UK Statutory Instrument 2013 United Kingdom

The National Grid (King’s Lynn B Power Station Connection) Order 2013

At a glance

What's here

1 compliance obligation

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

Browse 36 other Schedules — structural / supplementary
s.sch002

Interpretation

s.sch002

Archaeology

s.sch002

Landscape and ecological management plan

s.sch002

Code of construction practice

s.sch002

External lighting

s.sch002

Construction traffic

s.sch002

Control of noise during construction and maintenance

s.sch002

Construction hours

s.sch002

Control of dust emissions

s.sch002

Accumulations and deposits

s.sch002

Restoration of land used temporarily for construction

s.sch002

Time limits

s.sch002

Requirement for written approval

s.sch002

Amendments to approved details

s.sch002

Compliance with approved details

s.sch002

Provision of landscaping

s.sch002

Implementation and maintenance of landscaping

s.sch002

Highway accesses

s.sch002

Fencing and other means of enclosure

s.sch002

Contaminated land and groundwater

s.sch002

Controlled water protection scheme

s.sch003

Compensation enactments

s.sch003

Modification of the Land Compensation Act 1973

s.sch003

Application of the 1965 Act

s.sch003

For section 7 of the 1965 Act (measure of compensation...

s.sch003

For section 8 of the 1965 Act (other provisions as...

s.sch003

The following provisions of the 1965 Act (which state the...

s.sch003

Section 11 of the 1965 Act (powers of entry) is...

s.sch003

Section 20 of the 1965 Act (protection for interests of...

s.sch003

Section 22 of the 1965 Act (protection of acquiring authority’s...

s.sch009

Applications made under requirement

s.sch009

Further information

s.sch009

Appeals

s.sch009

Appeal process

s.sch009

Fees

s.sch009

Interpretation of Schedule 9

s.art017

Authority to survey and investigate the land

  • Give 14 days' notice before entering land for survey or investigation
Browse 40 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Application and modification of legislative provisions

s.art004

Development consent

s.art005

Maintenance of authorised development

s.art006

Limits of deviation

s.art007

Benefit of Order

s.art008

Consent to transfer benefit of Order

s.art009

Application of the

s.art010

Street works

s.art011

Temporary closure of streets and public rights of way

s.art012

Access to works

s.art013

Agreements with street authorities

s.art014

Discharge of water

s.art015

Defence to proceedings in respect of statutory nuisance

s.art016

Protective work to buildings

s.art018

Compulsory acquisition of rights

s.art019

Power to override interests, rights and restrictions

s.art020

Time limit for exercise of authority to acquire rights compulsorily

s.art021

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

s.art022

Acquisition of part of certain properties

s.art023

Acquisition of subsoil or airspace only

s.art024

Rights under or over streets

s.art025

Temporary use of land for carrying out the authorised development

s.art026

Temporary use of land for maintaining the authorised development

s.art027

Statutory undertakers

s.art028

Application of landlord and tenant law

s.art029

Operational land for purposes of the

s.art030

Felling or lopping of trees

s.art031

Protection of interests

s.art032

Certification of plans etc

s.art033

Service of notices

s.art034

Arbitration

s.art035

Procedure regarding certain approvals