any...

s.sch015

Where the undertaker takes temporary possession of any land or...

s.sch015

Removal of apparatus and rights for alternative apparatus

s.sch015

The parties must use their reasonable endeavours to produce a...

s.sch015

In this Part of this Schedule— “alternative apparatus” means apparatus...

s.sch015

(1) Before commencing construction of a specified work, the undertaker...

s.sch015

The undertaker must afford to Exolum the necessary facilities and...

s.sch015

Any alternative apparatus is to be constructed in land owned...

s.sch015

After the details for the works for alternative apparatus to...

s.sch015

The following paragraphs 204 and 205 shall only apply if—...

s.sch015

In the circumstances set out in paragraph 203, if the...

s.sch015

Nothing in paragraph 204 authorises the undertaker to execute the...

s.sch015

Facilities and rights for alternative apparatus

s.sch015

Alternative rights must be granted before any alternative apparatus is...

s.sch015

The Parties agree that the undertaker must use reasonable endeavours...

s.sch015

Nothing in this Part of this Schedule or contained in...

s.sch015

Without limiting the scope of paragraph 20, the requirements which...

s.sch015

If the facilities and rights to be afforded by the...

s.sch015

Retained apparatus and alternative apparatus: protection

s.sch015

No restricted works are to be commenced until the Plan...

s.sch015

Any approval of Exolum in respect of restricted works may...

s.sch015

Where reasonably required by either party, in view of the...

s.sch015

If in consequence of the works notified to Exolum by...

s.sch015

Nothing in paragraphs 211 to 216 precludes the undertaker from...

s.sch015

Where Exolum reasonably requires protective works, the Parties must use...

s.sch015

The undertaker must afford to Exolum the necessary facilities and...

s.sch015

Any protective works are to be constructed in land owned...

s.sch015

(1) Subject to sub-paragraph (2), any specified work, and all...

s.sch015

After the details for the protective works to be provided...

s.sch015

Cathodic protection testing

s.sch015

The parties must carry out the works and enter into...

s.sch015

Expenses

s.sch015

There will be no deduction from any sum payable under...

s.sch015

Upon the submission of proper and reasonable estimates of costs...

s.sch015

Damage to property and other losses

s.sch015

Nothing in paragraph 226 imposes any liability on the undertaker...

s.sch015

The fact that any act or thing may have been...

s.sch015

Nothing in paragraph 226 imposes any liability on the undertaker...

s.sch015

If by reason of the construction of a specified work...

s.sch015

The undertaker and Exolum shall at all times take reasonable...

s.sch015

The undertaker warrants that it will use reasonable endeavours to...

s.sch015

Exolum must give to the undertaker reasonable notice of any...

s.sch015

Insurance

s.sch015

The undertaker shall maintain such insurance for the construction period...

s.sch015

Co-operation and reasonableness

s.sch015

Exolum must use its reasonable endeavours to co-operate with the...

s.sch015

The undertaker and Exolum will act reasonably in respect of...

s.sch015

Emergency circumstances

s.sch015

In the following circumstances, Exolum may on written notice to...

s.sch015

The undertaker must make reasonable compensation for costs, charges and...

s.sch015

The parties agree to act in good faith and in...

s.sch015

Exolum shall not be liable for any costs, expenses, losses...

s.sch015

Dispute resolution

s.sch015

The undertaker and Exolum must each nominate a representative who...

s.sch015

If the meeting between senior executives fails to result in...

s.sch015

Miscellaneous

s.sch015

Application

s.sch015

Interpretation

s.sch015

On Street Apparatus

s.sch015

Apparatus of EDF in streets and public rights of way

s.sch015

(1) The undertaker must make reasonable compensation for liabilities, costs...

s.sch015

Protective works to buildings

s.sch015

Acquisition of land

s.sch015

Removal of apparatus

s.sch015

Facilities and rights for alternative apparatus

s.sch015

Retained apparatus: protection

s.sch015

Expenses

s.sch015

Indemnity

s.sch015

Enactments and agreements

s.sch015

Co-operation

s.sch015

Access

s.sch015

Any dispute arising between the undertaker and the drainage authority...

s.sch015

Arbitration

s.sch015

Notices

s.sch015

Application

s.sch015

Interpretation

s.sch015

On Street Apparatus

s.sch015

Apparatus of National Grid Electricity Transmission Plc in streets subject to temporary prohibition or restriction of use and public rights of way

s.sch015

Protective works to buildings

s.sch015

Acquisition of land

s.sch015

Removal of apparatus

s.sch015

Facilities and rights for alternative apparatus

s.sch015

Interpretation

s.sch015

Retained apparatus: protection of National Grid Electricity Transmission Plc as electricity undertaker

s.sch015

Expenses

s.sch015

Indemnity

s.sch015

Enactments and agreements

s.sch015

Co-operation

s.sch015

Access

s.sch015

Arbitration

s.sch015

Notices

s.sch015

Application

s.sch015

Interpretation

s.sch015

Powers requiring the Canal & River Trust’s consent

s.sch015

Precedence of 1991 Act in respect of apparatus in streets

s.sch015

Regardless of any provision in this Order or anything shown...

s.sch015

Removal of apparatus

s.sch015

Facilities and rights for alternative apparatus

s.sch015

Retained apparatus

s.sch015

Expenses and costs

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Expert determination

s.sch015

The provisions of this Part of this Schedule have effect...

s.sch015

In this Part of this Schedule— “authorised development” has the...

s.sch015

Fencing

s.sch015

(1) Before commencing construction of a specified work, the undertaker...

s.sch015

Without limiting the scope of paragraph 290, the requirements which...

s.sch015

(1) Subject to sub-paragraph (2), any specified work, and all...

s.sch015

If by reason of the construction of a specified work...

s.sch015

If by reason of construction of the specified work Trent...

s.sch015

The undertaker must indemnify Trent Valley Internal Drainage Board in...

s.sch015

(1) Without limiting the other provisions of this Part of...

s.sch015

Any dispute arising between the undertaker and Trent Valley Internal...

s.sch015

This Part of this Schedule does not apply to apparatus...

s.sch015

Survey of waterway

s.sch015

Approval of plans, protective works etc.

s.sch015

Design of works

s.sch015

Notice of works

s.sch015

Construction of specified works

s.sch015

Prevention of pollution

s.sch015

Access to work – provision of information

s.sch015

Alterations to the waterway

s.sch015

Repayment of the Canal & River Trust’s fees, etc.

s.sch015

Making good of detriment; compensation and indemnity, etc.

s.sch015

Regardless of the temporary prohibition or restriction of use of...

s.sch015

Arbitration

s.sch015

Capitalised sums

s.sch015

As built drawings

s.sch015

Decommissioning

s.sch015

The provisions of this Part apply for the protection of...

s.sch015

In this Part— “apparatus” means the cables, structures or other...

s.sch015

The consent of Cottam under this Part is not required...

s.sch015

Where conditions are included in any consent granted by Cottam...

s.sch015

(1) The undertaker must not under the powers of this...

s.sch015

Regardless of any provision in this Order or anything shown...

s.sch015

(1) The undertaker must give to Cottam not less than...

s.sch015

The undertaker must at all reasonable times during construction of...

s.sch015

(1) After the purpose of any temporary works has been...

s.sch015

If in consequence of the exercise of the powers conferred...

s.sch015

The undertaker must not exercise the powers conferred by this...

s.sch015

To ensure its compliance with this Part, the undertaker must...

s.sch015

The undertaker must pay to Cottam the reasonable expenses incurred...

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Any dispute arising between the undertaker and Cottam under this...

s.sch015

(1) If, in the exercise of the powers conferred by...

s.sch015

The provisions of this Part apply for the protection of...

s.sch015

In this Part— “apparatus” means the cables, structures or other...

s.sch015

The consent of Gate Burton under this Part is not...

s.sch015

Where conditions are included in any consent granted by Gate...

s.sch015

The undertaker must not under the powers of this Order...

s.sch015

(1) The undertaker must not under the powers of this...

s.sch015

(1) The undertaker must give to Gate Burton not less...

s.sch015

The undertaker must at all reasonable times during construction of...

s.sch015

(1) After the purpose of any temporary works has been...

s.sch015

If in consequence of the exercise of the powers conferred...

s.sch015

(1) Where, in accordance with the provisions of this Part...

s.sch015

The undertaker must not exercise the powers conferred by this...

s.sch015

To ensure its compliance with this Part, the undertaker must...

s.sch015

The undertaker and Gate Burton must each act in good...

s.sch015

The undertaker must pay to Gate Burton the reasonable expenses...

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Any dispute arising between the undertaker and Gate Burton under...

s.sch015

The provisions of this Part apply for the protection of...

s.sch015

In this Part— “apparatus” means the cables, structures or other...

s.sch015

The consent of West Burton under this Part is not...

s.sch015

Where conditions are included in any consent granted by West...

s.sch015

(1) Not less than 28 days before starting the execution...

s.sch015

The undertaker must not under the powers of this Order...

s.sch015

(1) The undertaker must not under the powers of this...

s.sch015

(1) The undertaker must give to West Burton not less...

s.sch015

The undertaker must at all reasonable times during construction of...

s.sch015

(1) After the purpose of any temporary works has been...

s.sch015

If in consequence of the exercise of the powers conferred...

s.sch015

The undertaker must not exercise the powers conferred by this...

s.sch015

To ensure its compliance with this Part, the undertaker must...

s.sch015

The undertaker and West Burton must each act in good...

s.sch015

The undertaker must pay to West Burton the reasonable expenses...

s.sch015

(1) Subject to the following provisions of this paragraph, the...

s.sch015

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch015

Any dispute arising between the undertaker and West Burton under...

s.sch015

Interpretation

s.sch015

(1) The undertaker must, prior to the date of final...

s.sch015

Costs

s.sch015

Application

s.sch015

Interpretation

s.sch015

On street apparatus

s.sch015

Apparatus of Cadent where there is a temporary prohibition or restriction on the use of streets and public rights of way

s.sch015

Protective works to buildings

s.sch016

Interpretation

s.sch016

Applications made under requirement

s.sch016

Further information and consultation

s.sch016

Appeals

s.sch016

Fees

s.art020

Authority to survey and investigate the land

  • Comply with conditions when surveying land under the Order
Browse 48 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent etc. granted by this Order

s.art004

Operation of generating station

s.art005

Power to maintain the authorised development

s.art006

Application and modification of statutory provisions

s.art007

Defence to proceedings in respect of statutory nuisance

s.art008

Street works

s.art009

Application of the relevant permit scheme

s.art010

Power to alter layout, etc., of streets

s.art011

Construction and maintenance of altered streets

s.art012

Temporary prohibition or restriction of the use of streets and public rights of way

s.art013

Claimed public right of way

s.art014

Use of private roads

s.art015

Access to works

s.art016

Agreements with street authorities

s.art017

Traffic regulation measures

s.art018

Discharge of water

s.art019

Protective works to buildings

s.art021

Compulsory acquisition of land

s.art022

Time limit for exercise of authority to acquire land compulsorily

s.art023

Compulsory acquisition of rights

s.art024

Private rights

s.art025

Application of the 1981 Act

s.art026

Acquisition of subsoil only

s.art027

Power to override easements and other rights

s.art028

Modification of Part 1 of the Compulsory Purchase Act 1965

s.art029

Rights under or over streets

s.art030

Temporary use of land for constructing the authorised development

s.art031

Temporary use of land for maintaining the authorised development

s.art032

Statutory undertakers

s.art033

Apparatus and rights of statutory undertakers in closed streets

s.art034

Recovery of costs of new connections

s.art035

Benefit of the Order

s.art036

Consent to transfer the benefit of the Order

s.art037

Application of landlord and tenant law

s.art038

Operational land for the purposes of the 1990 Act

s.art039

Felling or lopping of trees and removal of hedgerows

s.art040

Trees subject to tree preservation orders

s.art041

Certification of plans and documents, etc.

s.art042

No double recovery

s.art043

Arbitration

s.art044

Protective provisions

s.art045

Service of notices

s.art046

Procedure in relation to certain approvals etc.

s.art047

Guarantees in respect of payment of compensation

s.art048

Compulsory acquisition of land – incorporation of the mineral code

s.art049

Crown rights

Explore more

Browse legislation

Find other UK business legislation with related guidance.