Get a lawful development certificate

A lawful development certificate confirms that an existing or proposed use or work is lawful for planning purposes. Anyone can apply. For an existing use you carry the burden of proof on the balance of probabilities. Knowingly or recklessly making a materially false or misleading statement to get one is an offence.

UK-wide

Choose the certificate you need

Anyone can apply to the local planning authority for a lawful development certificate. The statute sets no requirement to own the land or hold an interest in it. You do not have to hold a certificate, but you may need one to confirm that a use, operation or activity is lawful for planning purposes.

Common reasons to apply are doubt over whether a proposal is permitted development and a belief that the enforcement time limit has run out on something already in place. Another is a sale where you need to show the buyer that the authority can take no enforcement action.

A certificate is not a replacement for planning permission. You still need planning permission for any development or use the certificate does not cover.

Existing or proposed

Detail Certificate for an existing use or work Certificate for a proposed use or work
It can cover An existing use of buildings or other land, operations already carried out in, on, over or under land, or a failure to comply with a condition or limitation of a planning permission A proposed use of buildings or other land, or operations proposed to be carried out in, on, over or under land
Test the authority applies Whether the use, operations or matter was lawful at the date of your application Whether the use or operations would be lawful if they began at the date of your application
How long lawfulness is presumed While the certificate is in force Unless a material change happens before the use starts or the operations begin

What counts as lawful

A use or operation is lawful for the purposes of a certificate if no enforcement action may then be taken against it and it does not contravene any requirement of an enforcement notice in force. Enforcement action cannot be taken where no planning permission was needed, where the time for enforcement has expired, or for any other reason.

A failure to comply with a condition or limitation of a planning permission is lawful only if the time for enforcement action has expired and the failure does not contravene an enforcement notice or breach of condition notice in force.

Planning merits are not relevant at any stage of the application or an appeal. The question is whether, on the facts and the law, the matter is or would be lawful.

Enforcement time limits in England

Enforcement action may not be taken after these periods, subject to the transitional rule that follows the table.

Breach of planning control Time limit Period runs from
Building, engineering, mining or other operations carried out without planning permission 10 years The date the operations were substantially completed
Change of use of a building to use as a single dwellinghouse 10 years The date of the breach
Any other breach of planning control 10 years The date of the breach
Relevant demolition No time limit. Enforcement action may be taken at any time. Not applicable

The 4-year limit still applies where the operations were substantially completed before 25 April 2024, or the change of use to a single dwellinghouse occurred before that day. Any other breach was always subject to a 10-year limit.

Relevant demolition means demolition of a building in a conservation area in England. It excludes listed buildings, certain ecclesiastical buildings, scheduled monuments and buildings the Secretary of State has excluded by direction.

The limits do not prevent further enforcement action where the authority took, or purported to take, enforcement action for the same breach during the 4 years ending with that action. They do not prevent service of a breach of condition notice while an enforcement notice for the breach is in effect.

A planning enforcement order is a route for cases involving concealment. A magistrates' court can make one for land in England. The order lets the authority take enforcement action at any time in the enforcement year, whether or not the time limits have expired. For a certificate, the time for enforcement is treated as not expired where the time for applying for the order has not expired, where an application for the order is undecided, or where an order has been made and its enforcement year has not expired.

Gather the evidence the authority will accept

You carry the burden of proof. For an existing use, the standard is the balance of probabilities.

For an existing use, if the authority has no evidence of its own, and none from others, that contradicts your account or makes it less than probable, it has no good reason to refuse. That holds only if your evidence alone is sufficiently precise and unambiguous to justify a certificate. The authority may refuse if it has evidence, or reasonable grounds to believe, that your claim is not correct.

The authority is entitled to canvass evidence before it decides. It must share any evidence it obtains with you, and you can comment on it and produce counter-evidence.

If you rely on the time limit for enforcement action having expired, show:

  • that any building was substantially complete at least the time limit for enforcement action before the date of your application
  • that any use, or breach of condition, has carried on continuously for at least the time limit for enforcement action up to the date of your application

For a proposal, describe it with enough clarity and precision for the authority to understand exactly what is involved.

Without sufficient or precise information the authority may be justified in refusing. A refusal is not necessarily conclusive that something is not lawful. It may mean that not enough evidence has been presented so far, and you can apply again with more.

False or misleading information given knowingly, recklessly or with intent to deceive is an offence

It is an offence to do any of these for the purpose of procuring a particular decision on an application for a certificate, whether the application is yours or someone else's:

  • knowingly or recklessly make a statement that is false or misleading in a material particular
  • use a document that is false or misleading in a material particular, with intent to deceive
  • withhold material information, with intent to deceive

In England and Wales, on summary conviction the penalty is an unlimited fine. On conviction on indictment it is up to 2 years in prison, a fine, or both. A magistrates' court may try the offence whenever the information is laid.

Apply to the local planning authority

  1. Decide what you are applying for

    Choose between an existing use, operations already carried out, a failure to comply with a condition, or a proposal. Describe it precisely, not just by its use class, and identify the land.

  2. Collect your evidence

    Gather evidence verifying the information in your application, as much as you can provide. For an existing use or breach of condition, include the date it started, or for a building the date it was substantially complete.

  3. Prepare the plan and the statement of interest

    The plan must identify the land, be drawn to an identified scale and show the direction of north. Where you specify two or more uses, operations or matters, it must show which part of the land each relates to. The statement must set out your interest in the land, the name and address of anyone else known to you to have an interest, and whether they have been notified.

  4. Complete the published form

    Use the form published by the Secretary of State for the type of certificate, or one substantially to the same effect. For a proposed use or operations on Crown land, add a statement that the land is Crown land and, if someone authorised in writing by the appropriate authority applies, a copy of the authorisation.

  5. Pay the fee and submit

    An application is valid only with the appropriate fee. The fee for an existing use or operations is the planning application fee, a proposal costs half of it, and a failure to comply with a condition has a flat fee. Fees can rise each 1 April, so check the current fee first. Apply online through the Planning Portal, or to your local planning authority.

Apply for a lawful development certificate on the Planning Portal (opens in a new tab)

What the authority does with your application

The authority must acknowledge a valid application as soon as reasonably practicable. If it considers the application invalid, it must tell you as soon as reasonably practicable. It may require further information by written notice.

For a valid application, the authority must give you written notice of its decision within 8 weeks beginning with the day after it receives the application. It may take a longer period if you agree in writing, but not once you have given notice of appeal.

There is no statutory requirement to consult neighbours or parish councils. The authority may seek evidence from them if it has good reason to believe they hold relevant information. Their views on planning merits, or on your private rights to carry out the work, are irrelevant.

If the authority is satisfied that the use, operations or matter was lawful at the date of your application, it must issue a certificate. Otherwise it must refuse. For a proposal, it must issue a certificate if you give it information that satisfies it that the use or operations would be lawful if begun at the date of the application.

Instead of refusing outright, the authority may issue a certificate for a modified description or a substituted one. GOV.UK says it is advisable to seek your agreement first.

A certificate must specify the land, describe the use, operations or matter, give the reasons, and specify the date of the application. Where a use falls within a use class, it must identify the class.

What the certificate protects you from, and what it does not

While a certificate for an existing use or operations is in force, their lawfulness is conclusively presumed. The certificate speaks only to the state of affairs on the land at the date of your application.

For a proposed use or operations, lawfulness is conclusively presumed unless there is a material change before the use starts or the operations begin. Examples are an article 4 direction that removes the permitted development right the certificate relies on, and a statutory amendment to permitted development rights.

A certificate has limits:

  • it may be issued for the whole or part of the land in your application, and for all or some of the uses, operations or matters it specifies
  • it does not affect a failure to comply with a condition or limitation of a planning permission unless it describes that matter
  • it speaks only to planning law and does not remove the need to comply with other legal requirements, such as the Building Regulations 2010, the Planning (Listed Buildings and Conservation Areas) Act 1990 or other licensing or permitting schemes
  • it does not protect the land from enforcement action if the specified use later changes materially without a planning application

Revocation

The authority may revoke a certificate if, on the application, a statement was made or a document used that was false in a material particular, or any material information was withheld.

Before revoking, the authority must give notice of its proposal to the owner and the occupier of the land, and to anyone else it considers the revocation will affect. For a certificate the Secretary of State issued, it must also notify the Secretary of State. The notice must invite representations within 14 days of service, and the authority must not revoke until those periods have expired. It must then give written notice of the revocation to each person it notified.

There is no right of appeal against revocation, but it can be challenged in the High Court by judicial review. Revocation may make the owner or occupier liable to immediate enforcement action. No compensation is payable.

If the authority refuses or does not decide

You can appeal to the Secretary of State if the authority refuses your application in whole or in part, or does not give notice of its decision within 8 weeks or a longer period you agreed in writing. A certificate issued for a modified or substituted description counts as a partial refusal.

A refusal notice must state the authority's full reasons clearly and precisely, and tell you that you may appeal to the Secretary of State.

About an appeal:

  • Only the person who made the application can appeal. There is no fee for appealing, and others can comment on the appeal.
  • GOV.UK says there is normally no deadline for appealing a lawful development certificate decision.
  • GOV.UK says not to appeal if you have already been given an enforcement notice, because you may have to pay additional costs.
  • You can apply for planning permission at the same time as you appeal.
  • You can apply for an award of costs if anyone involved in the appeal has cost you money by behaving unreasonably. Costs can also be awarded against you.

On appeal, the Secretary of State grants the certificate, or modifies the one the authority issued, if the refusal was not well-founded. Otherwise the appeal is dismissed. If the Secretary of State considers you responsible for undue delay, the Secretary of State may give you notice that the appeal will be dismissed unless you take steps to expedite it within a set period. If you do not take those steps within that period, the Secretary of State may dismiss the appeal. That power does not apply where both the authority's decision, or failure to decide, and your appeal came before 25 April 2024.

The Secretary of State's decision on an appeal is final. It can be challenged in the High Court by the appellant or the authority, but only on the ground that the Secretary of State got the law wrong or made a procedural error. GOV.UK advises getting advice from a lawyer if you are unsure.

Official guidance