Guide
Grid Connection Agreement
All electricity generators connecting to the GB electricity network require a connection agreement with either National Grid ESO (transmission) or a Distribution Network Operator (DNO).
Connection queue crisis
The transmission connections queue exceeds 700GW of projects - over four times the installed capacity needed by 2050. Major reforms are underway to address this backlog.
Connections reform: TM04+
From January 2025, new transmission connection applications follow the 'First Ready, First Connected' (TM04+) process with two gates:
- Gate 1: Initial application with indicative connection date
- Gate 2: Firm offer requiring proof of planning progress and land rights
Milestones and termination
Projects must meet milestones (planning submission, land agreements) within designated timeframes. Failure to meet milestones can result in offer termination with cancellation charges.
Distribution connections
Smaller generators connect via DNOs. For projects impacting transmission, DNOs submit applications to NESO on behalf of customers.
-
Identify connection type
Identify whether you need transmission (>50MW typically) or distribution connection
-
Submit transmission application
For transmission, submit application during open application windows
-
Prepare Gate 2 evidence
Prepare evidence of planning progress and land rights for Gate 2
-
Apply to DNO
For distribution, apply directly to your local DNO
-
Allow connection time
Allow 12-36+ months for connection depending on required reinforcement
-
Consider battery storage
Consider battery storage to manage grid constraints