UK Statutory Instrument SI 2001/3627 United Kingdom

The South Hampshire Rapid Transit Order 2001

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Statutory Undertaker1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Statutory Undertaker — also bound by 179 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art032 Power to survey and investigate land Regulated
  • Undertaker must give 7 days' notice before entering land for surveysStatutory Undertaker
70 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Application of enactments relating to railways
s.art004 Application of
s.art005 Power to construct works
s.art006 Power to deviate
s.art007 Designation of works
s.art008 Power to alter layout of streets
s.art009 Power to keep apparatus in streets
s.art010 Power to execute street works
s.art011 Stopping up of streets
s.art012 Temporary stopping up of streets
s.art013 Access to works
s.art014 Construction and maintenance of new or altered streets
s.art015 Construction of bridges and tunnels
s.art016 Restoration of streets if street tramway discontinued
s.art017 Agreements with street authorities
s.art018 Level crossings
s.art019 Agreements with
s.art020 As to local railway enactments
s.art021 Additional powers for tunnel
s.art022 Prohibitions within tunnel area
s.art023 Protection of tunnel,
s.art024 As to Portsmouth to Gosport ferry, etc.
s.art025 No apparatus in tunnel without consent
s.art026 Protection of navigation
s.art027 Attachment of equipment to buildings for purposes of transit system
s.art028 Discharge of water
s.art029 Safeguarding works to buildings
s.art030 Power to construct temporary transit systems
s.art031 Planning permission: supplementary matters
s.art033 Mode of construction and operation of transit system
s.art034 Obstruction of construction of transit system
s.art035 Power to acquire land
s.art036 Application of Part I of Compulsory Purchase Act 1965
s.art037 Application of Compulsory Purchase (Vesting Declarations) Act 1981
s.art038 Powers to acquire new rights
s.art039 Powers to acquire subsoil only
s.art040 Rights under or over streets
s.art041 Temporary use of land for construction of works
s.art042 Temporary use of land for maintenance of works
s.art043 Disregard of certain interests and improvements
s.art044 Acquisition of part of certain properties
s.art045 Extinction or suspension of private rights of way
s.art046 Time limit for exercise of powers of acquisition
s.art047 Power to operate and use transit system
s.art048 Maintenance of approved works, etc.
s.art049 Power to charge fares
s.art050 Disapplication of duties respecting provision of transport services
s.art051 Concessionary travel
s.art052 Removal of obstructions
s.art053 Traffic signs
s.art054 Traffic regulation
s.art055 Power to lop trees overhanging transit system
s.art056 Trespass on tramroads and busways
s.art057 Power to make byelaws
s.art058 Power to contract for police services
s.art059 Powers of disposal, agreements for operation, etc.
s.art060 Application of landlord and tenant law
s.art061 Tramcars deemed to be public service vehicles
s.art062 Substitute road services
s.art063 Statutory undertakers, etc.
s.art064 Protection of railway interests
s.art065 Minerals
s.art066 Saving for highway authorities
s.art067 Disclosure of confidential information
s.art068 Certification of plans, etc.
s.art069 Service of notices
s.art070 No double recovery
s.art071 Arbitration
Schedules

Schedules

0 of 51 shown
51 other schedules
s.sch007 In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
s.sch007 (1) The undertaker shall, before commencing any specified work or...
s.sch007 Without prejudice to any conditions attached to an approval by...
s.sch007 (1) Notwithstanding anything in this Order but subject to paragraph...
s.sch007 The Undertaker shall— (a) at all times afford reasonable facilities...
s.sch007 (1) The Queen’s Harbour Master may recover from the undertaker...
s.sch007 Any difference arising between the undertaker and the Queen’s Harbour...
s.sch007 The provisions of paragraphs 10 to 15 shall have effect...
s.sch007 Nothing in this Schedule shall prejudice or derogate from the...
s.sch007 (1) A tidal work shall not be constructed, altered, replaced...
s.sch007 (1) The undertaker shall— (a) during the whole time of...
s.sch007 (1) In case of damage to or destruction or decay...
s.sch007 (1) Where a tidal work is abandoned, or allowed to...
s.sch007 The Secretary of State may, if he considers it expedient,...
s.sch007 (1) The undertaker shall— (a) exhibit at the outer extremity...
s.sch007 (1) Where the undertaker is guilty of an offence under...
s.sch007 The Secretary of State shall be entitled to recover from...
s.sch008 The enactments for the time being in force with respect...
s.sch008 (1) Without prejudice to the generality of paragraph 1 above,...
s.sch008 (1) The 1965 Act shall have effect with the modifications...
s.sch008 For section 7 of the 1965 Act (measure of compensation)...
s.sch008 For section 8 of the 1965 Act (provisions as to...
s.sch008 The following provisions of the 1965 Act (which state the...
s.sch008 Section 11 of the 1965 Act (powers of entry) shall...
s.sch008 Section 20 of the 1965 Act (protection for interests of...
s.sch008 Section 22 of the 1965 Act (protection of acquiring authority’s...
s.sch011 (1) Subject to the following provisions of this paragraph, sections...
s.sch011 (1) Where a street is stopped up under article 11...
s.sch011 (1) Paragraph 21 of the telecommunications code shall not apply...
s.sch012 The following provisions of this Schedule shall have effect, unless...
s.sch012 The undertaker shall give to the engineer not less than...
s.sch012 The specified works shall, when commenced, be constructed—
s.sch012 The undertaker shall— (a) at all times afford reasonable facilities...
s.sch012 Railtrack shall at all times afford reasonable facilities to the...
s.sch012 Before either Railtrack or the undertaker provide any new illumination...
s.sch012 If at any time after completion of the specified works...
s.sch012 (1) Subject to paragraph 19 below, the undertaker shall pay...
s.sch012 Railtrack shall, on receipt of a request of a receipt...
s.sch012 The undertaker shall indemnify Railtrack from and against all claims...
s.sch012 Railtrack shall give to the undertaker reasonable notice of any...
s.sch012 In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
s.sch012 In the assessment of any sums payable to Railtrack under...
s.sch012 Nothing in this Schedule shall impose any liability on the...
s.sch012 If the cost to Railtrack of maintaining, working or removing...
s.sch012 In so far as the specified works or the acquisition...
s.sch012 The undertaker shall not under the powers of this Order...
s.sch012 (1) The undertaker shall not exercise the powers of article...
s.sch012 (1) For the purposes of this paragraph— “EMI” means, subject...
s.sch012 (1) The undertaker shall, as soon as reasonably practicable following...
s.sch012 (1) The undertaker shall before commencing construction of the specified...
s.sch012 (1) Upon signifying his approval or disapproval of the plans...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.