UK Statutory Instrument SI 2022/922 United Kingdom

The Manston Airport Development Consent Order 2022

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker2

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art018 Authority to survey and investigate the land Regulated
  • Serve at least 14 days' notice before entering land to survey or investigateStatutory Undertaker
42 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Maintenance of authorised development
s.art005 Maintenance of drainage works
s.art006 Limits of deviation
s.art007 Benefit of Order
s.art008 Consent to transfer benefit of Order
s.art009 Guarantees in respect of payment of compensation, etc.
s.art010 Application of the 1991 Act
s.art011 Construction and maintenance of new, altered or diverted streets
s.art012 Temporary stopping up and restriction of use of streets
s.art013 Permanent stopping up of public rights of way
s.art014 Access to works
s.art015 Traffic regulation
s.art016 Discharge of water
s.art017 Protective work to buildings
s.art019 Compulsory acquisition of land
s.art020 Compulsory acquisition of land – incorporation of the mineral code
s.art021 Time limit for exercise of authority to acquire land compulsorily
s.art022 Compulsory acquisition of rights
s.art023 Subsoil or new rights only to be acquired in certain land
s.art024 Private rights over land
s.art025 Modification of Part 1 of the 1965 Act
s.art026 Application of the 1981 Act
s.art027 Acquisition of subsoil or airspace only
s.art028 Rights under or over streets
s.art029 Temporary use of land for carrying out the authorised development
s.art030 Temporary use of land for maintaining the authorised development
s.art031 Statutory undertakers
s.art032 Apparatus and rights of statutory undertakers in stopped-up streets
s.art033 Recovery of costs of new connections
s.art034 Felling or lopping of trees and removal of hedgerows
s.art035 Abrogation of agreement
s.art036 Application of landlord and tenant law
s.art037 Removal of human remains
s.art038 Defence to proceedings in respect of statutory nuisance
s.art039 Protection of interests
s.art040 Crown rights
s.art041 Certification of documents, etc.
s.art042 Service of notices
s.art043 Arbitration
Schedules

Schedules

1 of 69 shown
s.sch009 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay for damage to telecoms apparatus caused by the developmentStatutory Undertaker
68 other schedules
s.sch002 In this Schedule— “bellyhold” means the cargo hold of a...
s.sch002 (1) No part of the authorised development is to commence,...
s.sch002 (1) In the event that land affected by contamination, including...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) No operations consisting of piling or other intrusive works...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 With respect to any requirement which requires the authorised development...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) Work Nos. 15, 16 and 17 must only be...
s.sch002 The authorised development must commence no later than the expiration...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) The operation of the airport is subject to—
s.sch002 Work Nos. 26 to 31 must be completed in accordance...
s.sch002 No part of the authorised development is to begin operation...
s.sch002 (1) No part of the authorised development must commence unless...
s.sch002 (1) Where an application has been made to a relevant...
s.sch002 (1) Where an application is made to a relevant planning...
s.sch002 (1) The undertaker may appeal to the Secretary of State...
s.sch002 (1) On an appeal under paragraph 27, the appointed person...
s.sch002 In Part 2 of Schedule 2— “the appeal parties” means...
s.sch002 (1) No part of the authorised development is to be...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) No part of Work No. 19 is to commence...
s.sch002 (1) No part of the authorised development is to commence...
s.sch002 (1) No part of the authorised development is to begin...
s.sch002 (1) No part of the authorised development may be commenced...
s.sch002 (1) The undertaker must fully implement the noise mitigation plan....
s.sch006 The enactments for the time being in force with respect...
s.sch006 (1) Without limiting paragraph 1, the 1961 Act has effect...
s.sch006 (1) Without limiting paragraph 1, the Land Compensation Act 1973...
s.sch006 Part 1 (compulsory purchase under Acquisition of Land Act 1946)...
s.sch006 (1) The modifications referred to in paragraph 4(a) are as...
s.sch009 The following provisions of this Part of this Schedule have...
s.sch009 (1) Subject to the following provisions of this paragraph, the...
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 Where in consequence of the proposed construction of any of...
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 For the protection of any operator, the following provisions have...
s.sch009 In this Part of this Schedule— “the 2003 Act” means...
s.sch009 The exercise of the powers conferred by article 31 (statutory...
s.sch009 The following provisions of this Part of this Schedule shall...
s.sch009 In this Part of this Schedule— “construction” includes execution, placing,...
s.sch009 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch009 (1) Where under this Part of this Schedule Network Rail...
s.sch009 (1) The undertaker shall before commencing construction of any specified...
s.sch009 (1) Any specified work and any protective works to be...
s.sch009 The undertaker shall— (a) at all times afford reasonable facilities...
s.sch009 Network Rail shall at all times afford reasonable facilities to...
s.sch009 (1) If any permanent or temporary alterations or additions to...
s.sch009 The undertaker shall repay to Network Rail all reasonable fees,...
s.sch009 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch009 If at any time after the completion of a specified...
s.sch009 The undertaker shall not provide any illumination or illuminated sign...
s.sch009 This Part of this Schedule does not apply to apparatus...
s.sch009 Any additional expenses which Network Rail may reasonably and properly...
s.sch009 (1) The undertaker shall pay to Network Rail all reasonable...
s.sch009 Network Rail shall, on receipt of a request from the...
s.sch009 In the assessment of any sums payable to Network Rail...
s.sch009 Nothing in this Order, or in any enactment incorporated with...
s.sch009 Any difference or dispute arising between the undertaker and Network...
s.sch009 (1) Where any street is stopped up under article 13...
s.sch009 The undertaker, in the case of the powers conferred by...
s.sch009 Regardless of any provision in this Order or anything shown...
s.sch009 (1) If, in the exercise of the powers conferred by...
s.sch009 (1) Where, in accordance with the provisions of this Part...
s.sch009 (1) Not less than 28 days before starting the execution...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.