UK Statutory Instrument SI 2008/2512 United Kingdom

The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art021 Power to survey and investigate land Regulated
  • Comply with conditions when surveying land for the projectStatutory Undertaker
51 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Incorporation of Railways Clauses Acts
s.art004 Application of the
s.art005 Power to construct and maintain works
s.art006 Power to deviate
s.art007 Power to execute street works
s.art008 Stopping up of streets
s.art009 Highways subject to redesignation
s.art010 Temporary stopping up of streets
s.art011 Traffic regulation
s.art012 Access to works
s.art013 Construction and maintenance of new or altered streets
s.art014 Construction of bridges
s.art015 Agreements with street authorities
s.art016 Alterations to level crossings as a result of the authorised works
s.art017 Provision of new level crossings in substitution for existing level crossings
s.art018 Stopping up of level crossings
s.art019 Discharge of water
s.art020 Protective works to buildings
s.art022 Power to acquire land
s.art023 Application of Part 1 of the Compulsory Purchase Act 1965
s.art024 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art025 Power to acquire new rights
s.art026 Rights under or over streets
s.art027 Temporary use of land for construction of works
s.art028 Temporary use of land for maintenance of works
s.art029 Disregard of certain interests and improvements
s.art030 Set-off for enhancement in value of retained land
s.art031 Acquisition of part of certain properties
s.art032 Extinction or suspension of private rights of way
s.art033 Time limit for exercise of powers of acquisition
s.art034 Planning permission and supplementary matters
s.art035 Power to lop trees overhanging the authorised works
s.art036 Power to operate and use railway
s.art037 Power to transfer undertaking
s.art038 Power to charge fares
s.art039 Agreements with
s.art040 Proceedings in respect of statutory nuisance
s.art041 Application of landlord and tenant law
s.art042 Obstruction of construction of authorised works
s.art043 Trespass
s.art044 Disclosure of confidential information
s.art045 Statutory undertakers,
s.art046 Protective provisions
s.art047 As to application of certain railway enactments
s.art048 Application of the Land Drainage Act 1991
s.art049 Certification of plans, etc.
s.art050 Service of notices
s.art051 No double recovery
s.art052 Arbitration
Schedules

Schedules

0 of 44 shown
44 other schedules
s.sch006 The enactments for the time being in force with respect...
s.sch006 (1) Without prejudice to the generality of paragraph 1, the...
s.sch006 (1) The 1965 Act shall have effect with the modifications...
s.sch006 For section 7 of the 1965 Act (measure of compensation)...
s.sch006 For section 8 of the 1965 Act (provisions as to...
s.sch006 The following provisions of the 1965 Act (which state the...
s.sch006 Section 11 of the 1965 Act (powers of entry) shall...
s.sch006 Section 20 of the 1965 Act (protection for interests of...
s.sch006 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch009 (1) Sections 271 to 274 of the 1990 Act (power...
s.sch009 (1) Where a street is stopped up under article 8...
s.sch009 (1) Subject to the following provisions of this paragraph, the...
s.sch010 The following provisions of this Schedule shall have effect unless...
s.sch010 The undertaker shall repay to Network Rail all reasonable fees,...
s.sch010 If at any time after the completion of a specified...
s.sch010 The undertaker shall not provide any illumination or illuminated sign...
s.sch010 Any additional expenses which Network Rail may reasonably incur in...
s.sch010 (1) The undertaker shall pay to Network Rail all reasonable...
s.sch010 Network Rail shall, on receipt of a request from the...
s.sch010 In the assessment of any sums payable to Network Rail...
s.sch010 The undertaker and Network Rail may, subject in the case...
s.sch010 (1) In this Part of this Schedule— “alternative apparatus” means...
s.sch010 (1) Notwithstanding the temporary stopping up or diversion of any...
s.sch010 In this Part of this Schedule— “construction” includes execution, placing,...
s.sch010 Notwithstanding anything in this Order or shown on the works...
s.sch010 (1) If, in the exercise of the powers conferred by...
s.sch010 (1) Where, in accordance with the provisions of this Part...
s.sch010 (1) Not less than 56 days before commencing the execution...
s.sch010 Where, by reason of this Order, any part of any...
s.sch010 (1) Subject to the following provisions of this paragraph, the...
s.sch010 (1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch010 (1) Where, by reason of the stopping up of any...
s.sch010 Nothing in this Part of this Schedule shall affect the...
s.sch010 (1) The provisions of this Part of this Schedule shall...
s.sch010 (1) Where under this Schedule Network Rail is required to...
s.sch010 The temporary stopping up or diversion of any street under...
s.sch010 If C&W suffers damage by reason or in consequence of...
s.sch010 Nothing in this Order shall affect any right of a...
s.sch010 (1) The undertaker shall not exercise the powers conferred by...
s.sch010 (1) The undertaker shall before commencing construction of any specified...
s.sch010 (1) Any specified work and any protective works to be...
s.sch010 The undertaker shall— (a) at all times afford reasonable facilities...
s.sch010 Network Rail shall at all times afford reasonable facilities to...
s.sch010 (1) If during the construction of a specified work or...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.