UK Statutory Instrument SI 2014/1599 United Kingdom

The East Anglia ONE Offshore Wind Farm Order 2014

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

sch. 9 para. 3 sch. 9 para. 3 Regulated
  • Pay costs, compensate and indemnify for damage to electronic communications apparatusStatutory Undertaker
53 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent
s.art004 Power to construct and maintain authorised project
s.art005 Benefit of the Order
s.art006 Application and modification of legislative provisions
s.art007 Defence to proceedings in respect of statutory nuisance
s.art008 Street works
s.art009 Temporary stopping up of public rights of way
s.art010 Temporary stopping up of streets
s.art011 Access to works
s.art012 Agreements with street authorities
s.art013 Discharge of water
s.art014 Authority to survey and investigate the land
s.art015 Compulsory acquisition of land
s.art016 Time limit for exercise of authority to acquire land compulsorily
s.art017 Compulsory acquisition of rights
s.art018 Private rights
s.art019 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art020 Acquisition of subsoil only
s.art021 Acquisition of part of certain properties
s.art022 Rights under or over streets
s.art023 Temporary use of land for carrying out the authorised project
s.art024 Temporary use of land for maintaining authorised project
s.art025 Protective provisions for specified
s.art026 Statutory undertakers
s.art027 Recovery of costs of new connections
s.art028 Operation of generating station
s.art029 Deemed marine licences under the Marine and Coastal Access Act 2009
s.art030 Application of landlord and tenant law
s.art031 Operational land for purposes of the
s.art032 Felling or lopping of trees and removal of hedgerows
s.art033 Certification of plans etc.
s.art034 Arbitration
s.art035 Requirements, appeals, etc.
s.art036 Abatement of works abandoned or decayed
s.art037 Saving provisions for
s.art038 Crown rights
Schedules

Schedules

0 of 74 shown
74 other schedules
s.sch001 Detailed design approval onshore
s.sch001 Landfall method statement
s.sch001 Provision of landscaping
s.sch001 Implementation and maintenance of landscaping
s.sch001 Highway accesses and improvements
s.sch001 Fencing and other means of enclosure
s.sch001 Surface and foul water drainage
s.sch001 Contaminated land and ground water
s.sch001 Archaeology
s.sch001 Ecological management plan
s.sch001 Code of construction practice
s.sch001 External lighting and control of artificial light emissions
s.sch001 Control of noise during construction
s.sch001 Construction hours
s.sch001 Control of noise during operational phase
s.sch001 Traffic
s.sch001 Port travel plan
s.sch001 European protected species
s.sch001 Restoration of land used temporarily for construction
s.sch001 Installation of cable ducts
s.sch001 Skills strategy
s.sch001 Onshore decommissioning
s.sch001 Decommissioning of Work No. 3B and Work No. 4
s.sch001 Requirement for written approval
s.sch001 Amendments to approved details
s.sch001 Transmission system
s.sch001 Marine mammal mitigation protocol
s.sch001 No meteorological mast, wind turbine generator or offshore substation forming...
s.sch001 (1) The total number of offshore substations forming part of...
s.sch001 (1) The total length of the cables comprising Work No....
s.sch001 (1) In relation to a WTG, each gravity base foundation...
s.sch001 As built offshore parameters
s.sch001 Aviation safety
s.sch001 Offshore decommissioning
s.sch007 Compensation enactments
s.sch007 (1) Without prejudice to the generality of paragraph 1, the...
s.sch007 Application of the 1965 Act
s.sch007 For section 7 of the 1965 Act (measure of compensation)...
s.sch007 For section 8 of the 1965 Act (provisions as to...
s.sch007 The following provisions of the 1965 Act (which state the...
s.sch007 Section 11 of the 1965 Act (powers of entry) shall...
s.sch007 Section 20 of the 1965 Act (protection for interests of...
s.sch007 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch009 Network Rail must, on receipt of a request from the...
s.sch009 In the assessment of any sums payable to Network Rail...
s.sch009 The undertakers and Network Rail may, subject in the case...
s.sch009 Nothing in this Order, or in any enactment incorporated with...
s.sch009 The undertakers must give written notice to Network Rail where...
s.sch009 The undertakers must no later than 28 days from the...
s.sch010 Force majeure
s.sch010 Pre-construction plans and documentation
s.sch010 (1) Any archaeological reports produced in accordance with condition 11(h)(iii)...
s.sch010 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch010 Foundation restrictions
s.sch010 Reporting of engaged agents, contractors and vessels
s.sch010 Equipment and operation of vessels engaged in licensed activities
s.sch010 Pre-construction monitoring and surveys
s.sch010 Construction monitoring
s.sch010 Post construction
s.sch010 Offshore safety management
s.sch010 Aids to navigation
s.sch010 Chemicals, drilling and debris
s.sch011 Pre-construction plans and documentation
s.sch011 (1) Any archaeological reports produced in accordance with condition 11(h)(iii)...
s.sch011 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch011 Foundation restrictions
s.sch011 Reporting of engaged agents, contractors and vessels
s.sch011 Equipment and operation of vessels engaged in licensed activities
s.sch011 Pre-construction monitoring and surveys
s.sch011 Construction monitoring
s.sch011 Post construction
s.sch011 Aids to navigation
s.sch011 Chemicals, drilling and debris
s.sch011 Force majeure