UK Statutory Instrument 2024 United Kingdom

The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024

At a glance

What's here

1 compliance obligation

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

Browse 88 other Schedules — structural / supplementary
s.sch002

Commencement of the authorised development

s.sch002

Surface water drainage

s.sch002

Flood risk mitigation

s.sch002

Ground conditions

s.sch002

Archaeology

s.sch002

Construction environmental management plan

s.sch002

Construction traffic management plan

s.sch002

Construction worker travel plan

s.sch002

Control of noise during operation

s.sch002

Decommissioning environmental management plan

s.sch002

Decommissioning traffic management plan

s.sch002

Phasing of the authorised development

s.sch002

Local liaison committee

s.sch002

Local employment plan

s.sch002

Notice of date of full commissioning

s.sch002

Requirement for written approval

s.sch002

Approved details and amendments to them

s.sch002

Detailed design approval

s.sch002

Provision of landscape and biodiversity mitigation and enhancement

s.sch002

External lighting during operation

s.sch002

Highway accesses during construction

s.sch003

The following provisions do not apply in so far as...

s.sch008

Interpretation

s.sch009

Compensation enactments

s.sch009

(1) Without limitation on the scope of paragraph 1, the...

s.sch009

(1) Without limitation on the scope of paragraph 1, the...

s.sch009

Application of Part 1 of the 1965 Act

s.sch009

(1) The modifications referred to in paragraph 4(a) are as...

s.sch011

Interpretation

s.sch011

Applications made under requirement

s.sch011

Further information and consultation

s.sch011

Fees

s.sch011

Appeals

s.sch012

For the protection of the utility undertakers referred to in...

s.sch012

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch012

Nothing in this Part of this Schedule affects the provisions...

s.sch012

Where the execution of works is required pursuant to paragraphs...

s.sch012

(1) For the protection of any operator, the following provisions...

s.sch012

The exercise of the powers of article 27 (statutory undertakers)...

s.sch012

(1) Subject to sub-paragraphs (2) to (4), if as the...

s.sch012

This Part of this Schedule does not apply to—

s.sch012

Nothing in this Part of this Schedule affects the provisions...

s.sch012

The undertaker must not exercise the powers granted under this...

s.sch012

Application

s.sch012

In this Part of this Schedule— “alternative apparatus” means alternative...

s.sch012

Interpretation

s.sch012

On Street Apparatus

s.sch012

Apparatus of National Grid in affected streets

s.sch012

Protective works to buildings

s.sch012

Acquisition of land

s.sch012

Removal of apparatus

s.sch012

Facilities and rights for alternative apparatus

s.sch012

Retained apparatus: protection

s.sch012

Expenses

s.sch012

Indemnity

s.sch012

This Part of this Schedule does not apply to apparatus...

s.sch012

Enactments and agreements

s.sch012

Co-operation

s.sch012

Access

s.sch012

Arbitration

s.sch012

Notices

s.sch012

Application etc.

s.sch012

Interpretation

s.sch012

General

s.sch012

Notwithstanding the limits of deviation permitted pursuant to article 3...

s.sch012

References to any standards, manuals, contracts, regulations and directives including...

s.sch012

Regardless of the temporary prohibition or restriction of use of...

s.sch012

Works outside the Order limits

s.sch012

Prior approvals and security

s.sch012

Construction of the specified works

s.sch012

Payments

s.sch012

Provisional Certificate

s.sch012

Opening

s.sch012

Final condition survey

s.sch012

Defects Period

s.sch012

Final Certificate

s.sch012

Security

s.sch012

Regardless of any provision in this Order or anything shown...

s.sch012

Commuted sums

s.sch012

Insurance

s.sch012

Indemnity

s.sch012

Maintenance of the specified works

s.sch012

Land

s.sch012

Expert Determination

s.sch012

(1) If, in the exercise of the powers conferred by...

s.sch012

(1) Where, in accordance with the provisions of this Part...

s.sch012

(1) Not less than 28 days before starting the execution...

s.sch012

(1) Subject to the following provisions of this paragraph, the...

s.art016

Authority to survey and investigate the land

  • Undertaker must give 14 days' notice before entering land for surveys
Browse 42 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent etc. granted by this Order

s.art004

Maintenance of authorised development

s.art005

Operation of authorised development

s.art006

Benefit of the Order

s.art007

Consent to transfer benefit of the Order

s.art008

Application and modification of statutory provisions

s.art009

Street Works

s.art010

Power to alter layout, etc., of streets

s.art011

Construction and maintenance of altered streets

s.art012

Temporary closure of public rights of way

s.art013

Access to works

s.art014

Agreements with street authorities

s.art015

Discharge of water

s.art017

Power to override easements and other rights

s.art018

Time limit for exercise of authority to acquire rights compulsorily

s.art019

Compulsory acquisition of rights

s.art020

Private Rights

s.art021

Application of the 1981 Act

s.art022

Acquisition of subsoil only

s.art023

Modification of Part 1 of the Compulsory Purchase Act 1965

s.art024

Rights under or over streets

s.art025

Temporary use of land for constructing the authorised development

s.art026

Temporary use of land for maintaining the authorised development

s.art027

Statutory undertakers

s.art028

Apparatus and rights of statutory undertakers in affected streets

s.art029

Recovery of costs of new connections

s.art030

Compulsory acquisition of land – incorporation of the mineral code

s.art031

Felling or lopping of trees and removal of hedgerows

s.art032

Protective works to buildings

s.art033

Protective provisions

s.art034

Application of landlord and tenant law

s.art035

Operational land for purposes of the 1990 Act

s.art036

Defence to proceedings in respect of statutory nuisance

s.art037

Certification of plans and documents, etc.

s.art038

Service of notices

s.art039

Procedure in relation to certain approvals etc

s.art040

Arbitration

s.art041

Guarantees in respect of payment of compensation

s.art042

Electronic communications

s.art043

Crown rights