UK Statutory Instrument
2022
United Kingdom
The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022
At a glance
What's here
1 compliance obligation
What this Act requires
Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.
Schedules
Browse 99 other Schedules — structural / supplementary
Bolder Mere Mitigation and Enhancement Area
Buxton Wood Environmental Mitigation Area
Stratford Brook Environmental Mitigation Area
Contaminated land and groundwater
Archaeology
Protected species
Fencing
Restoration and/or landscaping of land used temporarily for construction
Protection of certain tree roots at RHS Garden Wisley
Works in the village of Ripley
Time limits
Approvals and amendments to approved details
Applications made under requirements
Pre-application consultation
Further information
Register of requirements
Anticipatory steps towards compliance with any requirement
Construction and handover environmental management plans
Traffic management during construction
Detailed design
Landscaping
Design, layout and implementation of Replacement Land
Thames Basin Heaths Special Protection Area (SPA) Compensatory Habitat Creation and Enhancement Measures
Cockcrow Green Bridge
The enactments for the time being in force with respect...
(1) Without limitation on the scope of paragraph 1, the...
(1) Without limitation on the scope of paragraph 1, the...
Part 1 (compulsory purchase under Acquisition of Land Act 1946)...
(1) The modification referred to in paragraph 4(a) are as...
For the protection of the utility undertakers referred to in...
(1) Subject to the following provisions of this paragraph, the...
(1) Subject to sub-paragraphs (2) and (3), if by reason...
Where in consequence of the proposed construction of any part...
Nothing in this Part of this Schedule affects the provisions...
For the protection of any operator, the following provisions have...
In this Part of this Schedule— “the 2003 Act” means...
The exercise of the powers conferred by article 35 (statutory...
(1) Subject to sub-paragraphs (2) to (4), if as the...
(1) The following provisions shall apply for the protection of...
(1) Before beginning to construct any specified work, the undertaker...
In this Part of this Schedule— “alternative apparatus” means alternative...
Without limiting paragraph 19, the requirements which the Agency may...
(1) Subject to sub-paragraph (2), any specified work, and all...
(1) Subject to sub-paragraph (7) the undertaker must from the...
If by reason of the construction of any specified work...
If by reason of construction of the specified work the...
(1) The undertaker must take all such measures as may...
The undertaker must repay to the Agency all reasonable costs,...
(1) The undertaker must make reasonable compensation for costs and...
Any dispute arising between the undertaker and the Agency under...
The following provisions of this Part of this Schedule apply...
This Part of this Schedule does not apply to apparatus...
In this Part of this Schedule— “construction” includes execution, placing,...
(1) Before beginning to construct any specified work, the undertaker...
Without limitation on the scope of paragraph 31, the requirements...
(1) Subject to sub-paragraph (2) any specified work, and all...
(1) Subject to sub-paragraph (5), from the commencement of the...
If by reason of the construction of any specified work...
(1) The undertaker must repay to Surrey County Council all...
(1) Without limiting the other provisions of this Part of...
Any dispute arising between the undertaker and Surrey County Council...
For the protection of SGN the following provisions will, unless...
(1) Where any street is stopped up under article 15...
In this Part of this Schedule— “alternative apparatus” means appropriate...
(1) This Part of this Schedule does not apply to...
(1) Without prejudice to the generality of any other protection...
The undertaker must exercise the powers conferred by article 20...
(1) Regardless of any provision in this Order or anything...
(1) If, in the exercise of the powers conferred by...
(1) Where, in accordance with the provisions of this Part...
(1) Not less than 56 days before the commencement of...
(1) Subject to the following provisions of this paragraph, the...
(1) Subject to sub-paragraphs (2) and (3), if by reason...
The undertaker, in the case of the powers conferred by...
Except where this Part of this Schedule provides otherwise, nothing...
(1) Where in consequence of the proposed construction of any...
If in consequence of the agreement reached in accordance with...
Save for differences or disputes arising under sub-paragraphs 45(2), 45(4)...
(1) For the protection of National Grid the following provisions...
In this Part of this Schedule— “alternative apparatus” means appropriate...
Except for paragraphs 57 (apparatus of National Grid in stopped...
(1) Where any street is stopped up under article 15...
The undertaker must exercise the powers conferred by article 20...
(1) Regardless of any provision in this Order or anything...
Regardless of any provision in this Order or anything shown...
(1) If, in the exercise of the powers conferred by...
(1) Where, in accordance with the provisions of this Part...
(1) Not less than 56 days before the commencement of...
(1) Subject to the following provisions of this paragraph, the...
(1) Subject to sub-paragraphs (2) and (3), if by reason...
Nothing in this Part of this Schedule affects the provisions...
(1) Where in consequence of the proposed construction of any...
If in consequence of the agreement reached in accordance with...
Save for differences or disputes arising under paragraphs 60(2), 60(4)...
Notwithstanding article 47 (service of notices), any plans submitted to...
(1) If, in the exercise of the powers conferred by...
(1) Where, in accordance with the provisions of this Part...
(1) Not less than 28 days before starting the execution...
Authority to survey and investigate the land
- Give notice and obtain consents before surveying land, compensate for damage
Browse 47 other sections — procedural / definitional / commencement
Citation and commencement
Interpretation
Disapplication of legislative provisions
Development consent etc. granted by the Order
Maintenance of authorised development
Maintenance of drainage works
Limits of deviation
Benefit of Order
Consent to transfer benefit of Order
Planning permission
Application of the 1991 Act
Construction and maintenance of new, altered or diverted streets and other structures
Classification of roads, etc.
Temporary closure and restriction of use of streets
Permanent stopping up and restriction of use of streets and private means of access
Access to works
Clearways
Traffic regulation
Discharge of water
Protective work to buildings
Compulsory acquisition of land
Compulsory acquisition of land – incorporation of the mineral code
Time limit for exercise of authority to acquire land compulsorily
Compulsory acquisition of rights and restrictive covenants
Extinguishment of public rights of way
Private rights over land
Modification of Part 1 of the 1965 Act
Application of the 1981 Act
Acquisition of subsoil or airspace only
Rights under or over streets
Temporary use of land for carrying out the authorised development
Temporary use of land for maintaining the authorised development
Crown Rights
Statutory undertakers
Apparatus and rights of statutory undertakers in stopped up streets
Recovery of costs of new connections
Special category land
Felling or lopping of trees and removal of hedgerows
Trees subject to tree preservation orders
Application of landlord and tenant law
Operational land for purposes of the 1990 Act
Defence to proceedings in respect of statutory nuisance
Protection of interests
Certification of documents, etc.
Service of notices
Application of local legislation
Arbitration