UK Statutory Instrument 2013 United Kingdom

The Galloper Wind Farm Order 2013

At a glance

What's here

5 compliance obligations

Who this Act binds

Business-side actors with duties under this Act, ranked by how often they appear.

  • Statutory Undertaker 3
  • Licence Holder 1
  • Any Person 1

Other Acts binding the same actors

For each actor bound by this Act, the other UK Acts that bind them most often. Useful for understanding the full compliance landscape facing each role.

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch002

Reporting of engaged agents, contractors and vessels

  • Report agents, contractors, and vessels to the MMO before and during construction Statutory Undertaker
s.sch002

Equipment and operation of vessels engaged in licensed activities

  • Equip and operate vessels properly for licensed wind farm activities Licence Holder
s.sch002

Notifications and inspections

  • Distribute licence, collect confirmations, and manage inspections and notices Statutory Undertaker
s.sch002

Force majeure

  • Notify MMO in writing within 48 hours when depositing material outside Order limits due to stress of weather Any Person
Browse 53 other Schedules — structural / supplementary
s.sch001

Aids to navigation

s.sch001

The undertaker shall ensure that timely and efficient notices to...

s.sch001

The undertaker shall notify Trinity House, in writing, as soon...

s.sch001

The undertaker shall provide reports on the availability of aids...

s.sch001

The undertaker shall notify the UK Hydrographic Office, in writing,...

s.sch001

(1) The undertaker shall colour all structures yellow starting at...

s.sch001

(1) The undertaker shall exhibit such lights, with such shape,...

s.sch001

Provision against danger to navigation

s.sch001

Offshore decommissioning

s.sch001

Stages of authorised development onshore

s.sch001

Detailed design approval onshore

s.sch001

(1) The connection works and the transmission works shall be...

s.sch001

Provision of landscaping

s.sch001

Implementation and maintenance of landscaping

s.sch001

Fencing and other means of enclosure

s.sch001

Surface and foul water drainage

s.sch001

Archaeology

s.sch001

Ecological management plan

s.sch001

Construction code of practice

s.sch001

Construction hours

s.sch001

Control of noise during operational phase

s.sch001

Control of artificial light emissions

s.sch001

Detailed emergency response plan

s.sch001

European protected species

s.sch001

Restoration of land used temporarily for construction

s.sch001

Interference with telecommunications

s.sch001

Onshore decommissioning

s.sch001

Requirement for written approval

s.sch001

Amendments to approved details

s.sch001

Approval of detailed wind turbine design parameters by the Secretary of State

s.sch001

Further offshore design requirements

s.sch001

(1) The total number of offshore substation platforms, accommodation platforms...

s.sch001

(1) The number of cables forming part of the authorised...

s.sch001

(1) Each monopile foundation forming part of the authorised development...

s.sch001

Offshore safety management

s.sch002

Pre-construction plans and documentation

s.sch002

The undertaker shall ensure that a copy of any agreed...

s.sch002

(1) Except with the prior approval of the MMO, each...

s.sch002

Seasonal restrictions

s.sch002

Pre-construction monitoring

s.sch002

Construction monitoring

s.sch002

Post construction

s.sch002

Offshore decommissioning

s.sch002

Requirement for written approval

s.sch002

(1) The total number of offshore substation platforms, accommodation platforms...

s.sch002

(1) The number of cables forming part of the authorised...

s.sch002

(1) Each monopile foundation forming part of the authorised scheme...

s.sch002

Chemicals, drilling and debris

s.sch006

(1) If, in the exercise of the powers conferred by...

s.sch006

(1) Where, in accordance with the provisions of this Schedule,...

s.sch006

(1) Not less than 28 days before starting the execution...

s.sch006

(1) If in consequence of the exercise of the powers...

s.sch006

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.art015

Authority to survey and investigate the land

  • Give 14 days' notice before surveying land and compensate for damage Statutory Undertaker
Browse 34 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Development consent

s.art004

Maintenance of authorised project

s.art005

Operation of an offshore electricity generating station and keeping of overhead lines

s.art006

Requirements, appeals, etc.

s.art007

Benefit of the Order

s.art008

Public rights of navigation

s.art009

Abatement of works abandoned or decayed

s.art010

Deemed licence under the Marine and Coastal Access Act 2009

s.art011

Saving for

s.art012

Crown rights

s.art013

Street works

s.art014

Agreements with street authorities

s.art016

Compulsory acquisition of land

s.art017

Time limit for exercise of authority to acquire land compulsorily

s.art018

Compulsory acquisition of rights

s.art019

Private rights

s.art020

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

s.art021

Acquisition of subsoil only

s.art022

Rights under or over streets

s.art023

Temporary use of land for carrying out the authorised project

s.art024

Temporary use of land for maintaining authorised project

s.art025

For the protection of specified undertakers

s.art026

Statutory undertakers

s.art027

Recovery of costs of new connections

s.art028

Application of landlord and tenant law

s.art029

Operational land for purposes of the

s.art030

Certification of plans etc.

s.art031

Arbitration

Explore more

Browse legislation

Find other UK business legislation with related guidance.