- Status
- In Force
- Penalty ceiling
- Regulated
Does it bind you?
Business-side roles with duties under this instrument.
Licence Holder2
Statutory Undertaker1
Other Acts binding the same actors
If a role above is yours, these are the other instruments that most often bind it.
Licence Holder — also bound by 225 other Acts
Statutory Undertaker — also bound by 179 other Acts
The Cory Decarbonisation Project Order 2025
120 duties
Water Industry Act 1991
53 duties
What it requires
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
12 other provisions — procedural and definitional
s.art001
Citation and commencement
s.art002
Interpretation
s.art003
Development consent etc. granted by the Order
s.art004
Operation of generating station
s.art005
Deemed marine licences under the 2009 Act
s.art006
Power to maintain the authorised project
s.art007
Benefit of the Order
s.art008
Abatement of works abandoned or decayed
s.art009
Saving provisions for Trinity House
s.art010
Crown rights
s.art011
Certification of plans, etc.
s.art012
Service of notices
Schedules
Schedules
3 of 80 shown
s.sch003
(1) Each programme, statement, plan, protocol or scheme required to...
Regulated
- Get MMO approval for pre-construction plans and follow themLicence Holder
s.sch004
(1) Each programme, statement, plan, protocol or scheme required to...
Regulated
- Submit pre-construction plans on time and comply with approved plansStatutory Undertaker
s.sch004
Low order unexploded ordnance clearance
Regulated
- Get pre-approval for low order unexploded ordnance clearanceLicence Holder
77 other schedules
s.sch001
A nationally significant infrastructure project as defined in sections 14...
s.sch001
The grid coordinates for the scheduled works are as shown...
s.sch001
Works within the Order limits which fall within the scope...
s.sch002
Time limits
s.sch002
Decommissioning
s.sch002
Requirement for written approval
s.sch002
Amendments to approved details
s.sch002
Design parameters
s.sch002
Aviation safety
s.sch002
St Anne’s and Lowther Hill Primary Surveillance Radar
s.sch002
Operation of Warton Aerodrome (Air traffic services)
s.sch002
Warton Aerodrome Primary Surveillance Rader
s.sch002
Operation of Walney Aerodrome (Air traffic services)
s.sch002
Air traffic services at Isle of Man Airport
s.sch002
Operation of Blackpool Airport
s.sch003
Interpretation
s.sch003
Design parameters
s.sch003
The total number of offshore substation platforms forming part of...
s.sch003
The total length of interconnector cables forming part of the...
s.sch003
Maintenance of the authorised scheme
s.sch003
Extension of time periods
s.sch003
Notifications and inspections
s.sch003
Aids to navigation
s.sch003
Colouring of structures
s.sch003
Chemicals, drilling and debris
s.sch003
Force Majeure
s.sch003
Details of licensed marine activities
s.sch003
Pre-construction plans and documentation
s.sch003
Underwater Sound Management Strategy
s.sch003
Low order unexploded ordnance clearance
s.sch003
Marine Noise Registry
s.sch003
Offshore safety management
s.sch003
Reporting of engaged agents, contractors and vessels
s.sch003
Pre-construction monitoring and surveys
s.sch003
Construction monitoring
s.sch003
Post-construction monitoring
s.sch003
Such activities are authorised in relation to the construction, maintenance...
s.sch003
Reporting of scour and cable protection
s.sch003
Completion of construction
s.sch003
Requirement for written approval
s.sch003
The substances and objects authorised for deposit at sea are—...
s.sch003
The grid coordinates for Work No. 1, Work No. 2...
s.sch003
This marine licence remains in force until the authorised scheme...
s.sch003
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch003
With respect to any condition which requires the licensed activities...
s.sch003
Any amendments to or variations from the approved details, plans...
s.sch004
Interpretation
s.sch004
Design parameters
s.sch004
The total number of offshore substation platforms forming part of...
s.sch004
The total length of interconnector cables forming part of the...
s.sch004
Maintenance of the authorised scheme
s.sch004
Extension of time periods
s.sch004
Notifications and inspections
s.sch004
Aids to navigation
s.sch004
Colouring of structures
s.sch004
Chemicals, drilling and debris
s.sch004
Force Majeure
s.sch004
Details of licensed marine activities
s.sch004
Pre-construction plans and documentation
s.sch004
Underwater Sound Management Strategy
s.sch004
Marine Noise Registry
s.sch004
Offshore safety management
s.sch004
Reporting of engaged agents, contractors and vessels
s.sch004
Pre-construction monitoring and surveys
s.sch004
Construction monitoring
s.sch004
Post-construction monitoring
s.sch004
Such activities are authorised in relation to the construction, maintenance...
s.sch004
Reporting of scour and cable protection
s.sch004
Completion of construction
s.sch004
Requirement for written approval
s.sch004
The substances and objects authorised for deposit at sea are—...
s.sch004
The grid coordinates for Work No. 2 and Work No....
s.sch004
This marine licence remains in force until the authorised scheme...
s.sch004
The provisions of section 72 (variation, suspension, revocation and transfer)...
s.sch004
With respect to any condition which requires the licensed activities...
s.sch004
Any amendments to or variations from the approved details, plans...
s.sch005
The following documents are the list referred to in article...
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.