UK Statutory Instrument SI 2016/863 United Kingdom

The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1

Plus 1 duty on the regulator, Crown ministers and public bodies — folded into the section list below.

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art019 Authority to survey and investigate the land Regulated
Other duties (1) — Crown / regulator
  • Notify landowners and compensate before surveying landCrown / Minister / Government department
58 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Maintenance of authorised development
s.art005 Planning permission
s.art006 Power to deviate
s.art007 Benefit of the Order
s.art008 Consent to transfer benefit of the Order
s.art009 Application of the 1991 Act
s.art010 Power to alter layout etc. of streets
s.art011 Street works
s.art012 Construction and maintenance of new, altered or diverted streets
s.art013 Permanent stopping up of streets
s.art014 Temporary stopping up of streets
s.art015 Access to works
s.art016 Powers in relation to relevant navigations or watercourses
s.art017 Discharge of water
s.art018 Protective work to buildings
s.art020 Compulsory acquisition of land
s.art021 Time limit for exercise of authority to acquire land compulsorily
s.art022 Compulsory acquisition of rights
s.art023 Private rights over land
s.art024 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art025 Acquisition of subsoil or air-space only
s.art026 Acquisition of part of certain properties
s.art027 Rights under or over streets
s.art028 Temporary use of land for carrying out the authorised development
s.art029 Temporary use of land for maintaining the authorised development
s.art030 Statutory undertakers
s.art031 Apparatus and rights of statutory undertakers in stopped up streets
s.art032 Recovery of costs of new connections
s.art033 Compulsory acquisition of land – incorporation of the mineral code
s.art034 Special category land
s.art035 Felling or lopping of trees
s.art036 Trees subject to tree preservation orders
s.art037 Operational land for purposes of the 1990 Act
s.art038 Defence to proceedings in respect of statutory nuisance
s.art039 Protection of interests
s.art040 Certification of plans, etc.
s.art041 Service of notices
s.art042 Arbitration
s.art043 Traffic regulation
s.art044 Procedure in relation to certain approvals etc.
s.p01905/schedule/1/paragraph/1n1 In the administrative areas of West Berkshire Council, Wokingham Borough Council, Reading Borough Council, the Royal Borough of Windsor and Maidenhead, Bracknell Forest Council, Buckinghamshire County Council, South Bucks District Council, Slough Borough Council, the London Borough of Hillingdon, the London Borough of Hounslow and the Greater London Authority
s.p01905/schedule/1/paragraph/1n10 In the administrative area of Slough Borough Council and the Royal Borough of Windsor and Maidenhead
s.p01905/schedule/1/paragraph/1n11 In the administrative area of the Royal Borough of Windsor and Maidenhead
s.p01905/schedule/1/paragraph/1n12 In the administrative areas of the Royal Borough of Windsor and Maidenhead and Slough Borough Council
s.p01905/schedule/1/paragraph/1n13 In the administrative areas of Buckinghamshire County Council, South Bucks District Council and Slough Borough Council
s.p01905/schedule/1/paragraph/1n14 In the administrative area of Slough Borough Council
s.p01905/schedule/1/paragraph/1n15 In the administrative area of the London Borough of Hillingdon
s.p01905/schedule/1/paragraph/1n2 In the administrative area of West Berkshire Council
s.p01905/schedule/1/paragraph/1n3 In the administrative area of Wokingham Borough Council and Reading Borough Council
s.p01905/schedule/1/paragraph/1n4 In the administrative area of Wokingham Borough Council
s.p01905/schedule/1/paragraph/1n5 In the administrative area of the Royal Borough of Windsor and Maidenhead
s.p01905/schedule/1/paragraph/1n6 In the administrative areas of the Royal Borough of Windsor and Maidenhead and Buckinghamshire County Council, South Bucks District Council
s.p01905/schedule/1/paragraph/1n7 In the administrative area of Buckinghamshire County Council, South Bucks District Council
s.p01905/schedule/1/paragraph/1n8 In the administrative area of Buckinghamshire County Council, South Bucks District Council and Slough Borough Council
s.p01905/schedule/1/paragraph/1n9 In the administrative area of Slough Borough Council
Schedules

Schedules

1 of 156 shown
s.sch009 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay compensation for damage to electronic communications apparatus or service interruptionStatutory Undertaker
155 other schedules
s.sch002 Interpretation
s.sch002 Fencing
s.sch002 Ecological mitigation
s.sch002 Contaminated land and groundwater
s.sch002 Protected species
s.sch002 Surface water drainage
s.sch002 Archaeological remains
s.sch002 Written scheme of investigation
s.sch002 Buildings at risk
s.sch002 Construction traffic management
s.sch002 Permanent lighting
s.sch002 Time limits
s.sch002 Amendments to approved details
s.sch002 Control of noise during construction of the scheme
s.sch002 Acoustic barriers
s.sch002 Flood risk
s.sch002 Biodiversity management strategy
s.sch002 Road restraint standard
s.sch002 Air quality monitoring and management
s.sch002 Applications made under requirement
s.sch002 Further information
s.sch002 Register of requirements
s.sch002 Detailed design
s.sch002 Details of consultation
s.sch002 Gantry design
s.sch002 Carriageway surfacing
s.sch002 Engineering drawings, sections and other information
s.sch002 Environmental Management Plan
s.sch002 Construction Environmental Management Plan
s.sch002 Implementation and maintenance of landscaping
s.sch006 The enactments for the time being in force with respect...
s.sch006 (1) Without limitation on the scope of paragraph 1, the...
s.sch006 (1) The 1965 Act has effect with the modifications necessary...
s.sch006 For section 7 (measure of compensation in case of severance)...
s.sch006 For section 8 (provisions as to divided land) of the...
s.sch006 The following provisions of the 1965 Act (which state the...
s.sch006 Section 11 (powers of entry) of the 1965 Act is...
s.sch006 Section 20 (protection for interests of tenants at will, etc.)...
s.sch006 Section 22 (interests omitted from purchase) of the 1965 Act...
s.sch009 For the protection of the protected persons referred to in...
s.sch009 (1) Subject to the following provisions of this paragraph, the...
s.sch009 For the protection of the protected persons referred to in...
s.sch009 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch009 This Part of this Schedule does not apply to apparatus...
s.sch009 (1) Where any street is stopped up under article 13...
s.sch009 The undertaker, in the case of the powers conferred by...
s.sch009 Regardless of any provision in this Order or anything shown...
s.sch009 (1) If, in the exercise of the powers conferred by...
s.sch009 (1) Where, in accordance with the provisions of this Part...
s.sch009 (1) Not less than 28 days before starting the execution...
s.sch009 (1) Subject to the following provisions of this paragraph, the...
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 Where in consequence of the proposed construction of any of...
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 Where in consequence of the proposed construction of any of...
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 For the protection of any operator, the following provisions have...
s.sch009 In this Part of this Schedule— “the 2003 Act” means...
s.sch009 The exercise of the powers conferred by article 30 (statutory...
s.sch009 This Part of this Schedule does not apply to—
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch009 The following provisions of this Part of this Schedule have...
s.sch009 In this Part of this Schedule— “construction” includes execution, placing,...
s.sch009 (1) Where under this Part of this Schedule Network Rail...
s.sch009 (1) The undertaker must not exercise the powers conferred by...
s.sch009 (1) The undertaker must, before commencing construction of any specified...
s.sch009 (1) Any specified work and any protective works to be...
s.sch009 (1) The undertaker must— (a) at all times afford reasonable...
s.sch009 Network Rail must at all reasonable times afford reasonable facilities...
s.sch009 (1) If any permanent or temporary alterations or additions to...
s.sch009 The undertaker must repay to Network Rail all reasonable fees,...
s.sch009 This Part of this Schedule does not apply to apparatus...
s.sch009 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch009 If at any time after the completion of a specified...
s.sch009 The undertaker must not provide any illumination or illuminated sign...
s.sch009 Any additional expenses which Network Rail may reasonably incur in...
s.sch009 (1) The undertaker must pay to Network Rail all reasonable...
s.sch009 Network Rail must, on receipt of a request from the...
s.sch009 In the assessment of any sums payable to Network Rail...
s.sch009 The undertaker and Network Rail may, subject in the case...
s.sch009 Nothing in this Order, or in any enactment incorporated with...
s.sch009 The undertaker must give written notice to Network Rail where...
s.sch009 (1) Where any street is stopped up under article 13...
s.sch009 The undertaker must no later than 28 days from the...
s.sch009 Application
s.sch009 Interpretation
s.sch009 Except for paragraphs 44 (apparatus of undertakers in stopped up...
s.sch009 Apparatus of National Grid in stopped up streets
s.sch009 Protective works to buildings
s.sch009 Acquisition of land
s.sch009 Removal of apparatus
s.sch009 Facilities and rights for alternative apparatus
s.sch009 Retained apparatus: protection for gas undertakers
s.sch009 The undertaker, in the case of the powers conferred by...
s.sch009 Retained apparatus: protection for electricity undertakers
s.sch009 Expenses
s.sch009 Indemnity
s.sch009 Enactments and agreements
s.sch009 Co-operation
s.sch009 Access
s.sch009 Arbitration
s.sch009 For the protection of the protected persons referred to in...
s.sch009 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch009 On street apparatus
s.sch009 Regardless of any provision in this Order or anything shown...
s.sch009 Apparatus in stopped up streets
s.sch009 Protective works to buildings
s.sch009 Acquisition of land
s.sch009 Removal of apparatus
s.sch009 Facilities and rights for alternative apparatus
s.sch009 Retained apparatus
s.sch009 Expenses and costs
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 Co-operation
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 (1) If, in the exercise of the powers conferred by...
s.sch009 (1) The following provisions apply for the protection of the...
s.sch009 (1) Where, in the exercise of the powers conferred by...
s.sch009 If, in the exercise of the powers conferred by this...
s.sch009 The undertaker must maintain, inspect and retain any Flood Protection...
s.sch009 The undertaker must allow the Agency reasonable access to any...
s.sch009 (1) Where maintenance of any Flood Protection Work specified in...
s.sch009 If by reason of the construction of the authorised development...
s.sch009 The undertaker must indemnify the Agency in respect of all...
s.sch009 The fact that any work or thing has been executed...
s.sch009 Any dispute arising between the undertaker and the Agency under...
s.sch009 (1) Where, in accordance with the provisions of this Part...
s.sch009 Access to Slough Sewage Treatment Works
s.sch009 Iver South Sludge Dewatering Centre
s.sch009 (1) The undertaker must not in the exercise of the...
s.sch009 For the protection of the protected persons referred to in...
s.sch009 In this Part of this Schedule— “alternative apparatus” means alternative...
s.sch009 On street apparatus
s.sch009 Apparatus in stopped up streets
s.sch009 Protective works to buildings
s.sch009 Acquisition of land
s.sch009 Removal of apparatus
s.sch009 (1) Not less than 28 days before starting the execution...
s.sch009 Facilities and rights for alternative apparatus
s.sch009 Retained apparatus
s.sch009 Expenses and costs
s.sch009 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009 Co-operation
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 The following provisions of this Part of this Schedule have...
s.sch009 In this Part of this Schedule— “Heathrow Airport” means Heathrow...
s.sch009 (1) The undertaker must not exercise the powers conferred by...
s.sch009 Any difference or dispute arising between the undertaker and Heathrow...
s.sch011 Applications made for certain approvals
s.sch011 Further information
s.sch011 Fees
s.sch011 Appeals
s.sch011 Interpretation of Schedule 11

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.