UK Statutory Instrument SI 2017/817 United Kingdom

The National Grid (Richborough Connection Project) Development Consent Order 2017

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

sch. 14 para. 3 sch. 14 para. 3 Regulated
  • Pay for damage to electronic communications apparatus caused by developmentStatutory Undertaker
65 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Maintenance of authorised development
s.art005 Limits of deviation
s.art006 Benefit of Order
s.art007 Consent to transfer benefit of Order
s.art008 Application of the 1990 Act
s.art009 Application of the Community Infrastructure Levy Regulations 2010
s.art010 Street works
s.art011 Application of the 1991 Act
s.art012 Power to alter layout, etc. of streets
s.art013 Temporary stopping up of streets and public rights of way
s.art014 Access to works
s.art015 Agreements with street authorities
s.art016 Discharge of water
s.art017 Protective work to buildings
s.art018 Authority to survey and investigate the land
s.art019 Compulsory acquisition of right: incorporation of the mineral code
s.art020 Time limit for exercise of authority to acquire rights compulsorily
s.art021 Compulsory acquisition of rights
s.art022 Crown rights
s.art023 Extinguishment and suspension of private rights
s.art024 Extinguishment of private rights and restrictive covenants relating to apparatus removed from land subject to temporary possession
s.art025 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art026 Acquisition of subsoil or air-space only
s.art027 Rights under or over streets
s.art028 Temporary use of land by National Grid
s.art029 Temporary use of land by UK Power Networks
s.art030 Temporary use of land for maintaining the authorised development
s.art031 Special category land
s.art032 Statutory undertakers
s.art033 Recovery of costs of new connections
s.art034 Deemed marine licence
s.art035 Application of landlord and tenant law
s.art036 Operational land for purposes of the 1990 Act
s.art037 Defence to proceedings in respect of statutory nuisance
s.art038 Temporary closure of, and works in, the river Stour
s.art039 Traffic regulation
s.art040 Felling or lopping of trees
s.art041 Trees subject to tree preservation orders
s.art042 Protection of interests
s.art043 Certification of plans, etc.
s.art044 Service of notices
s.art045 Procedure regarding certain approvals, etc.
s.art046 Amendment of local legislation
s.art047 No double recovery
s.art048 Arbitration
Schedules

Schedules

0 of 72 shown
72 other schedules
s.sch001 Work No.5D – Removal of part of the PY route
s.sch001 Work No.6A — PX route removal
s.sch001 Work No.6B — PX route removal
s.sch001 Work No.6C — PX route removal
s.sch001 Work No.4A — PX route temporary diversion
s.sch001 Work No.4B – PX route temporary diversion
s.sch001 Work No.4C — PX route temporary diversion
s.sch001 Work No.5A — Temporary diversion of part of the PY route.
s.sch001 Work No.5B — Temporary diversion of part of the PY route.
s.sch001 Work No.5C —PY route
s.sch003 Interpretation
s.sch003 Retention and protection of existing trees and hedgerows
s.sch003 Bird flight diverters
s.sch003 Reinstatement schemes
s.sch003 Contamination of land or groundwater and controlled waters
s.sch003 Inspection of temporary watercourses
s.sch003 Removal of temporary bridges and culverts
s.sch003 Highway works
s.sch003 Clearance over the tidal River Stour
s.sch003 Removal of UK Power Networks Works
s.sch003 Decommissioning
s.sch003 Time Limits
s.sch003 Ancient Woodland Easement Management Plan
s.sch003 Location of Pylon PC10
s.sch003 Exercise of powers of compulsory acquisition in relation to the imposition of restrictions by National Grid
s.sch003 Design drawings
s.sch003 Stages of authorised development
s.sch003 Construction Environmental Management Plan
s.sch003 Approval and implementation of construction mitigation plans
s.sch003 Construction hours
s.sch003 Mitigation planting
s.sch003 Implementation of mitigation planting
s.sch004 Applications made under requirements
s.sch004 Fees
s.sch004 Appeals
s.sch004 Outcome of appeals
s.sch004 Interpretation of Schedule 4
s.sch009 Interpretation
s.sch009 The licence holder must inform the MMO Local Office in...
s.sch009 The licence holder must inform the relevant harbour authorities in...
s.sch009 Upon commencement of the works
s.sch009 Bunding and/or storage facilities must be installed to contain and...
s.sch009 The licence holder must ensure that any oil, fuel or...
s.sch009 Any construction materials that are misplaced below mean high water...
s.sch009 The licence holder must ensure that the MMO Local Office...
s.sch009 All equipment, temporary structures, waste and debris associated with the...
s.sch009 The licence holder must ensure that if maintenance is required...
s.sch009 Addresses
s.sch009 (1) Subject to the licence conditions in Part 4 of...
s.sch009 Any breach of this licence does not constitute a breach...
s.sch009 For such of the licensed activities that involve the construction,...
s.sch009 Should the licence holder become aware that any of the...
s.sch009 Prior to the commencement of the works
s.sch009 The licence holder must inform the MMO, the Environment Agency,...
s.sch009 The licence holder must ensure that they inform the MMO...
s.sch010 Compensation enactments
s.sch010 (1) Without limitation on the scope of paragraph 1, the...
s.sch010 Application of the 1965 Act
s.sch010 For section 7 of the 1965 Act (measure of compensation)...
s.sch010 For section 8 of the 1965 Act (provisions as to...
s.sch010 The following provisions of the 1965 Act (which state the...
s.sch010 Section 11 of the 1965 Act (powers of entry) is...
s.sch010 Section 20 of the 1965 Act (protection for interests of...
s.sch010 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch014 Nothing in this Order, or in any enactment incorporated with...
s.sch014 The undertaker must no later than 28 days from the...
s.schedule/1/chapter/1/crossheading/in/the/city/of/c Work No.1—PC route Canterbury North 400kV Substation to Richborough 400kV Substation
s.schedule/1/chapter/1/crossheading/in/the/city/of/c Work No.2 — Temporary site compound
s.schedule/1/chapter/1/crossheading/in/the/district/ Work No.3 — Temporary site compound
s.schedule/1/chapter/2/crossheading/in/the/city/of/c Work No.6D — PX route removal
s.schedule/1/chapter/2/crossheading/in/the/district/ Work No.6F — PX route removal
s.schedule/1/chapter/2/crossheading/in/the/district/ Work No.6E — PX route removal

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.