Choose the route that fits your change
A change to an approved planning permission in England can be made by a non-material amendment, by varying conditions or by a fresh application. Which applies depends on how far the change departs from what was approved.
| Route | What it can do | If the council refuses |
|---|---|---|
| Non-material amendment (section 96A) | Changes the permission where the council is satisfied the change is not material, including new, altered or removed conditions | No right of appeal. You would need to submit a planning application |
| Variation of conditions (section 73) | Varies or removes conditions only, and gives a new permission alongside the original. It cannot change the description of the development or extend the time to start | You can appeal to the Secretary of State. The appeal considers only the conditions in question |
| Fresh application | Covers a fundamental or substantial change | You can appeal to the Secretary of State |
Ask for a non-material amendment
The council may change a planning permission if it is satisfied that the change is not material. This power is in section 96A of the Town and Country Planning Act 1990. There is no statutory definition of non-material, because the answer depends on the context of the overall scheme. The route cannot be used to make a material amendment.
The council must consider the effect of your change together with any earlier changes made this way, measured against the permission as originally granted.
The power includes imposing new conditions and removing or altering existing ones, other than the biodiversity gain condition. It covers planning permissions only, not listed building consent.
Only a person with an interest in the land, or someone acting for them, can apply. If the interest covers only part of the land, the application can cover only so much of the permission as affects that land.
Make the application in writing on the form published by the Secretary of State, or a form substantially to the same effect. At the same time, you must notify any other owner of the land and any tenant of an agricultural holding that includes part of the land. The notice must say what the application is for and where the person can view it. It must also say that representations must reach the council within 14 days of the date of the notice.
The council must take into account representations made within those 14 days.
The decision is not a reissue of the permission. The original permission still stands, and the two documents are read together.
Vary or remove conditions
Under section 73 you apply for planning permission to develop the land without complying with conditions of your existing permission. The council considers only the conditions. If it decides on different conditions, or none, it must grant permission accordingly. If it decides the same conditions should apply, it must refuse the application.
A grant gives you a new, independent permission for the same development, with new or amended conditions. It sits alongside the original, which stays intact, and you choose which to implement. The decision notice should set out all the conditions of the new permission.
There is no statutory limit on how far the conditions can change. The change must relate only to conditions, not to the operative part of the permission, and the route cannot change the description of the development.
The route needs a condition listing the originally approved plans. If your permission has none, a section 96A application can seek one, which then allows a section 73 application.
The council may impose new conditions only if they do not materially alter the development and could have been imposed on the earlier permission. A section 73 application cannot disapply the biodiversity gain condition.
In England, the council may not grant the new permission subject to a pre-commencement condition without your written agreement to its terms. A pre-commencement condition must be complied with before building or other operations begin, or before a change of use begins. The rule does not apply to a grant of outline planning permission.
The council needs no agreement from you if it gave you written notice of the proposed condition and you gave no substantive response within 10 working days beginning with the day after the notice date. A substantive response is one that says you do not agree to the condition or comments on it. The notice must set out the text of the condition, the full reasons for it, and the full reasons for it being a pre-commencement condition. These rules apply to permissions granted on or after 1 October 2018.
A section 73 application counts as a new application under the Environmental Impact Assessment Regulations 2017. If the development is of a type listed in Schedule 2 to the Regulations and meets the criteria or thresholds set there, the council must screen it again. An environmental statement must be submitted with the application for environmental impact assessment development.
If the original permission was subject to a planning obligation, the obligation may need a deed of variation.
Conditions still need discharging
Discharging a condition that needs the council's consent, agreement or approval is a separate application.
Know the time to start development
In England, planning permissions carry a condition that development must begin within three years of the grant. The council may direct a longer or shorter period instead. Exceptions include permission granted for a limited period and permission for development already carried out.
Outline permission follows its own rule. An application for approval of reserved matters must be made within three years of the grant. Development must then begin within two years of the final approval of the reserved matters. If they were approved on different dates, the two years run from the last approval. The council may substitute other periods.
In England, the period for starting development is extended by one year if a court gives permission to bring proceedings challenging the validity of the grant. If a party is given permission to appeal against the decision on the challenge after a full hearing, the period is extended by a further year for the Court of Appeal and two years for the Supreme Court. For outline permission, the same extensions apply to any reserved matters or start period that is running. The extensions do not apply to a period that has already expired.
For these time conditions, development begins on the earliest date on which any material operation comprised in the development begins to be carried out.
The section 73 route does not apply at all if the permission carried a time condition for starting development and that time has expired without the development having begun.
Make a fresh application
If a change is fundamental or substantial, you will need to submit a new planning application. A section 96A amendment cannot be used to make a material amendment. A section 73 application cannot change the operative part of the permission or the description of the development.
The council decides whether a change is non-material. A fresh application is decided in the same way as any application for planning permission.
Check how long the council has to decide
For a section 73 or fresh application, the period runs from the day after the council receives a valid application. A valid application includes payment of the fee.
- Non-material amendment
- 28 days from receipt, or a longer period agreed in writing
- Major development (variation or fresh application)
- 13 weeks, or 10 weeks for public infrastructure development
- Other development (variation or fresh application)
- 8 weeks
- Public infrastructure development (variation or fresh application)
- 10 weeks
- With environmental impact assessment
- 16 weeks instead of 8 or 13 weeks
The 10 weeks apply to what the Order calls "public infrastructure development", a term it does not define. It does define "public service infrastructure development" as major development, which is not environmental impact assessment development, where the main purpose is a hospital, a school or further or higher education institution, or criminal justice accommodation, or works to extend or alter one. Check with the council which period applies.
Major development means development that involves any of these:
- minerals working or the use of land for mineral-working deposits
- waste development
- 10 or more homes, or a site of 0.5 hectares or more where the number of homes is not known
- 1,000 square metres or more of new floor space
- a site of 1 hectare or more
You and the council can agree a longer period in writing. For a section 73 or fresh application, you cannot agree an extension once you have given notice of appeal.
Pay the fee
A fee is payable for a non-material amendment application and for a section 73 application. The non-material amendment fee has one amount for a householder application and another amount in any other case.
The section 73 fee has separate amounts for a householder application, an application for major development and any other application. One section 73 application can remove or alter several conditions without multiplying the fee.
The regulations index the amounts each 1 April, so check the amount in force on the day you apply.
Appeal against a refusal
There is no right of appeal against refusal or non-determination of a section 96A application. You would need to submit a planning application to seek approval for the amendment.
You can appeal to the Secretary of State about a section 73 or fresh application if the council refuses it, grants it subject to conditions, or does not decide it within the prescribed or agreed period. There is no fee for appealing.
An appeal against refusal of a section 73 application considers only the conditions in question. If a fresh application is granted subject to conditions and you appeal against them, the Inspector re-determines the whole application, not only the conditions, and could refuse planning permission.
A shorter limit of 28 days applies in some cases where an enforcement notice has been served on the same or substantially the same land and development.
Otherwise, the limit for an appeal against refusal of a householder or minor commercial application is 12 weeks from the date of the decision notice. For every other appeal it is 6 months from the date of the decision notice, including an appeal against a grant made subject to conditions. If the council gave no decision, the 6 months run from the end of the period it had to decide.
Legal basis
Primary legislation and key regulations
Official guidance
GOV.UK planning conditions guidance (opens in a new tab)
MHCLG · England and Wales
Determining a planning application (opens in a new tab)
MHCLG · England
Fees for planning applications (opens in a new tab)
MHCLG · England
Flexible options for planning permissions (opens in a new tab)
MHCLG · England