UK Statutory Instrument SI 2011/41 United Kingdom

The River Mersey (Mersey Gateway Bridge) Order 2011

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker2 Any Person1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts
Any Person — also bound by 2340 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art016 Power to survey and investigate land Regulated
  • Give notice and compensate landowners before surveying landStatutory Undertaker
s.art042 Payment of tolls Regulated
  • Pay tolls for using the Mersey Gateway BridgeAny Person
61 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Application of the 1991 Act
s.art004 Power to construct and maintain works
s.art005 Power to deviate
s.art006 Restriction on works in the River Mersey and saltmarshes
s.art007 Power to execute street works
s.art008 Stopping up of streets
s.art009 Temporary stopping up of streets
s.art010 Access to works
s.art011 Construction and maintenance of new or altered streets
s.art012 Agreements with street authorities
s.art013 Use of the Astmoor Busway for the purposes of the construction of the authorised works
s.art014 Discharge of water
s.art015 Protective works to buildings
s.art017 Additional powers
s.art018 Prohibitions within the new crossing area, etc.
s.art019 Protection of the new crossing, etc.
s.art020 Restriction on mooring of vessels, etc.
s.art021 Power to acquire land
s.art022 Application of Part 1 of the 1965 Act
s.art023 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art024 Power to acquire new rights
s.art025 Rights under or over streets
s.art026 Open Space at Widnes
s.art027 Open Space on Wigg Island
s.art028 Temporary use of land for construction of works
s.art029 Temporary use of land for maintenance of works
s.art030 Disregard of certain interests and improvements
s.art031 Set-off for enhancement in value of retained land
s.art032 Acquisition of part of certain properties
s.art033 Extinction or suspension of private rights of way
s.art034 Time limit for exercise of powers of acquisition
s.art035 Power to operate, use and maintain the new crossing
s.art036 Restriction on use of the new crossing by certain classes of vehicle or person
s.art037 Closing the new crossing
s.art038 No mains or pipes
s.art039 Trespass on the new crossing
s.art040 Offences and power to make byelaws
s.art041 Power to charge tolls
s.art042 Power to make road user charging schemes
s.art043 Power to enter into concession agreements and lease or transfer the undertaking, etc.
s.art044 Application of landlord and tenant law
s.art045 Application of section 2 of the 1991 Act
s.art046 Enforcement
s.art047 Planning permission and supplementary matters
s.art048 Power to lop trees overhanging the authorised works
s.art049 Disapplication of the Commons Act 2006
s.art050 Proceedings in respect of statutory nuisance
s.art051 Saving for Trinity House and protection of navigation
s.art052 Removal of vessels
s.art053 Obstruction of construction of authorised works
s.art054 Disclosure of confidential information
s.art055 Statutory undertakers, etc.
s.art056 Protective provisions
s.art057 Disapplication of provisions relating to the conservation of the River Mersey
s.art058 Disapplication of certain provisions of the Manchester Ship Canal Acts and Orders
s.art059 Certification of plans, etc.
s.art060 Service of notices
s.art061 No double recovery
s.art062 Arbitration
Schedules

Schedules

1 of 131 shown
s.sch010 Access Regulated
  • Provide alternative access to apparatus when obstructed by bridge worksStatutory Undertaker
130 other schedules
s.sch006 The enactments for the time being in force with respect...
s.sch006 (1) Without limiting the scope of paragraph 1, the Land...
s.sch006 (1) The 1965 Act shall have effect with the modifications...
s.sch006 For section 7 of the 1965 Act (measure of compensation...
s.sch006 For section 8 of the 1965 Act (other provisions as...
s.sch006 The following provisions of the 1965 Act (which state the...
s.sch006 Section 11 of the 1965 Act (powers of entry) shall...
s.sch006 Section 20 of the 1965 Act (protection for interests of...
s.sch006 Section 22 of the 1965 Act (interests omitted from purchase)...
s.sch008 In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
s.sch008 The Secretary of State shall be entitled to recover from...
s.sch008 (1) Unless its construction has commenced within 5 years of...
s.sch008 (1) In case of damage to or destruction of a...
s.sch008 (1) Where a tidal work is abandoned, or allowed to...
s.sch008 Having concluded that it is expedient to do so the...
s.sch008 (1) The undertaker shall, at or near to a tidal...
s.sch008 (1) After completion of a tidal work the undertaker shall...
s.sch008 (1) In proceedings for an offence under paragraphs 3, 6...
s.sch008 (1) Where the undertaker is required to give notice of...
s.sch009 (1) Sections 271 to 274 of the 1990 Act (power...
s.sch009 (1) Where a street is stopped up under article 8...
s.sch009 (1) Subject to the following provisions of this paragraph, the...
s.sch010 (1) For the protection of the Manchester Ship Canal Company...
s.sch010 (1) The undertaker shall at all reasonable times on being...
s.sch010 (1) If any reasonable alterations or additions, either permanent or...
s.sch010 (1) The undertaker shall, upon completion of any part of...
s.sch010 (1) Following the completion of any specified work and any...
s.sch010 If as a result of the construction of any specified...
s.sch010 If at any time after the completion of a specified...
s.sch010 Any reasonable and proper additional expenses not otherwise provided for...
s.sch010 Before providing any illumination or illuminated traffic sign on or...
s.sch010 (1) If any canal work is abandoned, and is in...
s.sch010 The undertaker shall repay to MSCC all costs, charges and...
s.sch010 The undertaker shall not under the powers conferred by this...
s.sch010 (1) If any detriment to the Canals or any interference...
s.sch010 Where under any provision of this Part of this Schedule...
s.sch010 Except as provided by this Order, nothing in this Order...
s.sch010 Any differences arising between the undertaker and MSCC under this...
s.sch010 (1) For the protection of the Mersey Docks and Harbour...
s.sch010 Before commencing construction or maintenance of any specified work associated...
s.sch010 (1) The undertaker shall ensure, during the whole period of...
s.sch010 (1) If any specified work is abandoned or falls into...
s.sch010 Any differences arising between the undertaker and MDHC under this...
s.sch010 For the protection of the Agency, the following provisions of...
s.sch010 The undertaker shall not under the powers conferred by this...
s.sch010 In this Part of this Schedule— “accumulation” means any accumulation...
s.sch010 (1) Before beginning to construct any specified work other than...
s.sch010 Without limiting the scope of paragraph 31, the requirements which...
s.sch010 (1) Subject to sub-paragraph (2), any specified work other than...
s.sch010 (1) If, during the construction of any specified work, or...
s.sch010 Before commencing the construction of a specified work the undertaker...
s.sch010 (1) Subject to sub-paragraph (2), the undertaker shall, from the...
s.sch010 (1) If, by reason of the construction of any specified...
s.sch010 (1) The undertaker shall take all such measures as may...
s.sch010 The undertaker shall indemnify the Agency in respect of all...
s.sch010 Where so required by the engineer for the purpose of...
s.sch010 (1) Without prejudice to the other provisions of this Part...
s.sch010 (1) For the purposes of Chapter 2 of Part 2...
s.sch010 Any dispute arising between the undertaker and the Agency under...
s.sch010 Nothing in paragraphs 37(1) and 40(1) shall impose any liability...
s.sch010 For the protection of the Mersey Conservancy and the users...
s.sch010 In this Part of this Schedule— “ACRM” means the Acting...
s.sch010 (1) The undertaker shall not commence any tidal work until—...
s.sch010 (1) The undertaker must at all times comply with the...
s.sch010 When giving any notice required by this Order to Trinity...
s.sch010 (1) The undertaker must reimburse to the ACRM all costs,...
s.sch010 (1) The undertaker shall, before commencing construction of any specified...
s.sch010 Any difference arising between the undertaker and the ACRM under...
s.sch010 For the protection of Network Rail the following provisions of...
s.sch010 In this Part of this Schedule— “construction” includes execution, placing,...
s.sch010 (1) Where under this Part of this Schedule Network Rail...
s.sch010 (1) The undertaker shall not exercise the powers conferred by...
s.sch010 (1) The undertaker shall before commencing construction of any specified...
s.sch010 (1) Any specified work and any protective works to be...
s.sch010 The undertaker shall— (a) at all times afford reasonable facilities...
s.sch010 Network Rail shall at all times afford reasonable facilities to...
s.sch010 (1) If any permanent or temporary alterations or additions to...
s.sch010 The undertaker shall not impede, obstruct or interfere with, as...
s.sch010 The undertaker shall repay to Network Rail all reasonable fees,...
s.sch010 If at any time after the completion of a specified...
s.sch010 The undertaker shall not provide any illumination or illuminated sign...
s.sch010 Any additional expenses which Network Rail may reasonably incur in...
s.sch010 (1) The undertaker shall pay to Network Rail all reasonable...
s.sch010 Network Rail shall, on receipt of a request from the...
s.sch010 In the assessment of any sums payable to Network Rail...
s.sch010 The undertaker and Network Rail may, subject in the case...
s.sch010 Nothing in this Order, or in any enactment incorporated with...
s.sch010 The undertaker shall give written notice to Network Rail if...
s.sch010 The undertaker shall provide and maintain at its own expense...
s.sch010 The undertaker shall, no later than 28 days from the...
s.sch010 Interpretation
s.sch010 No application where street works code applies
s.sch010 Disapplication of Schedule 9 in part
s.sch010 Acquisition of apparatus, etc.
s.sch010 Exercise of powers respecting trial holes
s.sch010 Plan approval
s.sch010 (1) The specified works shall be constructed and, in the...
s.sch010 (1) Subject to the following provisions of this Part of...
s.sch010 (1) Any specified work shall, when commenced, be constructed—
s.sch010 (1) An officer of the company duly appointed for the...
s.sch010 As soon as reasonably practicable after the completion of the...
s.sch010 (1) For the protection of C&W, the following provisions of...
s.sch010 The temporary stopping up or diversion of any street under...
s.sch010 If C&W suffers damage by reason or in consequence of...
s.sch010 Nothing in this Order shall affect any right of a...
s.sch010 (1) The undertaker shall not in the course of constructing...
s.sch011 Initial toll range
s.sch011 (1) Where paragraph 7 applies to a proposed change and...
s.sch011 Where paragraph 7 applies to any proposed change and an...
s.sch011 (1) Where any objections have been made in accordance with...
s.sch011 (1) In any case where the undertaker holds a local...
s.sch011 (1) Where a local inquiry has been held the undertaker...
s.sch011 In this Schedule— “class 1 vehicle” means a moped falling...
s.sch011 Revision of toll ranges
s.sch011 Any revision to the toll ranges referred to in paragraph...
s.sch011 (1) Subject to sub-paragraph (2), the references in this Schedule...
s.sch011 Revision of tolls
s.sch011 (1) Whenever the undertaker proposes to revise the toll that...
s.sch011 Further provisions as to revision of toll ranges and classification of vehicles
s.sch011 (1) Prior to exercising its powers under paragraph 7 the...
s.sch011 (1) Any person may object to the changes proposed by...
s.sch012 Tolls may not be levied in respect of—
s.sch012 Vehicles falling within the following descriptions of motor vehicles shall...
s.sch012 The undertaker may require that an application to enter particulars...
s.sch012 Registration of a vehicle upon the exemptions register, and the...
s.sch012 Where the undertaker receives an application that complies with paragraph...
s.sch012 The undertaker shall remove particulars of a vehicle from the...
s.sch012 Where the registered keeper of a vehicle is aware that...
s.sch012 If the undertaker is no longer satisfied that a vehicle...
s.sch012 Nothing in this Schedule shall prevent the making of a...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.