Small site planning fast track

Quick checklist for SME developers submitting minor residential applications (1-9 dwellings). Skip the explanation - get straight to what you need to do.

Construction & Property Starting a Business Updated 15 September 2026
references 5 guides

Small site planning checklist

This is a fast-track checklist for experienced developers. If you need detailed explanations, see the full guides linked throughout.

Before application

Permitted development check

  • ☐ Checked if proposal qualifies as permitted development (prior approval)
  • ☐ Checked for Article 4 directions removing PD rights
  • ☐ If PD applies, submit prior approval application (not full planning)

Site constraints

  • ☐ Checked local plan designations (such as housing, green belt)
  • ☐ Checked conservation area / listed building status
  • ☐ Checked Tree Preservation Orders
  • ☐ Checked flood zone (use EA flood map)
  • ☐ Checked nutrient neutrality catchment (27 catchments)

Check if nutrient neutrality affects you

List of affected catchments

Application documents

Always required

  • ☐ Completed application form (online via Planning Portal)
  • ☐ Location plan (1:1250/1:2500) - red line site, blue line other ownership
  • ☐ Site plan (1:200/1:500)
  • ☐ Floor plans and elevations
  • ☐ Ownership certificate (A, B, C or D)
  • ☐ Agricultural holdings certificate
  • ☐ Correct fee paid

Often required (check local validation list)

  • ☐ Planning statement
  • ☐ Design and Access Statement (if in conservation area)
  • ☐ Biodiversity Gain Plan and metric
  • ☐ Tree survey (if trees on/adjacent to site)
  • ☐ Flood Risk Assessment (if in flood zone or >1ha)
  • ☐ Nutrient Neutrality Statement (if in affected catchment)

Biodiversity net gain

Exemption check

  • ☐ Self-build for own occupation → exempt
  • ☐ Householder application → exempt
  • ☐ Impact under 25sqm habitat AND under 5m linear habitat AND no priority habitat affected → exempt (de minimis)
  • ☐ Site of 0.2ha or under → exemption confirmed 15 April 2026 but NOT yet in force (expected ~end July 2026, with a priority-habitat carve-out) - until then BNG still applies

If BNG applies

  • ☐ Baseline survey completed (within 2 years)
  • ☐ Small Sites Metric completed
  • ☐ Post-development biodiversity value calculated
  • ☐ 10% net gain achieved (on-site preferred)
  • ☐ Biodiversity Gain Plan prepared

BNG for small sites

Simplified BNG compliance for minor development

Key timescales

Minor application determination8 weeks
Condition discharge8 weeks
Appeal deadline (householder)12 weeks
Appeal deadline (other minor)6 months
Permission validity3 years (unless stated)

Before starting work

  • ☐ All pre-commencement conditions discharged IN WRITING
  • ☐ CIL Assumption of Liability submitted
  • ☐ CIL exemptions claimed (if applicable)
  • ☐ Commencement Notice submitted (CIL)
  • ☐ Party wall notices served (if applicable)
  • ☐ Building control application/notice submitted

Discharge planning conditions

Step-by-step condition discharge guide

Full guides

For detailed guidance on any of these topics:

Planning for small sites

Complete guide for minor development

Apply for planning permission

Step-by-step application guide