UK Statutory Instrument SI 2024/807 United Kingdom

The Gate Burton Energy Park Order 2024

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker5

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art017 Authority to survey and investigate the land Regulated
  • Notify landowners and follow rules before surveying the landStatutory Undertaker
44 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by this Order
s.art004 Operation of generating station
s.art005 Power to maintain the authorised development
s.art006 Application and modification of statutory provisions
s.art007 Defence to proceedings in respect of statutory nuisance
s.art008 Street works
s.art009 Power to alter layout, etc., of streets
s.art010 Construction and maintenance of altered streets
s.art011 Temporary closure of streets and public rights of way
s.art012 Access to works
s.art013 Agreements with street authorities
s.art014 Traffic regulation measures
s.art015 Discharge of water
s.art016 Protective works to buildings
s.art018 Compulsory acquisition of land
s.art019 Time limit for exercise of authority to acquire land compulsorily
s.art020 Compulsory acquisition of rights
s.art021 Private rights
s.art022 Application of the 1981 Act
s.art023 Acquisition of subsoil only
s.art024 Power to override easements and other rights
s.art025 Modification of Part 1 of the Compulsory Purchase Act 1965
s.art026 Rights under or over streets
s.art027 Temporary use of land for constructing the authorised development
s.art028 Temporary use of land for maintaining the authorised development
s.art029 Statutory undertakers
s.art030 Apparatus and rights of statutory undertakers in temporarily closed streets
s.art031 Recovery of costs of new connections
s.art032 Benefit of the Order
s.art033 Consent to transfer the benefit of the Order
s.art034 Application of landlord and tenant law
s.art035 Operational land for the purposes of the 1990 Act
s.art036 Felling or lopping of trees and removal of hedgerows
s.art037 Trees subject to tree preservation orders
s.art038 Certification of plans and documents, etc.
s.art039 No double recovery
s.art040 Arbitration
s.art041 Protective provisions
s.art042 Service of notices
s.art043 Procedure in relation to certain approvals etc.
s.art044 Guarantees in respect of payment of compensation
s.art045 Crown rights
Schedules

Schedules

4 of 273 shown
s.sch014 (1) Subject to sub-paragraphs ‎(2) to ‎(4), if as the... Regulated
  • Pay costs of damage or interruption to telecoms apparatus caused by your worksStatutory Undertaker
s.sch014 The undertaker must not under the powers of this Order... Regulated
  • You must not interfere with Cottam's rights without consentStatutory Undertaker
s.sch014 The undertaker and Cottam must each act in good faith... Regulated
  • Act in good faith and co-operate with each other under the OrderStatutory Undertaker
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason... Regulated
  • Pay for damage or service interruption caused by your construction workStatutory Undertaker
269 other schedules
s.sch001 In this Schedule— “balance of solar system (BoSS) plant” means...
s.sch001 In the Districts of West Lindsey and Bassetlaw and in...
s.sch002 Interpretation
s.sch002 Surface and foul water drainage
s.sch002 Archaeology
s.sch002 Construction environmental management plan
s.sch002 Operational environmental management plan
s.sch002 Construction traffic management plan
s.sch002 Operational noise
s.sch002 Public rights of way diversions
s.sch002 Soils management
s.sch002 Skills, supply chain and employment
s.sch002 Decommissioning and restoration
s.sch002 Commencement of the authorised development
s.sch002 Approved details and amendments to them
s.sch002 Community liaison group
s.sch002 Detailed design approval
s.sch002 Battery safety management
s.sch002 Landscape and ecological management plan
s.sch002 Biodiversity net gain
s.sch002 Fencing and other means of enclosure
s.sch003 The following provisions do not apply in so far as...
s.sch004 Interpretation
s.sch009 Interpretation
s.sch010 Compensation enactments
s.sch010 (1) Without limitation on the scope of paragraph ‎1, the...
s.sch010 (1) Without limitation on the scope of paragraph ‎1, the...
s.sch010 Application of Part 1 of the 1965 Act
s.sch010 (1) The modifications referred to in paragraph ‎4(a) are as...
s.sch013 Commencing an arbitration
s.sch013 Time periods
s.sch013 Timetable
s.sch013 Procedure
s.sch013 Arbitrator’s powers
s.sch013 Costs
s.sch013 Confidentiality
s.sch014 For the protection of the utility undertakers referred to in...
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason...
s.sch014 Apparatus of National Grid in temporarily closed streets and public rights of way
s.sch014 Protective works to buildings
s.sch014 Acquisition of land
s.sch014 Removal of apparatus
s.sch014 Facilities and rights for alternative apparatus
s.sch014 Retained apparatus: Protection of National Grid as Electricity Undertaker
s.sch014 Expenses
s.sch014 Indemnity
s.sch014 Enactments and agreements
s.sch014 Co-operation
s.sch014 Nothing in this part of this Schedule affects the provisions...
s.sch014 Access
s.sch014 Arbitration
s.sch014 Notices
s.sch014 The provisions of this Part of this Schedule have effect,...
s.sch014 In this Part of this Schedule— “asset protection agreement” means...
s.sch014 (1) Where under this Part of this Schedule Network Rail...
s.sch014 (1) The undertaker must not exercise the powers conferred by—...
s.sch014 (1) The undertaker must before commencing construction of any specified...
s.sch014 (1) Any specified work and any protective works to be...
s.sch014 The undertaker must— (a) at all times afford reasonable facilities...
s.sch014 (1) For the protection of any operator, the following provisions...
s.sch014 Network Rail must at all times afford reasonable facilities to...
s.sch014 (1) If any permanent or temporary alterations or additions to...
s.sch014 The undertaker must repay to Network Rail all reasonable fees,...
s.sch014 (1) In this paragraph— “EMI” means, subject to sub-paragraph ‎(2),...
s.sch014 If at any time after the completion of a specified...
s.sch014 The undertaker must not provide any illumination or illuminated sign...
s.sch014 Any additional expenses which Network Rail may reasonably incur in...
s.sch014 (1) The undertaker must pay to Network Rail all reasonable...
s.sch014 Network Rail must, on receipt of a request from the...
s.sch014 In the assessment of any sums payable to Network Rail...
s.sch014 In this Part of this Schedule— “the 2003 Act” means...
s.sch014 The undertaker and Network Rail may, subject in the case...
s.sch014 Nothing in this Order, or in any enactment incorporated with...
s.sch014 The undertaker must give written notice to Network Rail if...
s.sch014 The undertaker must no later than 28 days from the...
s.sch014 Any dispute arising under this Part of this Schedule, unless...
s.sch014 Interpretation
s.sch014 Powers requiring the Canal & River Trust’s consent
s.sch014 Fencing
s.sch014 Survey of waterway
s.sch014 Approval of plans, protective works etc.
s.sch014 The exercise of the powers of article ‎29 (statutory undertakers)...
s.sch014 Design of works
s.sch014 Notice of works
s.sch014 Construction of specified works
s.sch014 Prevention of pollution
s.sch014 Access to work – provision of information
s.sch014 Alterations to the waterway
s.sch014 Repayment of the Canal & River Trust’s fees, etc.
s.sch014 Making good of detriment; compensation and indemnity, etc.
s.sch014 Arbitration
s.sch014 Capitalised sums
s.sch014 As built drawings
s.sch014 Decommissioning
s.sch014 Application
s.sch014 Acquisition of Apparatus
s.sch014 Removal of Apparatus and Rights for Alternative Apparatus
s.sch014 Facilities and Rights for Alternative Apparatus
s.sch014 Retained Apparatus and Alternative Apparatus: protection
s.sch014 Cathodic protection testing
s.sch014 Expenses
s.sch014 Damage to property and other losses
s.sch014 This Part of this Schedule does not apply to—
s.sch014 Insurance
s.sch014 Co-operation and reasonableness
s.sch014 Emergency circumstances
s.sch014 Dispute Resolution
s.sch014 Miscellaneous
s.sch014 Interpretation
s.sch014 Site visits
s.sch014 Costs
s.sch014 Arbitration
s.sch014 The provisions of this Part apply for the protection of...
s.sch014 Nothing in this Part of this Schedule affects the provisions...
s.sch014 In this Part— “apparatus” means the cables, structures or other...
s.sch014 The consent of Tillbridge under this Part is not required...
s.sch014 Where conditions are included in any consent granted by Tillbridge...
s.sch014 The undertaker must not under the powers of this Order...
s.sch014 (1) The undertaker must not under the powers of this...
s.sch014 (1) The undertaker must give to Tillbridge not less than...
s.sch014 The undertaker must at all reasonable times during construction of...
s.sch014 (1) After the purpose of any temporary works has been...
s.sch014 If in consequence of the exercise of the powers conferred...
s.sch014 The undertaker must not exercise the powers conferred by this...
s.sch014 The provisions of this Part of this Schedule have effect...
s.sch014 To ensure its compliance with this Part, the undertaker must...
s.sch014 The undertaker and Tillbridge must each act in good faith...
s.sch014 The undertaker must pay to Tillbridge the reasonable expenses incurred...
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason...
s.sch014 Any dispute arising between the undertaker and Tillbridge under this...
s.sch014 Application
s.sch014 Interpretation
s.sch014 On Street Apparatus
s.sch014 Apparatus of EDF in temporarily closed streets
s.sch014 Protective works to buildings
s.sch014 In this Part of this Schedule— “authorised development” has the...
s.sch014 Acquisition of land
s.sch014 Removal of apparatus
s.sch014 Facilities and rights for alternative apparatus
s.sch014 Retained apparatus: protection
s.sch014 Expenses
s.sch014 Indemnity
s.sch014 Enactments and agreements
s.sch014 Co-operation
s.sch014 Access
s.sch014 Arbitration
s.sch014 In this part of this Schedule— “alternative apparatus” means alternative...
s.sch014 (1) Before commencing construction of a specified work, the undertaker...
s.sch014 Notices
s.sch014 For the protection of Northern Powergrid (Yorkshire) Plc the following...
s.sch014 In this Part of this Schedule— “1991 Act” means the...
s.sch014 This Part of this Schedule does not apply to apparatus...
s.sch014 Regardless of the temporary prohibition or restriction of use of...
s.sch014 Regardless of any provision in the Order or anything shown...
s.sch014 Regardless of any provision in the Order or anything shown...
s.sch014 (1) If, in the exercise of the powers conferred by...
s.sch014 (1) Where in accordance with the provisions of this Part...
s.sch014 (1) Not less than twenty-eight working days before starting the...
s.sch014 Without limiting the scope of paragraph ‎20, the requirements which...
s.sch014 (1) Subject to the following provisions of this paragraph, the...
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason...
s.sch014 Nothing in this Part of this Schedule affects the provisions...
s.sch014 Any difference under the provisions of this Part of this...
s.sch014 Where in consequence of the proposed construction of any of...
s.sch014 The plans submitted to Northern Powergrid by the undertaker pursuant...
s.sch014 Prior to carrying out any works within the Order limits,...
s.sch014 Where practicable, the undertaker and Northern Powergrid will make reasonable...
s.sch014 For the protection of Uniper as referred to in this...
s.sch014 In this part of this Schedule— “acceptable credit provider” means...
s.sch014 (1) Subject to sub-paragraph ‎(2), any specified work, and all...
s.sch014 Except for paragraphs 221 (apparatus of Uniper in temporarily closed...
s.sch014 Apparatus of Uniper in temporarily closed streets
s.sch014 Protective works to buildings
s.sch014 Acquisition of land
s.sch014 Retained apparatus
s.sch014 Removal or replacement of apparatus
s.sch014 Expenses
s.sch014 Indemnity
s.sch014 Co-operation
s.sch014 Access
s.sch014 If by reason of the construction of a specified work...
s.sch014 Confidentiality
s.sch014 Arbitration
s.sch014 Notices
s.sch014 The undertaker must make reasonable compensation for costs, charges and...
s.sch014 (1) The undertaker must make reasonable compensation for liabilities, costs...
s.sch014 Any dispute arising between the undertaker and the drainage authority...
s.sch014 The provisions of this Part apply for the protection of...
s.sch014 In this Part— “apparatus” means the cables, structures or other...
s.sch014 The consent of Cottam under this Part is not required...
s.sch014 This part of this Schedule does not apply to apparatus...
s.sch014 Where conditions are included in any consent granted by Cottam...
s.sch014 (1) The undertaker must not under the powers of this...
s.sch014 (1) The undertaker must give to Cottam not less than...
s.sch014 The undertaker must at all reasonable times during construction of...
s.sch014 (1) After the purpose of any temporary works has been...
s.sch014 If in consequence of the exercise of the powers conferred...
s.sch014 The undertaker must not exercise the powers conferred by this...
s.sch014 To ensure its compliance with this Part, the undertaker must...
s.sch014 Regardless of the temporary prohibition or restriction of use of...
s.sch014 The undertaker must pay to Cottam the reasonable expenses incurred...
s.sch014 Any dispute arising between the undertaker and Cottam under this...
s.sch014 The provisions of this Part apply for the protection of...
s.sch014 In this Part— “apparatus” means the cables, structures or other...
s.sch014 The consent of West Burton under this Part is not...
s.sch014 Where conditions are included in any consent granted by West...
s.sch014 The undertaker must not under the powers of this Order...
s.sch014 (1) The undertaker must not under the powers of this...
s.sch014 (1) The undertaker must give to West Burton not less...
s.sch014 Regardless of any provision in this Order or anything shown...
s.sch014 The undertaker must at all reasonable times during construction of...
s.sch014 (1) After the purpose of any temporary works has been...
s.sch014 If in consequence of the exercise of the powers conferred...
s.sch014 The undertaker must not exercise the powers conferred by this...
s.sch014 To ensure its compliance with this Part, the undertaker must...
s.sch014 The undertaker and West Burton must each act in good...
s.sch014 The undertaker must pay to West Burton the reasonable expenses...
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason...
s.sch014 Any dispute arising between the undertaker and West Burton under...
s.sch014 Application
s.sch014 (1) If, in the exercise of the powers conferred by...
s.sch014 Interpretation
s.sch014 On street apparatus
s.sch014 Apparatus in temporarily closed streets
s.sch014 Protective works to buildings
s.sch014 Acquisition of land
s.sch014 Removal of apparatus
s.sch014 Facilities and rights for alternative apparatus
s.sch014 Retained apparatus
s.sch014 Expenses and costs
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason...
s.sch014 (1) Where, in accordance with the provisions of this part...
s.sch014 Cooperation
s.sch014 Where the undertaker identifies any apparatus which they have reason...
s.sch014 Nothing in this Part of this Schedule affects the provisions...
s.sch014 The undertaker and Anglian Water may by written agreement substitute...
s.sch014 Application
s.sch014 Interpretation
s.sch014 Precedence of 1991 Act in respect of apparatus in streets
s.sch014 No acquisition except by agreement
s.sch014 Removal of apparatus
s.sch014 Facilities and rights for alternative apparatus
s.sch014 (1) Not less than 28 days before starting the execution...
s.sch014 Retained apparatus
s.sch014 Expenses and costs
s.sch014 (1) Subject to sub-paragraphs ‎(2) and ‎(3), if by reason...
s.sch014 Expert Determination
s.sch014 The following provisions apply for the protection of the Agency...
s.sch014 In this Part of this Schedule— “Agency” means the Environment...
s.sch014 Submission and approval of plans
s.sch014 Construction of protective works
s.sch014 Timing of works and service of notices
s.sch014 Works not in accordance with this Part of this Schedule
s.sch014 (1) Subject to the following provisions of this paragraph, the...
s.sch014 Maintenance of works
s.sch014 Remediating impaired drainage work
s.sch014 Agency access
s.sch014 Free passage of fish
s.sch014 Indemnity
s.sch014 (1) The undertaker is responsible for and indemnifies the Agency...
s.sch014 Disputes
s.sch014 Application
s.sch014 Interpretation
s.sch014 On Street Apparatus
s.sch015 Interpretation
s.sch015 Applications made under requirement
s.sch015 Further information and consultation
s.sch015 Appeals
s.sch015 Fees

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.