What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch009

Protection of DCC apparatus

  • Notify DCC and obtain approval before starting works affecting their apparatus
s.sch009

(1) Subject to sub-paragraphs (2) to (4), if as the...

  • Pay for damage to electronic communications apparatus or service interruption
Browse 57 other Schedules — structural / supplementary
s.sch002

Interpretation

s.sch002

Construction Hours

s.sch002

Contaminated land and groundwater

s.sch002

Archaeology

s.sch002

Construction Environmental Management Plan

s.sch002

Piling

s.sch002

Restoration of land used temporarily for construction

s.sch002

Requirement for written approval

s.sch002

Decommissioning

s.sch002

Decommissioning Environmental Management Plan

s.sch002

Expiry of development consent

s.sch002

Time limits

s.sch002

Requirements for written approval, etc.

s.sch002

Approved plans and amendments to approved plans.

s.sch002

Detailed Design

s.sch002

Stages of authorised development

s.sch002

Landscaping

s.sch002

Dying, diseased, damaged planting

s.sch002

Reinstatement planting

s.sch002

Felling

s.sch002

Highway works

s.sch007

The enactments in force with respect to compensation for the...

s.sch007

(1) The Land Compensation Act 1973 has effect subject to...

s.sch007

(1) The 1965 Act has effect for the compulsory acquisition...

s.sch007

For section 7 of the 1965 Act (measure of compensation)...

s.sch007

For section 8 of the 1965 Act (provisions as to...

s.sch007

The following provisions of the 1965 Act (which state the...

s.sch007

Section 11 of the 1965 Act (powers of entry) is...

s.sch007

Section 20 of the 1965 Act (protection for interests of...

s.sch007

Section 22 of the 1965 Act (protection of acquiring authority’s...

s.sch009

(1) For the protection of any operator, the following provisions...

s.sch009

Suspension of works

s.sch009

(1) In the event that either the undertaker or DCC...

s.sch009

Emergency Works

s.sch009

Insurance

s.sch009

Damage to DCC apparatus

s.sch009

(1) The following provisions shall apply for the protection of...

s.sch009

Regardless of any provision in this Order or anything shown...

s.sch009

(1) Before beginning to construct any specified work, the undertaker...

s.sch009

The requirements which the consenting authority may make under paragraph...

s.sch009

The exercise of the powers of article 29 (statutory undertakers)...

s.sch009

(1) Subject to sub-paragraph (2), any specified work, and all...

s.sch009

(1) Subject to sub-paragraph (6) the undertaker shall, from the...

s.sch009

If by reason of the construction of any specified work...

s.sch009

The fact that any work or thing has been executed...

s.sch009

This Part of this Schedule does not apply to—

s.sch009

Nothing in this Part of this Schedule affects the provisions...

s.sch009

For the protection of DCC referred to in this Part...

s.sch009

In this Part of this Schedule— “acceptable insurance” means a...

s.sch009

(1) Regardless of any provision in this Order or anything...

s.sch009

Precedence of the WIA 1991

s.sch010

Applications made under Requirements

s.sch010

Further information

s.sch010

Appeals

s.sch010

On an appeal under this paragraph, the appointed person may—...

s.sch010

(1) The decision of the appointed person on an appeal...

s.sch010

In this Schedule— “relevant authority” means the relevant planning authority,...

s.art017

Authority to survey and investigate the land

  • Allow authorised surveyors to enter land for wind farm connection works
s.art022

Funding

  • Secure compensation liabilities before exercising land powers
Browse 38 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent etc. granted by the Order

s.art004

Limits of deviation

s.art005

Operation of authorised development

s.art006

Maintenance of authorised development

s.art007

Benefit of the Order

s.art008

Consent to transfer benefit of the Order

s.art009

Power to alter layout, etc., of streets

s.art010

Street works

s.art011

Construction and maintenance of new or altered means of access

s.art012

Temporary prohibition or restriction of use of streets and public rights of way

s.art013

Traffic regulation

s.art014

Access to works

s.art015

Agreements with street authorities

s.art016

Discharge of water

s.art018

Compulsory acquisition of rights

s.art019

Crown land

s.art020

Statutory authority to override easements and other rights

s.art021

Time limit for exercise of authority to acquire rights compulsorily

s.art023

Private rights

s.art024

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

s.art025

Acquisition of subsoil or airspace only

s.art026

Rights under or over streets

s.art027

Temporary use of land for carrying out the authorised development

s.art028

Temporary use of land for maintaining and decommissioning the authorised development

s.art029

Statutory undertakers

s.art030

Recovery of costs of new connections

s.art031

Felling or lopping of trees and removal of hedgerows

s.art032

Application of landlord and tenant law

s.art033

Disapplication of legislative provisions

s.art034

Defence to proceedings in respect of statutory nuisance

s.art035

Crown rights

s.art036

Certification of plans

s.art037

Application and modification of legislative provisions

s.art038

Service of notices

s.art039

Procedure in relation to certain approvals etc.

s.art040

Arbitration

Explore more

Browse legislation

Find other UK business legislation with related guidance.