What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art017 Authority to survey and investigate the land Regulated
  • Allow authorised surveyors to enter land for wind farm connection worksStatutory Undertaker
s.art022 Funding Regulated
  • Secure compensation liabilities before exercising land powersStatutory Undertaker
38 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent etc. granted by the Order
s.art004 Limits of deviation
s.art005 Operation of authorised development
s.art006 Maintenance of authorised development
s.art007 Benefit of the Order
s.art008 Consent to transfer benefit of the Order
s.art009 Power to alter layout, etc., of streets
s.art010 Street works
s.art011 Construction and maintenance of new or altered means of access
s.art012 Temporary prohibition or restriction of use of streets and public rights of way
s.art013 Traffic regulation
s.art014 Access to works
s.art015 Agreements with street authorities
s.art016 Discharge of water
s.art018 Compulsory acquisition of rights
s.art019 Crown land
s.art020 Statutory authority to override easements and other rights
s.art021 Time limit for exercise of authority to acquire rights compulsorily
s.art023 Private rights
s.art024 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art025 Acquisition of subsoil or airspace only
s.art026 Rights under or over streets
s.art027 Temporary use of land for carrying out the authorised development
s.art028 Temporary use of land for maintaining and decommissioning the authorised development
s.art029 Statutory undertakers
s.art030 Recovery of costs of new connections
s.art031 Felling or lopping of trees and removal of hedgerows
s.art032 Application of landlord and tenant law
s.art033 Disapplication of legislative provisions
s.art034 Defence to proceedings in respect of statutory nuisance
s.art035 Crown rights
s.art036 Certification of plans
s.art037 Application and modification of legislative provisions
s.art038 Service of notices
s.art039 Procedure in relation to certain approvals etc.
s.art040 Arbitration
Schedules

Schedules

2 of 59 shown
s.sch009 Protection of DCC apparatus Regulated
  • Notify DCC and obtain approval before starting works affecting their apparatusStatutory Undertaker
s.sch009 (1) Subject to sub-paragraphs (2) to (4), if as the... Regulated
  • Pay for damage to electronic communications apparatus or service interruptionStatutory Undertaker
57 other schedules
s.sch002 Interpretation
s.sch002 Construction Hours
s.sch002 Contaminated land and groundwater
s.sch002 Archaeology
s.sch002 Construction Environmental Management Plan
s.sch002 Piling
s.sch002 Restoration of land used temporarily for construction
s.sch002 Requirement for written approval
s.sch002 Decommissioning
s.sch002 Decommissioning Environmental Management Plan
s.sch002 Expiry of development consent
s.sch002 Time limits
s.sch002 Requirements for written approval, etc.
s.sch002 Approved plans and amendments to approved plans.
s.sch002 Detailed Design
s.sch002 Stages of authorised development
s.sch002 Landscaping
s.sch002 Dying, diseased, damaged planting
s.sch002 Reinstatement planting
s.sch002 Felling
s.sch002 Highway works
s.sch007 The enactments in force with respect to compensation for the...
s.sch007 (1) The Land Compensation Act 1973 has effect subject to...
s.sch007 (1) The 1965 Act has effect for the compulsory acquisition...
s.sch007 For section 7 of the 1965 Act (measure of compensation)...
s.sch007 For section 8 of the 1965 Act (provisions as to...
s.sch007 The following provisions of the 1965 Act (which state the...
s.sch007 Section 11 of the 1965 Act (powers of entry) is...
s.sch007 Section 20 of the 1965 Act (protection for interests of...
s.sch007 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch009 (1) For the protection of any operator, the following provisions...
s.sch009 Suspension of works
s.sch009 (1) In the event that either the undertaker or DCC...
s.sch009 Emergency Works
s.sch009 Insurance
s.sch009 Damage to DCC apparatus
s.sch009 (1) The following provisions shall apply for the protection of...
s.sch009 Regardless of any provision in this Order or anything shown...
s.sch009 (1) Before beginning to construct any specified work, the undertaker...
s.sch009 The requirements which the consenting authority may make under paragraph...
s.sch009 The exercise of the powers of article 29 (statutory undertakers)...
s.sch009 (1) Subject to sub-paragraph (2), any specified work, and all...
s.sch009 (1) Subject to sub-paragraph (6) the undertaker shall, from the...
s.sch009 If by reason of the construction of any specified work...
s.sch009 The fact that any work or thing has been executed...
s.sch009 This Part of this Schedule does not apply to—
s.sch009 Nothing in this Part of this Schedule affects the provisions...
s.sch009 For the protection of DCC referred to in this Part...
s.sch009 In this Part of this Schedule— “acceptable insurance” means a...
s.sch009 (1) Regardless of any provision in this Order or anything...
s.sch009 Precedence of the WIA 1991
s.sch010 Applications made under Requirements
s.sch010 Further information
s.sch010 Appeals
s.sch010 On an appeal under this paragraph, the appointed person may—...
s.sch010 (1) The decision of the appointed person on an appeal...
s.sch010 In this Schedule— “relevant authority” means the relevant planning authority,...