UK Statutory Instrument 2022 United Kingdom

The Sizewell C (Nuclear Generating Station) Order 2022

At a glance

What's here

2 compliance obligations

Who this Act binds

Business-side actors with duties under this Act, ranked by how often they appear.

  • Statutory Undertaker 1

Plus 1 non-business duty on Crown ministers, regulators, local authorities or tribunals — shown collapsed under each section below.

Other Acts binding the same actors

For each actor bound by this Act, the other UK Acts that bind them most often. Useful for understanding the full compliance landscape facing each role.

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch019

Compensation

  • Pay costs and compensation for damage to electronic communications apparatus caused by the development Statutory Undertaker
Browse 190 other Schedules — structural / supplementary
s.sch001

Work No. 1A

s.sch002

Interpretation

s.sch016

Compensation enactments

s.sch016

For Schedule 2A of the 1965 Act substitute— SCHEDULE 2A...

s.sch016

(1) Without limiting the scope of sub-paragraph (1), the Land...

s.sch016

(1) Without limiting the scope of sub-paragraph (1), the 1961...

s.sch016

Application of the 1965 Act

s.sch016

For section 7 of the 1965 Act (Measure of compensation...

s.sch016

The following provisions of the 1965 Act (which state the...

s.sch016

Section 11 of the 1965 Act (Powers of entry) is...

s.sch016

Section 20 of the 1965 Act (Tenants at will, etc)...

s.sch016

Section 22 of the 1965 Act (Interests omitted from purchase)...

s.sch018

Acquisition of necessary wayleaves

s.sch018

Compulsory acquisition of easements or other rights

s.sch018

Interpretation

s.sch018

Court imposition of code rights

s.sch018

Compulsory acquisition of easements or other rights

s.sch018

Interpretation

s.sch018

Compulsory acquisition of easements or other rights

s.sch018

Compulsory acquisition of easements or other rights

s.sch019

Application

s.sch019

Co-operation

s.sch019

Application

s.sch019

Interpretation

s.sch019

Interaction at Sizewell Gap

s.sch019

Interaction at Snape Road

s.sch019

Interaction at Friday Street

s.sch019

Sizewell C proposed intake infrastructure

s.sch019

Acquisition of land

s.sch019

Arbitration

s.sch019

Application

s.sch019

Interpretation

s.sch019

Agreements

s.sch019

Interaction at Sizewell Gap

s.sch019

Interaction at Snape Road

s.sch019

Interaction at Friday Street

s.sch019

Sizewell C proposed intake infrastructure

s.sch019

Acquisition of land

s.sch019

Arbitration

s.sch019

Application

s.sch019

Interpretation

s.sch019

Electronic communications apparatus installed on, under or over any land

s.sch019

Application

s.sch019

Co-operation

s.sch019

Enactments and agreements

s.sch019

The provisions of this Part of this Schedule have effect,...

s.sch019

Interpretation

s.sch019

In this Part of this Schedule— “construction” includes execution, placing,...

s.sch019

(1) Where under this Part of this Schedule Network Rail...

s.sch019

(1) The undertaker must not exercise the powers conferred by—...

s.sch019

(1) The undertaker must before commencing construction of any specified...

s.sch019

(1) Any specified work and any protective works to be...

s.sch019

The undertaker must— (a) at all times afford reasonable facilities...

s.sch019

Network Rail must at all times afford reasonable facilities to...

s.sch019

(1) If any permanent or temporary alterations or additions to...

s.sch019

The undertaker must repay to Network Rail all reasonable fees,...

s.sch019

(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

s.sch019

On-street apparatus

s.sch019

If at any time after the completion of a specified...

s.sch019

The undertaker must not provide any illumination or illuminated sign...

s.sch019

Any additional expenses which Network Rail may reasonably incur in...

s.sch019

(1) The undertaker must pay to Network Rail all reasonable...

s.sch019

Network Rail must, on receipt of a request from the...

s.sch019

In the assessment of any sums payable to Network Rail...

s.sch019

The undertaker and Network Rail may, subject in the case...

s.sch019

Nothing in this Order, or in any enactment incorporated with...

s.sch019

The undertaker must give written notice to Network Rail if...

s.sch019

The undertaker must no later than 28 days from the...

s.sch019

Acquisition of apparatus

s.sch019

In relation to any dispute arising under this Part of...

s.sch019

(1) For the protection of Anglian Water, the following provisions...

s.sch019

Application

s.sch019

Interpretation

s.sch019

Except for paragraphs 45 (Apparatus of National Grid in stopped...

s.sch019

Apparatus of National Grid in stopped up streets

s.sch019

Protective works to buildings

s.sch019

Acquisition of land

s.sch019

Removal of apparatus

s.sch019

Facilities and rights for alternative apparatus

s.sch019

Removal of apparatus

s.sch019

Retained apparatus: Protection of National Grid

s.sch019

Expenses

s.sch019

Indemnity

s.sch019

Enactments and agreements

s.sch019

Co-operation

s.sch019

Access

s.sch019

Arbitration

s.sch019

Notices

s.sch019

For the protection of Essex and Suffolk Water, the following...

s.sch019

In this Part of this Schedule— “Authority” has the meaning...

s.sch019

Facilities and rights for alternative apparatus

s.sch019

The undertaker must not interfere with, build over or near...

s.sch019

The alteration, extension, removal or re-location of any apparatus shall...

s.sch019

In the situation, where in exercise of the powers conferred...

s.sch019

Regardless of any provision in this Order or anything shown...

s.sch019

If in consequence of the exercise of the powers conferred...

s.sch019

If in consequence of the exercise of the powers conferred...

s.sch019

If for any reason or in consequence of the construction...

s.sch019

Any agreement or approval of ESW required under these provisions...

s.sch019

Any dispute arising between the undertaker and ESW under this...

s.sch019

Water Industry Act 1991

s.sch019

Retained apparatus: protection

s.sch019

Supply of potable water to the authorised development

s.sch019

Condition 1

s.sch019

Following satisfaction of paragraph 71, ESW, acting reasonably, has confirmed...

s.sch019

Condition 2

s.sch019

Following satisfaction of paragraph 73, the Secretary of State for...

s.sch019

Following satisfaction of paragraph 74, the Authority has approved the...

s.sch019

Application

s.sch019

Interpretation

s.sch019

Acquisition of Land

s.sch019

Apparatus and/or Service Media of ENGL in stopped up streets

s.sch019

Compensation

s.sch019

Article 5

s.sch019

Discharge or requirements

s.sch019

Service Media plan

s.sch019

Enactments and agreements

s.sch019

Arbitration

s.sch019

Application

s.sch019

Interpretation

s.sch019

Acquisition of Land and Installations

s.sch019

Right of access

s.sch019

Removal of Installations and Execution of Specified Works

s.sch019

Expenses

s.sch019

(1) Not less than 56 working days before the intended...

s.sch019

(1) Following receipt of plans under paragraph 90 of this...

s.sch019

Expenses

s.sch019

NDA and / or Magnox (as applicable) is not required...

s.sch019

In paragraph 93 of this Part “emergency” means works whose...

s.sch019

Indemnity

s.sch019

Enactments and agreements

s.sch019

Co-operation

s.sch019

Arbitration

s.sch019

Installation(s) plan

s.sch021

Interpretation

s.sch021

Local mariners, fishermen’s organisations and the UK Hydrographic Office must...

s.sch021

(1) The undertaker must provide the name, address and function...

s.sch021

(1) The undertaker must notify the MMO in writing of...

s.sch021

The undertaker must ensure that a copy of this licence...

s.sch021

(1) No licenced activity may commence until a CPMMP (marine)...

s.sch021

(1) No licensed activity or phase of licensed activity must...

s.sch021

(1) No licensed activity or phase of licensed activity must...

s.sch021

(1) No licensed activity must commence until a FLCP has...

s.sch021

During construction, operation and maintenance

s.sch021

The storage, handling, transport and use of fuels, lubricants, chemicals...

s.sch021

Addresses

s.sch021

(1) Drill or vibro piling must be used as standard,...

s.sch021

Except for activities taking place below MHWS, concrete and cement...

s.sch021

If concrete is to be sprayed, suitable protective sheeting must...

s.sch021

During licensed activities, all wastes must be stored in designated...

s.sch021

The undertaker must ensure that any equipment, temporary structures, waste...

s.sch021

(1) No gravel or rock may be placed in the...

s.sch021

The undertaker must ensure that any vessels used for rock...

s.sch021

The undertaker must ensure that sea going tugs or tugs...

s.sch021

(1) No vessel movements within the Outer Thames Estuary Special...

s.sch021

(1) The undertaker must report all dropped objects to the...

s.sch021

The provisions of section 72 of the 2009 Act apply...

s.sch021

In the event that any rock or sediment material used...

s.sch021

(1) Cooling water abstraction must not commence until a MAP...

s.sch021

Dredging

s.sch021

(1) No dredging activity or phase of dredging activity must...

s.sch021

(1) Within 4 weeks of the completion of any dredging...

s.sch021

Aids to navigation

s.sch021

Beach Landing Facility and Temporary Marine Bulk Import Facility

s.sch021

Soft Coastal Defence Feature (SCDF)

s.sch021

Combined Drainage Outfall (CDO)

s.sch021

Cooling Water Intake and Outfall Heads, Shafts and Tunnels

s.sch021

(1) Subject to the licence conditions in Part 3 of...

s.sch021

(1) The construction of Work Nos. 2A, 2C and 2E...

s.sch021

(1) The construction of Work Nos. 2A to 2J must...

s.sch021

(1) The construction of Work Nos. 2A to 2J must...

s.sch021

Drill arisings from Work Nos. 2B, 2D and 2F must...

s.sch021

(1) Water abstraction must not commence until a FIEMP has...

s.sch021

(1) Water abstraction must not commence until a SMP has...

s.sch021

(1) Work Nos. 2M, 2N, 2O and 2P must not...

s.sch021

The licensed activities must be carried out in either the...

s.sch021

General

s.sch021

Pre-construction

s.sch021

(1) No licensed activity or phase of activity must be...

s.sch021

(1) The local MMO office and Trinity House must be...

s.sch024

Applications made under requirement

s.sch024

Further information

s.sch024

Fees

s.sch024

Appeals

s.sch024

Definitions

s.sch025

Introduction

s.sch025

Highways Act 1980

s.sch025

Community Infrastructure Levy Regulations 2010

s.sch025

Town and Country Planning Act 1990

s.sch025

Local Government (Miscellaneous Provisions) Act 1976

s.art027

Authority to survey and investigate the land

Other duties (1) — Crown / regulator
  • The undertaker may enter land for surveys after giving 14 days' notice Crown / Minister / Government department
Browse 87 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent etc granted by Order

s.art004

Limits of deviation

s.art005

Effect of the Order on the Sizewell B relocated facilities permissions

s.art006

Maintenance of authorised development

s.art007

Authorisation of use

s.art008

Benefit of Order

s.art009

Consent to transfer benefit of the Order

s.art010

Enforcement of the Deed of Obligation

s.art011

Modification and discharge of Deed of Obligation

s.art012

Defence to proceedings in respect of statutory nuisance

s.art013

Power to alter layout, etc., of streets

s.art014

Street works

s.art015

Application of the 1991 Act

s.art016

Permanent stopping up of streets, change of status, and extinguishment of private means of access

s.art017

Status of public rights of way created or improved

s.art018

Benefit of permanent private means of access and private rights of way created

s.art019

Temporary closure of streets and private means of access

s.art020

Use of private roads for construction

s.art021

Access to works

s.art022

Construction and maintenance of new and altered streets

s.art023

Agreements with street authorities

s.art024

Traffic regulation measures

s.art025

Discharge of water

s.art026

Protective work to buildings

s.art028

Compulsory acquisition of land

s.art029

Compulsory acquisition of land – incorporation of the mineral code

s.art030

Statutory authority to override easements and other rights

s.art031

Time limit for exercise of authority to acquire land compulsorily

s.art032

Compulsory acquisition of rights and imposition of restrictive covenants

s.art033

Private rights of way

s.art034

Application of the 1981 Act

s.art035

Acquisition of subsoil and airspace only

s.art036

Acquisition of part of certain properties

s.art037

Modification of the 1965 Act

s.art038

Rights under or over streets

s.art039

Temporary use of land for carrying out authorised development

s.art040

Time limit for exercise of authority to temporarily use land for carrying out the authorised development

s.art041

Temporary use of land for maintaining authorised development

s.art042

Statutory undertakers

s.art043

Apparatus and rights of statutory undertakers in stopped-up streets

s.art044

Acquisition of wayleaves, easements and other rights

s.art045

Recovery of costs of new connections

s.art046

No double recovery

s.art047

Protective provisions

s.art048

Use of airspace within the Order limits

s.art049

Incorporation of the Harbours, Docks, and Piers Clauses Act 1847

s.art050

Further powers as to works and extinguishment of rights

s.art051

Harbour authority

s.art052

Agreements entered into by the undertaker

s.art053

Application of Pilotage Act 1987

s.art054

Limits of harbour

s.art055

Obstruction of work

s.art056

Obstruction of officers

s.art057

Abatement of works abandoned or decayed

s.art058

Survey of marine works

s.art059

Lights on marine works etc. during construction

s.art060

Provision against danger to navigation

s.art061

Permanent lights on marine works

s.art062

Rights to lease etc.

s.art063

Byelaws

s.art064

Confirmation of byelaws

s.art065

Power to make general directions to vessels

s.art066

Publication of general directions

s.art067

Power to make special directions to vessels

s.art068

Master’s responsibility in relation to directions

s.art069

Failure to comply with directions

s.art070

Enforcement of special directions

s.art071

Boarding of vessels

s.art072

Charges

s.art073

Use of beach landing facility and marine bulk import facility

s.art074

Duration of the powers in Part 6

s.art075

Saving for termination of Part 6

s.art076

Saving for Trinity House

s.art077

Deemed marine licence under the 2009 Act

s.art078

Removal of human remains

s.art079

Application of landlord and tenant law

s.art080

Operational land for purposes of the 1990 Act

s.art081

Felling or lopping of trees and removal of hedgerows

s.art082

Certification of plans, etc.

s.art083

Service of notices

s.art084

Arbitration

s.art085

Procedure in relation to certain approvals etc.

s.art086

Application, exclusion and modification of legislative provisions

s.art087

Crown rights

s.art088

Security in respect of the payment of compensation etc.

Explore more

Browse legislation

Find other UK business legislation with related guidance.