UK Statutory Instrument SI 2020/325 United Kingdom

The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker2

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art016 Authority to survey and investigate the land Regulated
  • Complying with conditions for land surveys and investigationsStatutory Undertaker
37 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Limits of deviation
s.art005 Operation of authorised development
s.art006 Maintenance of authorised development
s.art007 Benefit of the Order
s.art008 Consent to transfer benefit of the Order
s.art009 Power to alter layout, etc. of streets
s.art010 Street works
s.art011 Temporary prohibition or restriction of use of streets and public rights of way
s.art012 Traffic regulation
s.art013 Access to works
s.art014 Agreement with street authorities
s.art015 Discharge of water
s.art017 Compulsory acquisition of rights: incorporation of the mineral code
s.art018 Compulsory acquisition of rights
s.art019 Statutory authority to override easements and other rights
s.art020 Time limit for exercise of authority to acquire rights compulsorily
s.art021 Private rights
s.art022 Application of the 1981 Act
s.art023 Acquisition of subsoil or airspace only
s.art024 Modification of Part 1 of the 1965 Act
s.art025 Rights under or over streets
s.art026 Temporary use of land for carrying out the authorised development
s.art027 Temporary use of land for maintaining the authorised development
s.art028 Special category land
s.art029 Statutory undertakers
s.art030 Recovery of costs of new connections
s.art031 Felling or lopping of trees and removal of hedgerows
s.art032 Application of landlord and tenant law
s.art033 Operational land for the purposes of the 1990 Act
s.art034 Defence to proceedings in respect of statutory nuisance
s.art035 Certification of plans etc.
s.art036 Service of notices
s.art037 Procedure in relation to certain approvals etc.
s.art038 Arbitration
Schedules

Schedules

1 of 106 shown
s.sch006 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay for damage to telecoms apparatus caused by your workStatutory Undertaker
105 other schedules
s.sch001 A nationally significant infrastructure project, as defined in sections 14(1)(b)...
s.sch002 Interpretation
s.sch002 Approved plans and amendments to approved plans
s.sch002 A5(T) Traffic Management Crossing
s.sch002 Time limits
s.sch002 Compliance with approved details
s.sch002 Restriction on the limits of deviation
s.sch002 Plans
s.sch002 Felling
s.sch002 Construction hours
s.sch002 Contaminated land and groundwater
s.sch002 Construction environmental management plan
s.sch004 The enactments for the time being in force with respect...
s.sch004 (1) Without limitation on the scope of paragraph (1), the...
s.sch004 (1) Without limitation on the scope of paragraph 1, the...
s.sch004 Part 1 (compulsory purchase under Acquisition of Land Act 1946)...
s.sch004 (1) The modifications referred to in paragraph 4(1)(a) are as...
s.sch006 (1) For the protection of any operator, the following provisions...
s.sch006 (1) If, in the exercise of the powers conferred by...
s.sch006 (1) Not less than 28 days before starting the execution...
s.sch006 (1) Subject to the following provisions of this paragraph, the...
s.sch006 The following provisions of this Part have effect, unless otherwise...
s.sch006 In this Part— “construction” includes execution, placing, alteration and reconstruction...
s.sch006 (1) Where under this Part Network Rail is required to...
s.sch006 (1) The undertaker must not exercise the powers conferred by...
s.sch006 (1) The undertaker must before commencing construction of any specified...
s.sch006 (1) Any specified work and any protective works to be...
s.sch006 The undertaker must— (a) at all times afford reasonable facilities...
s.sch006 The exercise of the powers of article 29 (statutory undertakers)...
s.sch006 Network Rail must at all times afford reasonable facilities to...
s.sch006 (1) If any permanent or temporary alterations or additions to...
s.sch006 The undertaker must repay to Network Rail all reasonable fees,...
s.sch006 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch006 If at any time after the completion of a specified...
s.sch006 The undertaker must not provide any illumination or illuminated sign...
s.sch006 Any additional expenses which Network Rail may reasonably incur in...
s.sch006 (1) The undertaker must pay to Network Rail all reasonable...
s.sch006 Network Rail must, on receipt of a request from the...
s.sch006 In the assessment of any sums payable to Network Rail...
s.sch006 The undertaker and Network Rail may, subject in the case...
s.sch006 Nothing in this Order, or in any enactment incorporated with...
s.sch006 The undertaker must give written notice to Network Rail if...
s.sch006 The undertaker must no later than 28 days from the...
s.sch006 Interpretation
s.sch006 Powers requiring the Trust's consent
s.sch006 Approval of plans, protective works etc.
s.sch006 Design of works
s.sch006 Notice of works
s.sch006 Construction of specified works
s.sch006 This Part of this Schedule does not apply to—
s.sch006 Prevention of pollution
s.sch006 Access to work – provision of information
s.sch006 Alterations to the waterway
s.sch006 Maintenance of works
s.sch006 Repayment of the Trust's fees, etc.
s.sch006 Making good of detriment; compensation and indemnity, etc.
s.sch006 Arbitration
s.sch006 Capitalised sums
s.sch006 Vehicles, plant and machinery
s.sch006 Fencing
s.sch006 Nothing in this Part of this Schedule affects the provisions...
s.sch006 Survey of waterway
s.sch006 Further engagement
s.sch006 Application
s.sch006 Interpretation
s.sch006 On Street Apparatus
s.sch006 Acquisition of land
s.sch006 Removal of apparatus
s.sch006 Facilities and rights for alternative apparatus
s.sch006 Retained apparatus: Protection of National Grid as Electricity Undertaker
s.sch006 Expenses
s.sch006 For the protection of the statutory undertakers referred to in...
s.sch006 Indemnity
s.sch006 Enactments and agreements
s.sch006 Co-operation
s.sch006 Access
s.sch006 Arbitration
s.sch006 Notices
s.sch006 Application
s.sch006 Interpretation
s.sch006 Prior approvals
s.sch006 Construction of the HE works
s.sch006 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch006 Payments
s.sch006 Indemnity
s.sch006 Arbitration
s.sch006 This Part of this Schedule does not apply to apparatus...
s.sch006 Regardless of any provision in this Order or anything shown...
s.sch007 Applications made under requirements
s.sch007 Further information
s.sch007 Fees
s.sch007 Appeals
s.sch007 Interpretation of Schedule 7
s.sch009 The Works Plans listed below— Table 7 (1) Application documents...
s.sch009 The Access and Rights of Way Plans listed below— Table...
s.sch009 The Plans of Important Hedgerows Affected Table 9 (1) Application...
s.sch009 The additional documents listed below— Table 10 (1) Application documents...
s.sch009 The Book of Reference listed below— Table 5 (1) Application...
s.sch009 The Land Plans listed below— Table 6 (1) Application document...
s.schedule/1/part/1/chapter//paragraph/wrapper2n2 Work No. 1 Works at Oswestry substation as shown on...
s.schedule/1/part/2/chapter//paragraph/wrapper3n2 Work No. 2 the construction and installation and keeping of...
s.schedule/1/part/3/chapter//paragraph/wrapper4n2 Work No. 3 the construction and installation and keeping of...
s.schedule/1/part/4/chapter//paragraph/wrapper5n2 Work No.4A the removal of existing 11kV and 33kV overhead...
s.schedule/1/part/4/chapter//paragraph/wrapper6n2 Work No.4B the undergrounding of 11kV and 33kV cables between...
s.schedule/1/part/5/chapter//paragraph/wrapper7n2 Work No.5 —Works at Wem substation as shown on sheet...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.