UK Statutory Instrument SI 2020/419 United Kingdom

The Riverside Energy Park Order 2020

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker2

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art019 Authority to survey and investigate the land Regulated
  • Enter land for surveys and investigations after giving noticeStatutory Undertaker
42 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent granted by the Order
s.art004 Maintenance of authorised development
s.art005 Operation of the authorised development
s.art006 Disapplication of legislative provisions and modifications to section 36 consent and RRRF planning permission
s.art007 Port of London Act 1968
s.art008 Benefit of this Order
s.art009 Consent to transfer benefit of the Order
s.art010 Guarantees in respect of payment of compensation
s.art011 Street works
s.art012 Power to alter layout, etc., of streets
s.art013 Temporary prohibition or restriction of use of streets and public rights of way
s.art014 Permanent stopping up of streets
s.art015 Access to works
s.art016 Agreements with street authorities
s.art017 Traffic regulation measures
s.art018 Discharge of water
s.art020 Protective work to buildings
s.art021 Felling or lopping of trees
s.art022 Compulsory acquisition of land
s.art023 Time limit for exercise of authority to acquire land compulsorily
s.art024 Compulsory acquisition of rights
s.art025 Acquisition of subsoil only
s.art026 Private rights
s.art027 Power to override easements and other rights
s.art028 Application of the 1981 Act
s.art029 Modification of Part 1 of the 1965 Act
s.art030 Rights under or over streets
s.art031 Temporary use of land for carrying out the authorised development
s.art032 Temporary use of land for maintaining the authorised development
s.art033 Statutory undertakers
s.art034 Apparatus and rights of statutory undertakers in stopped up streets
s.art035 Recovery of costs of new connections
s.art036 Application of landlord and tenant law
s.art037 Operational land for the purposes of the 1990 Act
s.art038 Defence to proceedings in respect of statutory nuisance
s.art039 Protective provisions
s.art040 Certification of plans etc.
s.art041 Service of notices
s.art042 Procedures in relation to certain approvals etc.
s.art043 No double recovery
Schedules

Schedules

1 of 185 shown
s.sch010 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay costs and compensation for damage to electronic communications apparatusStatutory Undertaker
184 other schedules
s.sch001 Work No. 8 — Works to construct temporary construction compounds...
s.sch001 In the London Borough of Bexley and the Borough of...
s.sch001 Work No. 9 — Works to construct and install an...
s.sch001 In the Borough of Dartford
s.sch001 Work No. 10 — Works to connect the electrical connection...
s.sch001 In connection with and in addition to Work Nos. 1,...
s.sch001 A nationally significant infrastructure project as defined in section 14(1)(a)...
s.sch001 In the London Borough of Bexley
s.sch001 Work No. 1 — Works to construct an integrated energy...
s.sch001 Work No. 2 — Works to construct—
s.sch001 Work No. 3 — Works to construct and install combined...
s.sch001 Work No.4 — Works to construct an electrical substation including...
s.sch001 Work No. 5 — Works to construct or install supporting...
s.sch001 Work No. 6 — Works to construct and install supporting...
s.sch001 Work No. 7 — Works to construct and install from...
s.sch002 Time limits
s.sch002 Ground conditions and ground stability
s.sch002 Code of construction practice
s.sch002 Construction Hours
s.sch002 Construction traffic management plan(s)
s.sch002 Heavy commercial vehicle movements delivering waste
s.sch002 Emission limits – Work No. 1B
s.sch002 Waste hierarchy scheme
s.sch002 Operational worker travel plan
s.sch002 Operational lighting strategy
s.sch002 Control of operational noise
s.sch002 Detailed design approval
s.sch002 River wall
s.sch002 Community benefits
s.sch002 Notice of start of commissioning and notice of date of final commissioning
s.sch002 Phasing of construction and commissioning of Work No. 1
s.sch002 Combined heat and power
s.sch002 Use of compost material and gas from Work No. 1B
s.sch002 Decommissioning
s.sch002 Amendments to approved details
s.sch002 Flood Risk Activity Permit Area
s.sch002 Finished Floor Levels
s.sch002 Parameters of authorised development
s.sch002 Metropolitan Open Land
s.sch002 Delivery and Servicing Plan
s.sch002 Tonnage cap
s.sch002 Notification from the undertaker
s.sch002 Pre–commencement biodiversity mitigation strategy
s.sch002 Biodiversity and landscape mitigation strategy
s.sch002 Replacement planting for Work No. 9
s.sch002 Archaeology
s.sch002 Highway access
s.sch002 Surface and foul water drainage
s.sch007 Interpretation
s.sch008 Compensation enactments
s.sch008 (1) Without limitation on the scope of paragraph 1, the...
s.sch008 (1) Without limitation on the scope of paragraph 1, the...
s.sch008 Application of Part 1 of the 1965 Act
s.sch008 (1) The modifications referred to in paragraph 4(a) are as...
s.sch010 For the protection of RRRL as referred to in this...
s.sch010 (1) Subject to the following provisions of this paragraph, the...
s.sch010 If in consequence of the exercise of the powers under...
s.sch010 If in consequence of the exercise of the powers under...
s.sch010 If for any reason or in consequence of the construction...
s.sch010 Consultation
s.sch010 Application
s.sch010 Interpretation
s.sch010 On Street Apparatus
s.sch010 Apparatus of SGN in stopped up streets
s.sch010 Protective works to buildings
s.sch010 Acquisition of land
s.sch010 Nothing in this part of this Schedule affects the provisions...
s.sch010 Removal of apparatus
s.sch010 Facilities and rights for alternative apparatus
s.sch010 Retained apparatus: protection of SGN
s.sch010 Expenses
s.sch010 Indemnity
s.sch010 Enactments and agreements
s.sch010 Co-operation
s.sch010 Access
s.sch010 Arbitration
s.sch010 Notices
s.sch010 Where in consequence of the proposed construction or maintenance of...
s.sch010 If in consequence of any agreement reached or the powers...
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch010 The provisions of this Part have effect for the protection...
s.sch010 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch010 This Part of this Schedule does not apply to apparatus...
s.sch010 Regardless of the temporary prohibition or restriction of use of...
s.sch010 In this part of this Schedule “access road” means that...
s.sch010 Regardless of any provision in this Order or anything shown...
s.sch010 (1) If, in the exercise of the powers conferred by...
s.sch010 (1) Where, in accordance with the provisions of this Part...
s.sch010 (1) Not less than 28 days before starting the execution...
s.sch010 (1) Subject to the following provisions of this paragraph, the...
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch010 Nothing in this Part of this Schedule affects the provisions...
s.sch010 (1) For the protection of any operator, the following provisions...
s.sch010 The exercise of the powers of article 33 (statutory undertakers)...
s.sch010 Upon the permanent stopping up of the access road pursuant...
s.sch010 This Part of this Schedule does not apply to—
s.sch010 Nothing in this Part of this Schedule affects the provisions...
s.sch010 (1) The following provisions shall apply for the protection of...
s.sch010 The provisions within this Part shall not apply where a...
s.sch010 (1) Before beginning to construct any specified work, the undertaker...
s.sch010 Without limiting paragraph 34, the requirements which the Agency may...
s.sch010 No buildings will be erected within the area defined by...
s.sch010 (1) Subject to sub-paragraph (2), any specified work, and all...
s.sch010 (1) Subject to sub–paragraph (6), the undertaker must from the...
s.sch010 Subject to paragraph 41, if by reason of the construction...
s.sch010 The undertaker must not install pipes for the offtake of...
s.sch010 If by reason of construction of the specified work the...
s.sch010 The undertaker must indemnify the Agency in respect of all...
s.sch010 (1) The undertaker is responsible for and must indemnify the...
s.sch010 Any dispute arising between the undertaker and the Agency under...
s.sch010 The following provisions of this Part of this Schedule have...
s.sch010 In this Part of this Schedule— “construction” includes execution, placing,...
s.sch010 (1) Where under this Part of this Schedule Network Rail...
s.sch010 (1) The undertaker must not exercise the powers conferred by—...
s.sch010 (1) The undertaker must before commencing construction of any specified...
s.sch010 (1) Any specified work and any protective works to be...
s.sch010 Regardless of the temporary prohibition or restriction of use of...
s.sch010 The undertaker must— (a) at all times afford reasonable facilities...
s.sch010 Network Rail must at all times afford reasonable facilities to...
s.sch010 (1) If any permanent or temporary alterations or additions to...
s.sch010 The undertaker must repay to Network Rail all reasonable fees,...
s.sch010 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch010 If at any time after the completion of a specified...
s.sch010 The undertaker must not provide any illumination or illuminated sign...
s.sch010 Any additional expenses which Network Rail may reasonably incur in...
s.sch010 (1) The undertaker must pay to Network Rail all reasonable...
s.sch010 Network Rail must, on receipt of a request from the...
s.sch010 Regardless of any provision in this Order or anything shown...
s.sch010 In the assessment of any sums payable to Network Rail...
s.sch010 The undertaker and Network Rail may, subject in the case...
s.sch010 Nothing in this Order, or in any enactment incorporated with...
s.sch010 The undertaker must give written notice to Network Rail if...
s.sch010 The undertaker must no later than 28 days from the...
s.sch010 In relation to any dispute arising under this Part of...
s.sch010 For the protection of National Grid referred to in this...
s.sch010 Interpretation
s.sch010 On Street Apparatus
s.sch010 Apparatus of National Grid in stopped up streets
s.sch010 (1) If, in the exercise of the powers conferred by...
s.sch010 Protective works to buildings
s.sch010 Acquisition of land
s.sch010 Removal of apparatus
s.sch010 Facilities and rights for alternative apparatus
s.sch010 Retained apparatus
s.sch010 Expenses
s.sch010 Indemnity
s.sch010 Enactments and agreements
s.sch010 Co–operation
s.sch010 Access
s.sch010 (1) Where, in accordance with the provisions of this part...
s.sch010 Arbitration
s.sch010 Notices
s.sch010 For the protection of the utility undertakers referred to in...
s.sch010 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch010 This Part of this Schedule does not apply to apparatus...
s.sch010 Regardless of the temporary prohibition or restriction of use of...
s.sch010 Regardless of any provision in this Order or anything shown...
s.sch010 (1) If, in the exercise of the powers conferred by...
s.sch010 (1) Where, in accordance with the provisions of this Part...
s.sch010 (1) Not less than 28 days before starting the execution...
s.sch010 (1) Not less than 28 days before starting the execution...
s.sch010 (1) Subject to the following provisions of this paragraph, the...
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch010 Where in consequence of the proposed construction of any of...
s.sch010 Nothing in this Part of this Schedule affects the provisions...
s.sch010 Application
s.sch010 Interpretation
s.sch010 Apparatus
s.sch010 The alteration, extension, removal or relocation of any apparatus must...
s.sch010 In the situation where in exercise of the powers under...
s.sch010 Regardless of any provision in this Order or anything shown...
s.sch012 Interpretation
s.sch012 Applications made under requirements
s.sch012 Further information and consultation
s.sch012 Appeals
s.sch012 Application to protective provisions
s.sch013 Delete the words “associated open storage areas for ash container...
s.sch013 Delete “and” at the end of paragraph 3(1)(i).
s.sch013 For the words “25 September 2014.” at the end of...
s.sch013 After paragraph 3(1)(ii) insert new paragraph 3(1)(iii) as follows, “...
s.sch013 After RRRF condition 1(iii), insert new condition 1(iv) as follows,...
s.sch013 In RRRF condition 7, insert the words “ (except for...
s.sch013 For RRRF condition 23, substitute new condition 23 as follows...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.