Statutory Undertaker1
Other Acts binding the same actors
If a role above is yours, these are the other instruments that most often bind it.
Statutory Undertaker — also bound by 179 other Acts
The Cory Decarbonisation Project Order 2025
120 duties
Water Industry Act 1991
53 duties
What it requires
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
s.art011
Power to survey and investigate land
Regulated
- Notify landowners before surveying and pay compensation for damageStatutory Undertaker
32 other provisions — procedural and definitional
s.art001
Citation and commencement
s.art002
Interpretation
s.art003
Incorporation of enactments relating to railways
s.art004
Incorporation of local railway enactments
s.art005
Power to construct and maintain works
s.art006
Power to deviate
s.art007
Power to execute street works
s.art008
Permanent and temporary stopping up and diversion of streets
s.art009
Access to works
s.art010
Discharge of water
s.art012
Power to transfer and lease rights of operation
s.art013
Power to acquire land
s.art014
Application of Part I of the Compulsory Purchase Act 1965
s.art015
Powers to acquire new rights
s.art016
Temporary use of land for construction of works
s.art017
Temporary use of land for maintenance of works
s.art018
Disregard of certain interests and improvements
s.art019
Acquisition of part of certain properties
s.art020
Extinction or suspension of private rights of way
s.art021
Time limit for exercise of powers of acquisition
s.art022
Power to operate and use railways
s.art023
Maintenance of approved works etc.
s.art024
Disclosure of confidential information
s.art025
Statutory undertakers etc.
s.art026
Certification of plans etc.
s.art027
Service of notices
s.art028
No double recovery
s.art029
Arbitration
s.art030
Trespass on railway
s.art031
Agreements with
s.art032
For the protection of Network Rail
s.art033
For the protection of the Environment Agency
Schedules
Schedules
0 of 40 shown40 other schedules
s.sch004
The enactments for the time being in force with respect...
s.sch004
(1) Without prejudice to the generality of paragraph 1, the...
s.sch004
(1) The 1965 Act shall have effect with the modifications...
s.sch004
For section 7 of the 1965 Act (measure of compensation)...
s.sch004
For section 8 of the 1965 Act (provisions as to...
s.sch004
The following provisions of the 1965 Act (which state the...
s.sch004
Section 11 of the 1965 Act (powers of entry) shall...
s.sch004
Section 20 of the 1965 Act (protection for interests of...
s.sch004
Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch006
(1) Sections 271 to 274 of the 1990 Act (power...
s.sch006
(1) Where a street is stopped up under article 8...
s.sch006
(1) Subject to the following provisions of this paragraph, the...
s.sch007
(1) The following provisions of this Schedule shall have effect...
s.sch007
If at any time after the completion of an identified...
s.sch007
The undertaker shall not provide any illumination or illuminated sign...
s.sch007
Any additional expenses which Network Rail may reasonably incur in...
s.sch007
(1) The undertaker shall pay to Network Rail all reasonable...
s.sch007
In the assessment of any sums payable to Network Rail...
s.sch007
The provisions of Schedule 6 to this Order shall not...
s.sch007
Nothing in this Schedule shall impose any liability on the...
s.sch007
(1) The undertaker shall not under the powers conferred by...
s.sch007
(1) The undertaker shall, before commencing construction of any identified...
s.sch007
Any identified work shall, when commenced, be constructed—
s.sch007
The undertaker shall— (a) at all times afford reasonable facilities...
s.sch007
Network Rail shall at all times afford reasonable facilities to...
s.sch007
(1) If any alterations or additions, either permanent or temporary,...
s.sch007
The undertaker shall repay to Network Rail all reasonable fees,...
s.sch007
(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch008
(1) The following provisions shall apply for the protection of...
s.sch008
The fact that any work or thing has been executed...
s.sch008
For the purposes of Chapter II of Part II of...
s.sch008
Any dispute arising between the undertaker and the Environment Agency...
s.sch008
(1) Before beginning to construct any specified work, the undertaker...
s.sch008
Without prejudice to the generality of paragraph 2, the requirements...
s.sch008
(1) Any specified work, and all protective works required by...
s.sch008
(1) The undertaker shall from the commencement of the construction...
s.sch008
If by reason of the construction of any specified work...
s.sch008
(1) The undertaker shall take all such measures as may...
s.sch008
The undertaker shall indemnify the Environment Agency in respect of...
s.sch008
(1) Without prejudice to the other provisions of this Schedule,...
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.