UK Statutory Instrument SI 2024/1014 United Kingdom

The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker4

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art026 Authority to survey and investigate the land Regulated
  • Serve notice and compensate when entering land for surveysStatutory Undertaker
41 other provisions — procedural and definitional
s.art001 Citation and Commencement
s.art002 Interpretation
s.art003 Disapplication and modification of legislative provisions
s.art004 Incorporation of the 1847 Act
s.art005 Development consent etc. granted by the Order
s.art006 Maintenance of authorised development
s.art007 Limits of deviation
s.art008 Benefit of Order
s.art009 Transfer of benefit of Order, etc.
s.art010 Compulsory acquisition of rights
s.art011 Time limit for exercise of powers of compulsory acquisition
s.art012 Private rights over land
s.art013 Power to override easements and other rights
s.art014 Modification of Part 1 of the 1965 Act
s.art015 Application of the 1981 Act
s.art016 Statutory undertakers and operator of the electronic communications code network
s.art017 Recovery of costs of new connection
s.art018 Disregard of certain interests and improvements
s.art019 Set-off for enhancement in value of retained land
s.art020 No double recovery
s.art021 Operation and use of development
s.art022 Power to appropriate
s.art023 Planning legislation
s.art024 Discharge of water
s.art025 Powers to dredge
s.art027 Protective works to buildings
s.art028 Agreement with highway authority
s.art029 Defence to proceedings in respect of statutory nuisance
s.art030 Deemed marine licence
s.art031 Trees subject to a tree preservation order
s.art032 Application of landlord and tenant law
s.art033 Certification of plans and documents etc.
s.art034 Service of notices
s.art035 Arbitration
s.art036 Saving for Trinity House
s.art037 Provision against danger to navigation
s.art038 Lights on tidal works during construction
s.art039 Permanent light on tidal works
s.art040 Crown rights
s.art041 Protective provisions
s.art042 Byelaws relating to the authorised development
Schedules

Schedules

3 of 200 shown
s.sch003 Concrete and cement Regulated
  • Do not discharge concrete waste into marine environment; contain mixing areas 10m from waterStatutory Undertaker
s.sch003 Notice to Mariners Regulated
  • Issue Notice to Mariners before licensed activitiesStatutory Undertaker
s.sch004 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay for damage to or interruption of electronic communications servicesStatutory Undertaker
197 other schedules
s.sch002 Interpretation
s.sch002 Noise insulation
s.sch002 Woodland management
s.sch002 East Gate Improvements
s.sch002 Operational freight management plan
s.sch002 Lighting plan
s.sch002 Flood risk assessment
s.sch002 Contaminated land
s.sch002 Materials Management Plan
s.sch002 Impact Protection Measures for the IOT trunkway
s.sch002 Impact Protection Measures for the IOT finger pier
s.sch002 Time limit for commencement of the authorised development
s.sch002 Amending the Port of Immingham Marine Operations Manual
s.sch002 Interpretation
s.sch002 Applications made under requirements
s.sch002 Further information regarding requirements
s.sch002 Appeals
s.sch002 Anticipatory steps towards compliance with any requirement
s.sch002 Amendments to approved details
s.sch002 Construction hours – onshore works
s.sch002 Travel plan
s.sch002 Piling and marine construction works restrictions
s.sch002 External appearance and height of the authorised development
s.sch002 Onshore construction environmental management plan
s.sch002 Surface water drainage
s.sch003 Interpretation
s.sch003 Marine written scheme of archaeological investigation
s.sch003 Offshore Construction Environmental Management Plan
s.sch003 Piling and marine construction works
s.sch003 Percussive piling reporting protocol
s.sch003 Coatings and treatment
s.sch003 Pollution and Spills
s.sch003 Disposal at Sea
s.sch003 Sediment sampling
s.sch003 The material to be disposed of within the disposal sites...
s.sch003 Contacts
s.sch003 During the course of disposal at sea, deposited material must...
s.sch003 Dropped objects
s.sch003 A copy of the notice must be provided to the...
s.sch003 Meaning of “application”
s.sch003 Further information regarding application
s.sch003 Determination of application
s.sch003 Notice of determination
s.sch003 Licensed marine activities
s.sch003 Licence to dredge and deposit
s.sch003 Details of licensed marine activities
s.sch003 Notifications regarding licensed activities
s.sch003 Agents / contractors / sub-contractors
s.sch003 Cold weather construction restriction strategy
s.sch003 Marine Noise Registry
s.sch004 Interpretation
s.sch004 Protective action
s.sch004 Interpretation
s.sch004 Protective works to buildings
s.sch004 Acquisition of land
s.sch004 Removal of apparatus
s.sch004 Facilities and rights for alternative apparatus
s.sch004 Retained apparatus: protection of Cadent
s.sch004 Expenses
s.sch004 Indemnity
s.sch004 Enactments and agreements
s.sch004 Co-operation
s.sch004 Abandoned or decayed works
s.sch004 For the avoidance of doubt whenever Cadent’s consent, agreement or...
s.sch004 Access
s.sch004 Arbitration
s.sch004 Notices
s.sch004 Application
s.sch004 Interpretation
s.sch004 The exercise of the powers of article 16 (statutory undertakers...
s.sch004 This Part of this Schedule does not apply to—
s.sch004 Nothing in this Part of this Schedule affects the provisions...
s.sch004 Facilities for navigation
s.sch004 Application
s.sch004 Interpretation
s.sch004 Consultation and notification
s.sch004 Indemnity
s.sch004 Operations
s.sch004 Disputes
s.sch004 Application
s.sch004 Interpretation
s.sch004 Cooperation
s.sch004 Notice of and consultation on works and vessel movements
s.sch004 Sedimentation, etc.: remedial action
s.sch004 Any operations for the construction of any specified work, once...
s.sch004 Indemnity
s.sch004 Arbitration
s.sch004 Application
s.sch004 Interpretation
s.sch004 The undertaker must not make any opening into or connections...
s.sch004 Without limiting paragraph 135, the requirements which the Board may...
s.sch004 (1) Subject to sub–-paragraph (2), any specified work, and all...
s.sch004 If by reason of the construction of the authorised development...
s.sch004 If the Board considers that, as a direct result of...
s.sch004 Indemnity
s.sch004 The undertaker must compensate the Board in respect of all...
s.sch004 Without limiting the other provisions of this Part of this...
s.sch004 The fact that any work or thing has been executed...
s.sch004 Any dispute between the undertaker and the Board under this...
s.sch004 Statutory functions
s.sch004 Operating procedures
s.sch004 Oil Spillage Plan
s.sch004 Application
s.sch004 (1) Prior to the commencement of any specified work, the...
s.sch004 General
s.sch004 The undertaker must ensure— (a) that the authorised development including...
s.sch004 On completion of the works, all debris and surplus material...
s.sch004 The undertaker must bring the conditions contained in paragraphs 19...
s.sch004 Any dispute arising between the undertaker and the Agency under...
s.sch004 Application
s.sch004 Interpretation
s.sch004 Acquisition of apparatus
s.sch004 Relevant Works
s.sch004 Expenses
s.sch004 Damage to property and other losses
s.sch004 Tidal Works: approval of detailed design
s.sch004 (1) Where in consequence of the proposed construction of any...
s.sch004 Miscellaneous
s.sch004 Any dispute arising between the Undertaker and Exolum under this...
s.sch004 Emergency circumstances
s.sch004 Application
s.sch004 Interpretation
s.sch004 Acquisition of apparatus
s.sch004 Expenses
s.sch004 Damage to property and other losses
s.sch004 Co-operation and reasonableness
s.sch004 Commencement of Tidal Works
s.sch004 Miscellaneous
s.sch004 Emergency circumstances
s.sch004 Application
s.sch004 Interpretation
s.sch004 Acquisition of Land
s.sch004 Removal of Apparatus
s.sch004 Facilities and rights for alternative apparatus
s.sch004 Retained apparatus
s.sch004 Expenses and costs
s.sch004 Damage to property and other losses
s.sch004 Discharges, etc.
s.sch004 Nothing in this Part of this Schedule affects the provisions...
s.sch004 Cooperation
s.sch004 If in consequence of an agreement reached in accordance with...
s.sch004 The plans submitted to Northern Powergrid by the undertaker pursuant...
s.sch004 Where practicable, the undertaker and Northern Powergrid will make reasonable...
s.sch004 Application
s.sch004 Interpretation
s.sch004 Protective works to buildings
s.sch004 Acquisition of land
s.sch004 Removal of apparatus
s.sch004 Obstruction in river
s.sch004 Facilities and rights for alternative apparatus
s.sch004 Retained apparatus
s.sch004 Expenses and costs
s.sch004 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch004 Cooperation
s.sch004 Where the undertaker identifies any apparatus which may belong to...
s.sch004 Nothing in this Part of this Schedule affects the provisions...
s.sch004 The undertaker and Anglian Water may by written agreement substitute...
s.sch004 Application
s.sch004 Interpretation
s.sch004 Removal etc. of the Statutory Conservancy and Navigation Authority ’s moorings and buoys
s.sch004 (1) Where under this Part of this Schedule Network Rail...
s.sch004 (1) The undertaker must not exercise the powers conferred by—...
s.sch004 (1) The undertaker must, before commencing construction of any specified...
s.sch004 (1) Any specified work and any protective works to be...
s.sch004 The undertaker must— (a) at all times afford reasonable facilities...
s.sch004 Network Rail must at all times afford reasonable facilities to...
s.sch004 (1) If any permanent or temporary alterations or additions to...
s.sch004 The undertaker must repay to Network Rail all reasonable fees,...
s.sch004 If at any time after the completion of a specified...
s.sch004 The undertaker must not provide any illumination or illuminated sign...
s.sch004 Navigational lights, buoys, etc.
s.sch004 Any additional expenses which Network Rail may reasonably incur in...
s.sch004 (1) The undertaker must pay to Network Rail all reasonable...
s.sch004 Network Rail must, on receipt of a request from the...
s.sch004 In the assessment of any sums payable to Network Rail...
s.sch004 Nothing in this Order, or in any enactment incorporated with...
s.sch004 The undertaker must give written notice to Network Rail where...
s.sch004 The undertaker must no later than 28 days from the...
s.sch004 Any dispute arising between the undertaker and Network Rail under...
s.sch004 Application
s.sch004 Interpretation
s.sch004 Removal of temporary works
s.sch004 (1) Before beginning to construct any specified work, the undertaker...
s.sch004 Without limitation on the scope of paragraph 90 the requirements...
s.sch004 (1) Subject to sub-paragraph (2), any specified work, and all...
s.sch004 (1) Subject to sub-paragraph 2 the undertaker must from the...
s.sch004 Subject to paragraph 93, if by reason of the construction...
s.sch004 (1) The undertaker must indemnify North East Lincolnshire Council in...
s.sch004 (1) Without affecting the other provisions of this Part of...
s.sch004 The fact that any work or thing has been executed...
s.sch004 Any dispute arising between the undertaker and North East Lincolnshire...
s.sch004 Application
s.sch005 The enactments for the time being in force with respect...
s.sch005 (1) Without limitation on the scope of paragraph 1, the...
s.sch005 (1) Without limitation on the scope of paragraph 1, the...
s.sch005 Application of Part 1 of the 1965 Act
s.sch005 (1) The modifications referred to in paragraph 4(a) are as...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.