UK Statutory Instrument SI 2024/393 United Kingdom

The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker2

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art021 Authority to survey and investigate the land Regulated
  • Give notice, obtain consents, and restore land when surveying for developmentStatutory Undertaker
52 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Maintenance of authorised development
s.art005 Limits of deviation
s.art006 Benefit of the Order
s.art007 Consent to transfer benefit of the Order
s.art008 Planning Permission
s.art009 Application of the 1990 Act
s.art010 Application of the Community Infrastructure Levy Regulations 2010
s.art011 Street works
s.art012 Application of the 1991 Act
s.art013 Power to alter layout, etc. of streets
s.art014 Temporary closure of streets, cycle tracks and public rights of way
s.art015 Use of private roads for construction
s.art016 Access to works
s.art017 Construction, alteration and maintenance of streets
s.art018 Agreements with street authorities
s.art019 Discharge of water
s.art020 Protective work to land, buildings, structures, apparatus or equipment
s.art022 Compulsory acquisition of land
s.art023 Compulsory acquisition of land – incorporation of the mineral code
s.art024 Time limit for exercise of authority to acquire land and rights compulsorily
s.art025 Compulsory acquisition of rights
s.art026 Extinguishment and suspension of private rights
s.art027 Extinguishment of private rights and restrictive covenants relating to apparatus removed from land subject to temporary possession
s.art028 Power to override easements and other rights
s.art029 Disregard of certain interests and improvements
s.art030 Set-off for enhancement in value of retained land
s.art031 No double recovery
s.art032 Modification of Part 1 of the 1965 Act
s.art033 Application of the 1981 Act
s.art034 Acquisition of subsoil or airspace only
s.art035 Use of subsoil under or airspace over streets
s.art036 Temporary use of land by National Grid
s.art037 Temporary use of land by NPG
s.art038 Temporary use of land by NGN
s.art039 Temporary use of land for maintaining the authorised development
s.art040 Statutory undertakers
s.art041 Recovery of costs of new connections
s.art042 Application of landlord and tenant law
s.art043 Defence to proceedings in respect of statutory nuisance
s.art044 Maintenance of drainage works
s.art045 Traffic regulation
s.art046 Felling or lopping of trees and removal of hedgerows
s.art047 Protection of interests
s.art048 Certification of plans, etc.
s.art049 Service of notices
s.art050 Procedure regarding certain approvals, etc.
s.art051 Amendment of local legislation
s.art052 Arbitration
s.art053 Temporary closure of, and works in, the river Ouse
Schedules

Schedules

1 of 169 shown
s.sch015 (1) Subject to sub-paragraphs (2) to (3), if as the... Regulated
  • Pay costs of repairing damage to electronic communications apparatus caused by constructionStatutory Undertaker
168 other schedules
s.sch003 Interpretation
s.sch003 Replacement planting
s.sch003 Reinstatement schemes
s.sch003 Contamination of land or groundwater and controlled waters
s.sch003 Removal of temporary bridges and culverts
s.sch003 Highway works
s.sch003 Removal of existing overhead line
s.sch003 Decommissioning
s.sch003 Clearance over the River Ouse
s.sch003 Approval of details having regard to the Design Approach to Site Specific Infrastructure
s.sch003 Site specific mitigation scheme
s.sch003 Time limits
s.sch003 Design drawings
s.sch003 Stages of authorised development
s.sch003 Construction management plans
s.sch003 Construction management plans to be approved
s.sch003 Construction hours
s.sch003 Landscaping at Overton, Tadcaster and Monk Fryston
s.sch003 Retention and protection of existing trees
s.sch004 Applications made under requirements
s.sch004 Fees
s.sch004 Appeals
s.sch004 Outcome of appeals
s.sch004 Interpretation of Schedule 4
s.sch005 NPG may not carry out the NPG Works under sub-paragraph...
s.sch005 Article 52 (arbitration) has effect in relation to any dispute...
s.sch005 If NPG fails to carry out any of the NPG...
s.sch005 On the date specified in any notice under paragraph (2)...
s.sch005 Where a notice is issued under paragraph (2), paragraph (3)...
s.sch005 NGN may not carry out the NGN Works under sub-paragraph...
s.sch005 If NGN fails to carry out any of the NGN...
s.sch005 On the date specified in any notice under paragraph (6)...
s.sch005 Where a notice is issued under paragraph (6), paragraph (7)...
s.sch005 The exercise by NPG or NGN of any benefits or...
s.sch010 Compensation enactments
s.sch010 (1) Without limitation on the scope of paragraph 1, the...
s.sch010 Application of the 1965 Act
s.sch010 For section 7 of the 1965 Act (measure of compensation)...
s.sch010 For section 8 of the 1965 Act (provisions as to...
s.sch010 The following provisions of the 1965 Act (which state the...
s.sch010 Section 11 of the 1965 Act (powers of entry) is...
s.sch010 Section 20 of the 1965 Act (protection for interests of...
s.sch010 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch015 For the protectionof the statutory undertakers referred to in this...
s.sch015 This Part of this Schedule does not apply to—
s.sch015 Apparatus of Statutory undertaker in affected streets
s.sch015 Acquisition of land
s.sch015 Removal or diversion of apparatus
s.sch015 Facilities and rights for alternative apparatus
s.sch015 Retained apparatus: protection
s.sch015 Expenses
s.sch015 Enactments and agreements
s.sch015 Co-operation
s.sch015 Access
s.sch015 Arbitration
s.sch015 Nothing in this Part of this Schedule affects the provisions...
s.sch015 Works falling outside of development authorised by the Order
s.sch015 Cathodic protection testing
s.sch015 Interpretation
s.sch015 Notice to be given prior to specified works
s.sch015 Fencing
s.sch015 Survey of waterway
s.sch015 Approval of plans etc.
s.sch015 Failure to complete specified works
s.sch015 Lighting
s.sch015 Construction of specified works
s.sch015 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch015 Access to work – provision of information
s.sch015 Maintenance of works
s.sch015 Repayment of the Trust’s fees, etc.
s.sch015 Making good of detriment; compensation and indemnity, etc.
s.sch015 Arbitration
s.sch015 As built drawings
s.sch015 The provisions of this Part of this Schedule have effect,...
s.sch015 In this Part of this Schedule— “asset protection agreement” means...
s.sch015 (1) Where under this Part of this Schedule Network Rail...
s.sch015 (1) Subject to sub-paragraph (2) the undertaker must not exercise...
s.sch015 This Part of this Schedule does not apply to apparatus...
s.sch015 (1) The undertaker must before commencing construction of any specified...
s.sch015 (1) Any specified work and any protective works to be...
s.sch015 The undertaker must— (a) at all times afford reasonable facilities...
s.sch015 Network Rail must at all times afford reasonable facilities to...
s.sch015 (1) If any permanent or temporary alterations or additions to...
s.sch015 The undertaker must repay to Network Rail all reasonable fees,...
s.sch015 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch015 If at any time after the completion of a specified...
s.sch015 The undertaker must not provide any illumination or illuminated sign...
s.sch015 Any additional expenses which Network Rail may reasonably incur in...
s.sch015 (1) If, in the exercise of the powers conferred by...
s.sch015 (1) The undertaker must pay to Network Rail all reasonable...
s.sch015 Network Rail must, on receipt of a request from the...
s.sch015 In the assessment of any sums payable to Network Rail...
s.sch015 The undertaker and Network Rail may, subject in the case...
s.sch015 Nothing in this Order, or in any enactment incorporated with...
s.sch015 The undertaker must give written notice to Network Rail if...
s.sch015 The undertaker must no later than 28 days from the...
s.sch015 For the protection of Northern Powergrid the following provisions have...
s.sch015 In this Part of this Schedule— “1991 Act” means the...
s.sch015 This Part of this Schedule does not apply to apparatus...
s.sch015 (1) Not less than 28 days before starting the execution...
s.sch015 Regardless of any provision in this Order or anything shown...
s.sch015 (1) If, in the exercise of the powers conferred by...
s.sch015 (1) Where, in accordance with the provisions of this Part...
s.sch015 (1) Not less than 48 days before starting the execution...
s.sch015 (1) Subject to the following provisions of this paragraph, the...
s.sch015 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch015 Nothing in this Part of this Schedule affects the provisions...
s.sch015 Where in consequence of the proposed construction of any of...
s.sch015 If in consequence of an agreement reached in accordance with...
s.sch015 The plans submitted to Northern Powergrid by the undertaker pursuant...
s.sch015 (1) Subject to the following provisions of this paragraph, the...
s.sch015 Where practicable, the undertaker and Northern Powergrid will make reasonable...
s.sch015 Application etc.,
s.sch015 Interpretation
s.sch015 General
s.sch015 Notwithstanding the limits of deviation permitted pursuant to article 5...
s.sch015 References to any standards, manuals, contracts, regulations and directives including...
s.sch015 Works outside the Order limits
s.sch015 Prior approvals and security
s.sch015 Construction of the specified works
s.sch015 Payments
s.sch015 (1) For the protection of any operator, the following provisions,...
s.sch015 Provisional Certificate
s.sch015 Opening
s.sch015 Final condition survey
s.sch015 Defects Period
s.sch015 Final Certificate
s.sch015 Security
s.sch015 Insurance
s.sch015 Indemnity
s.sch015 Maintenance of the specified works
s.sch015 Land
s.sch015 The exercise of the powers of article 40 (statutory undertakers)...
s.sch015 Arbitration
s.sch015 Application
s.sch015 Interpretation
s.sch015 On Street Apparatus
s.sch015 Apparatus of NGT in affected streets
s.sch015 Protective works to buildings
s.sch015 Acquisition of land
s.sch015 Removal of apparatus
s.sch015 Facilities and rights for alternative apparatus
s.sch015 Retained apparatus: protection
s.sch015 Expenses
s.sch015 Indemnity
s.sch015 Enactments and agreements
s.sch015 Co-operation
s.sch015 Access
s.sch015 Arbitration
s.sch015 Notices
s.sch015 Application
s.sch015 Interpretation
s.sch015 Except for paragraphs 100 (apparatus of Statutory undertaker in affected...
s.schedule/1/crossheading/osbaldwick/substation_para Work No. 1 – Osbaldwick Substation and YR overhead electric line
s.schedule/1/crossheading/overhead/electric/lines/an Work No. 10 – XC overhead electric line
s.schedule/1/crossheading/overhead/electric/lines/an Work No. 11 – Monk Fryston Substation
s.schedule/1/crossheading/overhead/electric/lines/an Work No. 2 – YR/2TW overhead electric line and YN overhead electric line
s.schedule/1/crossheading/overhead/electric/lines/mo Work No. 7 – XC overhead electric line
s.schedule/1/crossheading/overhead/electric/lines/mo Work No. U6
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. 8 – XC and XD overhead electric lines
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U7
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U8
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. 9 – XC overhead electric line
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U9
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U10
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U11
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U12
s.schedule/1/crossheading/overhead/electric/lines/ta Work No. U13

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.