UK Statutory Instrument 2013 United Kingdom

The North Blyth Biomass Power Station Order 2013

At a glance

What's here

1 compliance obligation

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

Browse 67 other Schedules — structural / supplementary
s.sch001

In Northumberland the construction use and maintenance of a nationally...

s.sch001

Associated development within the meaning of section 115(2) of the...

s.sch002

Interpretation

s.sch002

Earthworks and remediation

s.sch002

Ecological management

s.sch002

Code of construction practice and

s.sch002

Suppression of dust and dirt during construction

s.sch002

Construction traffic routing and management plan

s.sch002

Control of noise during construction and commissioning

s.sch002

External lighting during construction

s.sch002

Unexploded ordnance (

s.sch002

Travel plan – construction

s.sch002

Flooding – mitigation

s.sch002

Time limits

s.sch002

Flooding – warning and evacuation plan

s.sch002

Fire prevention

s.sch002

Otter mitigation strategy

s.sch002

Asbestos

s.sch002

Storage of liquids on site

s.sch002

Database of tall structures

s.sch002

Aviation safety

s.sch002

European protected species

s.sch002

Construction hours

s.sch002

Piling and vibration

s.sch002

Detailed design

s.sch002

Control of artificial light emissions

s.sch002

Control of dust emissions

s.sch002

Waste management on site

s.sch002

Travel plan and traffic management plan – operational period

s.sch002

Combined heat and power

s.sch002

Site safety and signage

s.sch002

Control of noise during operational phase

s.sch002

External storage

s.sch002

Deliveries of fuel stock by road

s.sch002

Biomass fuel sustainability

s.sch002

Highway accesses

s.sch002

Decommissioning

s.sch002

Workforce development strategy

s.sch002

Requirement for written approval

s.sch002

Amendments to approved details

s.sch002

Fencing and other means of enclosure

s.sch002

Surface and foul water drainage

s.sch002

Surface water drainage – contamination

s.sch002

Contaminated land and groundwater

s.sch002

Disposal of contaminated materials

s.sch004

Activity specific conditions

s.sch005

For the protection of Network Rail

s.sch005

The undertaker shall repay to Network Rail all reasonable fees,...

s.sch005

(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

s.sch005

If at any time after the completion of a specified...

s.sch005

The undertaker shall not provide any illumination or illuminated sign...

s.sch005

Any additional expenses which Network Rail may reasonably incur in...

s.sch005

(1) The undertaker shall pay to Network Rail all reasonable...

s.sch005

Network Rail shall, on receipt of a request from the...

s.sch005

In the assessment of any sums payable to Network Rail...

s.sch005

The undertaker and Network Rail may, subject in the case...

s.sch005

Nothing in this Order, or in any enactment incorporated with...

s.sch005

In this Schedule— “construction” includes execution, placing, alteration and reconstruction...

s.sch005

The undertaker shall give written notice to Network Rail if...

s.sch005

The undertaker shall no later than 28 days from the...

s.sch005

(1) Where, under this Schedule, Network Rail is required to...

s.sch005

(1) The undertaker shall not exercise the powers conferred by...

s.sch005

(1) The undertaker shall before commencing construction of any specified...

s.sch005

(1) Any specified work and any protective works to be...

s.sch005

The undertaker shall— (a) at all times afford reasonable facilities...

s.sch005

Network Rail shall at all times afford reasonable facilities to...

s.sch005

(1) If any permanent or temporary alterations or additions to...

s.art012

Authority to survey and investigate the land

  • Give 14 days' notice and obtain consents before surveying land, and compensate for damage
Browse 33 other sections — procedural / definitional / commencement
sch. 4 para. 1

sch. 4 para. 1

s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent

s.art004

Procedure in relation to approvals etc under the Requirements

s.art005

Maintenance of authorised development

s.art006

Operation of generating station

s.art007

Benefit of Order

s.art008

Defence to proceedings in respect of statutory nuisance

s.art009

Street works

s.art010

Agreements with street authorities

s.art011

Discharge of water

s.art013

Compulsory acquisition of land

s.art014

Compulsory acquisition of land – incorporation of the minerals code

s.art015

Time limit for exercise of authority to acquire land compulsorily

s.art016

Compulsory acquisition of rights

s.art017

Private rights of way

s.art018

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

s.art019

Acquisition of subsoil only

s.art020

Acquisition of part of certain properties

s.art021

Rights under or over streets

s.art022

Statutory undertakers

s.art023

Recovery of costs of new connections

s.art024

Railway and navigation undertakings

s.art025

Application of landlord and tenant law

s.art026

Operational land for purposes of the

s.art027

Deemed licence for purposes of the

s.art028

Certification of plans etc

s.art029

Arbitration

s.art030

Crown rights

s.art031

Protective provisions