UK Statutory Instrument 2022 United Kingdom

The Thurrock Flexible Generation Plant Development Consent Order 2022

At a glance

What's here

1 compliance obligation

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

Browse 40 other Schedules — structural / supplementary
s.sch002

Interpretation

s.sch002

Surface and foul water drainage

s.sch002

Flood evacuation plan

s.sch002

Contaminated land

s.sch002

Archaeology

s.sch002

Landscaping and ecological management plan

s.sch002

Construction compound restoration

s.sch002

Operational noise

s.sch002

Local employment and skills strategy

s.sch002

Operational hours

s.sch002

Details to accord with Environmental Statement

s.sch002

Time limit

s.sch002

Carbon capture readiness

s.sch002

Carbon capture readiness monitoring report

s.sch002

Amendments to approved plans, etc.

s.sch002

Anticipatory steps

s.sch002

Submissions and approvals

s.sch002

Applications made under requirements

s.sch002

Further information

s.sch002

Provision of information by Consultees

s.sch002

Fees

s.sch002

Appeal

s.sch002

Notice of commencement of authorised development

s.sch002

Documents

s.sch002

Detailed design

s.sch002

Code of construction practice

s.sch002

Construction traffic management plan

s.sch002

Construction worker travel plan

s.sch002

External lighting

s.sch002

Construction hours

s.sch007

Compensation enactments

s.sch007

Without limitation on the scope of paragraph 1, the 1961...

s.sch007

(1) Without limitation on the scope of paragraph 1, the...

s.sch007

Application of Part 1 of the 1965 Act

s.sch008

Network Rail must, on receipt of a request from the...

s.sch008

In the assessment of any sums payable to Network Rail...

s.sch008

The promoter and Network Rail may, subject in the case...

s.sch008

Nothing in this Order, or in any enactment incorporated with...

s.sch008

The promoter must give written notice to Network Rail if...

s.sch008

The promoter must no later than 28 days from the...

s.art017

Authority to survey and investigate the land

  • Give notice, obtain consents, and compensate before surveying land
Browse 56 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent etc. granted by the Order

s.art004

Limits of deviation

s.art005

Maintenance of authorised development

s.art006

Operation of generating station

s.art007

Benefit of Order

s.art008

Consent to transfer benefit of Order

s.art009

Defence to proceedings in respect of statutory nuisance

s.art010

Disapplication of legislation etc.

s.art011

Street works

s.art012

Application of the 1991 Act

s.art013

Temporary restriction of use of streets

s.art014

Access to works

s.art015

Traffic regulation

s.art016

Discharge of water

s.art018

Removal of human remains

s.art019

Compulsory acquisition of land

s.art020

Statutory authority to override easements and other rights

s.art021

Time limit for exercise of authority to acquire land compulsorily

s.art022

Compulsory acquisition of rights

s.art023

Private rights

s.art024

Application of the 1981 Act

s.art025

Acquisition of subsoil only

s.art026

Modification of Part 1 of the 1965 Act

s.art027

Rights under or over streets

s.art028

Temporary use of land for carrying out the authorised development

s.art029

Temporary use of land for maintaining the authorised development

s.art030

Statutory undertakers

s.art031

Apparatus and rights of statutory undertakers in stopped up streets

s.art032

Recovery of costs of new connections

s.art033

Special category land

s.art034

Funding

s.art035

Felling or lopping of trees and removal of hedgerows

s.art036

Protective provisions

s.art037

Operational land for the purposes of the 1990 Act

s.art038

Certification of plans, etc.

s.art039

Service of notices

s.art040

No double recovery

s.art041

Application of landlord and tenant law

s.art042

Arbitration