UK Statutory Instrument 2020 United Kingdom

The Norfolk Vanguard Offshore Wind Farm Order 2020

At a glance

What's here

4 compliance obligations

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch009

Notifications and inspections

  • Notify MMO and other bodies of construction activities and provide access for inspections
s.sch010

Notifications and inspections

  • Distribute licence copies, notify MMO of construction, and keep documents for inspection
s.sch016

(1) Subject to sub-paragraphs (2) to (4), if as the...

  • Pay for damage to or interruption of electronic communications equipment
Browse 232 other Schedules — structural / supplementary
s.sch001

A nationally significant infrastructure project as defined in sections 14...

s.sch001

(1) In relation to any LIDAR measurement buoys, each foundation...

s.sch001

The total amount of scour protection for the wind turbine...

s.sch001

Aviation safety

s.sch001

Ministry of Defence surveillance operations

s.sch001

Offshore decommissioning

s.sch001

Stages of authorised development onshore

s.sch001

Detailed design parameters onshore

s.sch001

Landfall method statement

s.sch001

Provision of landscaping

s.sch001

Implementation and maintenance of landscaping

s.sch001

Detailed offshore design parameters

s.sch001

Code of construction practice

s.sch001

Traffic

s.sch001

Highway accesses

s.sch001

Archaeological written scheme of investigation

s.sch001

Ecological management plan

s.sch001

Watercourse crossings

s.sch001

Construction hours

s.sch001

Control of noise during operational phase and during maintenance

s.sch001

European protected species onshore

s.sch001

Onshore decommissioning

s.sch001

(1) The total number of wind turbine generators forming part...

s.sch001

Requirement for written approval

s.sch001

Amendments to approved details

s.sch001

Operational drainage plan

s.sch001

Skills and employment strategy

s.sch001

Cromer Primary Surveillance Radar

s.sch001

(1) The dimensions of any offshore electrical platforms forming part...

s.sch001

The total length of the cables and the volume and...

s.sch001

(1) In relation to a wind turbine generator, each foundation...

s.sch001

(1) In relation to a meteorological mast, each foundation using...

s.sch001

(1) In relation to an offshore electrical platform, each foundation...

s.sch001

(1) In relation to any accommodation platform, each foundation using...

s.sch007

The enactments for the time being in force with respect...

s.sch007

(1) Without prejudice to the generality of paragraph 1, the...

s.sch007

(1) The 1965 Act has effect with the modifications necessary...

s.sch007

For section 7 of the 1965 Act (measure of compensation)...

s.sch007

Section 8(1) of the Compulsory Purchase Act 1965 has effect...

s.sch007

The following provisions of the 1965 Act (which state the...

s.sch007

Section 11 of the 1965 Act (powers of entry) is...

s.sch007

Section 20 of the 1965 Act (protection for interests of...

s.sch007

Section 22 of the 1965 Act (protection of acquiring authority’s...

s.sch009

In this licence— “the 2004 Act” means the Energy Act...

s.sch009

Aids to navigation

s.sch009

Colouring of structures

s.sch009

Chemicals, drilling and debris

s.sch009

Force majeure

s.sch009

Pre-construction plans and documentation

s.sch009

(1) Any archaeological reports produced in accordance with condition 14(h)(iii)...

s.sch009

Post-construction plans and documents

s.sch009

Reporting of engaged agents, contractors and vessels

s.sch009

Pre-construction monitoring and surveys

s.sch009

Construction monitoring

s.sch009

A reference to any statute, order, regulation or similar instrument...

s.sch009

Post construction

s.sch009

Reporting of impact pile driving

s.sch009

Reporting of cable protection

s.sch009

Decommissioning of cable protection within marine protected areas

s.sch009

Unless otherwise indicated— (a) all times are taken to be...

s.sch009

Except where otherwise notified in writing by the relevant organisation,...

s.sch009

The substances or articles authorised for deposit at sea are—...

s.sch009

The grid coordinates for the authorised scheme are specified below—...

s.sch009

(1) In relation to any LIDAR measurement buoys, each foundation...

s.sch009

Phasing of the authorised scheme

s.sch010

(1) In this licence— “the 2004 Act” means the Energy...

s.sch010

Aids to navigation

s.sch010

Colouring of structures

s.sch010

Chemicals, drilling and debris

s.sch010

Force majeure

s.sch010

Pre-construction plans and documentation

s.sch010

(1) Any archaeological reports produced in accordance with condition 14(h)(iii)...

s.sch010

Post-construction plans and documents

s.sch010

Reporting of engaged agents, contractors and vessels

s.sch010

Pre-construction monitoring and surveys

s.sch010

Construction monitoring

s.sch010

A reference to any statute, order, regulation or similar instrument...

s.sch010

Post construction

s.sch010

Reporting of impact pile driving

s.sch010

Reporting of cable protection

s.sch010

Decommissioning of cable protection within marine protected areas

s.sch010

Unless otherwise indicated— (a) all times are taken to be...

s.sch010

Except where otherwise notified in writing by the relevant organisation,...

s.sch010

The substances or articles authorised for deposit at sea are—...

s.sch010

The grid coordinates for the authorised scheme are specified below—...

s.sch010

(1) In relation to any LIDAR measurement buoys, each foundation...

s.sch010

Phasing of the authorised scheme

s.sch011

(1) In this licence— “the 2004 Act” means the Energy...

s.sch011

(1) Any archaeological reports produced in accordance with condition 9(1)(h)(iii)...

s.sch011

Post-construction plans and documents

s.sch011

Reporting of engaged agents, contractors and vessels

s.sch011

Pre-construction monitoring and surveys

s.sch011

Construction monitoring

s.sch011

Post construction

s.sch011

Reporting of impact pile driving

s.sch011

Reporting of cable protection

s.sch011

Restriction on cable installation construction works

s.sch011

Decommissioning of cable protection within marine protected areas

s.sch011

The provisions of section 72 (variation, suspension, revocation and transfer)...

s.sch011

With respect to any condition which requires the licensed activities...

s.sch011

Any amendments to or variations from the approved plans, protocols...

s.sch011

The substances or articles authorised for deposit at sea are—...

s.sch011

The grid coordinates for the authorised scheme are specified below—...

s.sch011

Chemicals, drilling and debris

s.sch011

Force majeure

s.sch011

Pre-construction plans and documentation

s.sch012

(1) In this licence— “the 2004 Act” means the Energy...

s.sch012

(1) Any archaeological reports produced in accordance with condition 9(1)(h)(iii)...

s.sch012

Post-construction plans and documents

s.sch012

Reporting of engaged agents, contractors and vessels

s.sch012

Pre-construction monitoring and surveys

s.sch012

Construction monitoring

s.sch012

Post construction

s.sch012

Reporting of impact pile driving

s.sch012

Reporting of cable protection

s.sch012

Restriction on cable installation construction works

s.sch012

Decommissioning of cable protection within marine protected areas

s.sch012

The provisions of section 72 (variation, suspension, revocation and transfer)...

s.sch012

With respect to any condition which requires the licensed activities...

s.sch012

Any amendments to or variations from the approved plans, protocols...

s.sch012

The substances or articles authorised for deposit at sea are—...

s.sch012

The grid coordinates for the authorised scheme are specified below—...

s.sch012

Chemicals, drilling and debris

s.sch012

Force majeure

s.sch012

Pre-construction plans and documentation

s.sch014

Primary objective

s.sch014

Time periods

s.sch014

Timetable

s.sch014

Procedure

s.sch014

Arbitrator’s powers

s.sch014

Costs

s.sch014

Confidentiality

s.sch015

Applications made under requirement

s.sch015

Further information

s.sch015

Appeals

s.sch015

Interpretation of this Schedule

s.sch016

For the protection of the undertakers referred to in this...

s.sch016

Any difference or dispute arising between the undertaker and the...

s.sch016

Nothing in this Part shall affect the provisions of any...

s.sch016

Application

s.sch016

Interpretation

s.sch016

(1) Except for paragraphs 15 (apparatus in stopped up streets),...

s.sch016

Apparatus of Undertakers in stopped up streets

s.sch016

Acquisition of land

s.sch016

Removal of apparatus

s.sch016

Facilities and rights for alternative apparatus

s.sch016

Retained apparatus: protection Gas Undertakers

s.sch016

In this Part— “affected undertaker” means any licence holder within...

s.sch016

Retained apparatus: protection Electricity Undertakers

s.sch016

Expenses

s.sch016

Compensation

s.sch016

Enactments and agreements

s.sch016

Co-operation

s.sch016

Access

s.sch016

Arbitration

s.sch016

Notices

s.sch016

Application

s.sch016

Interpretation

s.sch016

This Part does not apply to apparatus in respect of...

s.sch016

On Street Apparatus

s.sch016

Apparatus of Undertakers in stopped up streets

s.sch016

Acquisition of land

s.sch016

Removal of apparatus

s.sch016

Facilities and rights for alternative apparatus

s.sch016

Retained apparatus: protection Gas Undertakers

s.sch016

Expenses

s.sch016

Compensation

s.sch016

Enactments and agreements

s.sch016

Co-operation

s.sch016

Regardless of any provision in this Order or anything shown...

s.sch016

Access

s.sch016

Arbitration

s.sch016

Notices

s.sch016

(1) For the protection of any operator, the following provisions...

s.sch016

The exercise of the powers of article 29 (statutory undertakers)...

s.sch016

This Part does not apply to— (a) any apparatus in...

s.sch016

Nothing in this Part shall affect the provisions of any...

s.sch016

The following provisions of this Schedule have effect, unless otherwise...

s.sch016

In this Part— “construction” includes execution, placing, alteration and reconstruction...

s.sch016

(1) If, in the exercise of the powers conferred by...

s.sch016

(1) Where under this Part Network Rail is required to...

s.sch016

(1) The undertaker must not exercise the powers conferred by—...

s.sch016

(1) The undertaker must before commencing construction of any specified...

s.sch016

(1) Any specified work and any protective works to be...

s.sch016

The undertaker must— (a) at all times afford reasonable facilities...

s.sch016

Network Rail must at all times afford reasonable facilities to...

s.sch016

(1) If any permanent or temporary alterations or additions to...

s.sch016

The undertaker must repay to Network Rail all reasonable fees,...

s.sch016

(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

s.sch016

If at any time after the completion of a specified...

s.sch016

(1) Where, in accordance with the provisions of this Part,...

s.sch016

The undertaker must not provide any illumination or illuminated sign...

s.sch016

Any additional expenses which Network Rail may reasonably incur in...

s.sch016

(1) The undertaker must pay to Network Rail all reasonable...

s.sch016

Network Rail must, on receipt of a request from the...

s.sch016

In the assessment of any sums payable to Network Rail...

s.sch016

The undertaker and Network Rail may, subject in the case...

s.sch016

Nothing in this Order, or in any enactment incorporated with...

s.sch016

The undertaker must give written notice to Network Rail if...

s.sch016

The undertaker must no later than 28 days from the...

s.sch016

In relation to any dispute arising under this Part that...

s.sch016

(1) Not less than 28 days before starting the execution...

s.sch016

(1) For the protection of Anglian Water, the following provisions...

s.sch016

The provisions of this Part have effect for the protection...

s.sch016

In this Part— “construction” includes execution, placing, altering, replacing, relaying...

s.sch016

(1) Before beginning to construct any specified work, the undertaker...

s.sch016

Without limiting paragraph 71, the requirements which the drainage authority...

s.sch016

(1) Subject to sub–paragraph (2), any specified work, and all...

s.sch016

(1) Subject to sub–paragraph (5) the undertaker must from the...

s.sch016

If by reason of the construction of any specified work...

s.sch016

The undertaker must compensate the drainage authority in respect of...

s.sch016

(1) Without limiting the other provisions of this Part, the...

s.sch016

(1) Subject to the following provisions of this paragraph, the...

s.sch016

The fact that any work or thing has been executed...

s.sch016

Any dispute between the undertaker and the drainage authority under...

s.sch016

The provisions of this Part apply for the protection of...

s.sch016

In this Part— “apparatus” means the cables, structures or other...

s.sch016

The consent of Orsted under this Part is not required...

s.sch016

Where conditions are included in any consent granted by Orsted...

s.sch016

The undertaker must not under the powers of this Order—...

s.sch016

(1) The undertaker must not under the powers of this...

s.sch016

(1) The undertaker must give to Orsted not less than...

s.sch016

The undertaker must at all reasonable times during construction of...

s.sch016

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch016

(1) After the purpose of any temporary works has been...

s.sch016

If in consequence of the exercise of the powers conferred...

s.sch016

The undertaker must not exercise the powers conferred by this...

s.sch016

To ensure its compliance with this Part, the undertaker must...

s.sch016

The undertaker and Orsted must each act in good faith...

s.sch016

The undertaker must pay to Orsted the reasonable expenses incurred...

s.sch016

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch016

Any dispute arising between the undertaker and Orsted under this...

s.art016

Authority to survey and investigate the land onshore

  • Serve 14 days' notice to landowners before surveying or investigating land
Browse 60 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent etc. granted by the Order

s.art004

Limits of deviation

s.art005

Power to construct and maintain authorised project

s.art006

Benefit of the Order

s.art007

Application and modification of legislative provisions

s.art008

Defence to proceedings in respect of statutory nuisance

s.art009

Street works

s.art010

Public rights of way

s.art011

Temporary stopping up of streets

s.art012

Access to works

s.art013

Agreements with street authorities

s.art014

Application of the 1991 Act

s.art015

Discharge of water and works to watercourses

s.art017

Removal of human remains

s.art018

Compulsory acquisition of land

s.art019

Time limit for exercise of authority to acquire land compulsorily

s.art020

Compulsory acquisition of rights

s.art021

Private rights

s.art022

Application of the 1981Act

s.art023

Application of Part 1 of the Compulsory Purchase Act 1965

s.art024

Acquisition of subsoil or airspace only

s.art025

Rights under or over streets

s.art026

Temporary use of land for carrying out the authorised project

s.art027

Temporary use of land for maintaining authorised project

s.art028

Extinguishment of private rights and restrictive covenants relating to apparatus removed from land subject to temporary possession

s.art029

Statutory undertakers

s.art030

Recovery of costs of new connections

s.art031

Operation of generating station

s.art032

Deemed marine licences under the 2009 Act

s.art033

Application of landlord and tenant law

s.art034

Operational land for purposes of the 1990 Act

s.art035

Felling or lopping of trees and removal of hedgerows

s.art036

Trees subject to tree preservation orders

s.art037

Certification of plans etc

s.art038

Arbitration

s.art039

Procedure in relation to certain approvals etc

s.art040

Abatement of works abandoned or decayed

s.art041

Saving provisions for Trinity House

s.art042

Crown rights

s.art043

Protective provisions

s.p00883/schedule/1/part/1/paragraph/1n2

Offshore

s.p00883/schedule/1/part/1/paragraph/1n3

Intertidal area

s.p00883/schedule/1/part/1/paragraph/1n4

In the county of Norfolk, district of North Norfolk

s.p00883/schedule/1/part/1/paragraph/1n5

In the county of Norfolk, district of Broadland

s.p00883/schedule/1/part/1/paragraph/1n6

In the county of Norfolk, district of Breckland

s.para.46

Work No. 2 – up to two offshore electrical platforms...

s.para.47

Work No. 3 – a network of subsea cables and...

s.para.48

Work No. 4A – up to four subsea export cables...

s.para.51

Work No. 5 – onshore transmission works consisting of up...

s.para.54

Work No. 8A – onshore project substation to the east...

s.para.55

Work No.8B – surface water management, bunding, embankments, boundary treatments...

s.para.56

Work No. 9 – works consisting of the connection of...

s.para.57

Work No. 10A – an extension to the existing National...

s.para.58

Work No. 10B – additional surface water management for the...

s.para.59

Work No. 10C – bunding, embankments, boundary treatments and landscaping...

s.para.60

Work No. 11 –the removal of one existing pylon and...

s.para.61

Work No. 11A – the overhead line modification;

s.para.62

Work No. 12 – permanent accesses connecting the A47 to...

Explore more

Browse legislation

Find other UK business legislation with related guidance.