Energy & Utilities Energy and utilities UK-wide

Offshore Wind Development Consent Orders (DCO)

Offshore wind projects over 100MW in English territorial waters require a Development Consent Order from the Secretary of State. Understand the specific thresholds, fees, timelines and 7-stage process for offshore wind NSIPs.

Guide summary

You must get a Development Consent Order (DCO) for offshore wind farms over 100MW in English waters. Apply to the Planning Inspectorate and expect the process to take around 4 years from start to finish. The fee is £9,286 when you apply, with extra costs for inspections.

  • Get a DCO for offshore wind farms over 100MW in English waters
  • Apply to the Planning Inspectorate, not the local council
  • Pay a £9,286 application fee plus inspection costs
  • Pre-application work takes about 2 years
  • Statutory process from acceptance to decision takes about 12 months
  • Real-world average total time is 4.2 years from start to consent
  • A single DCO covers planning, marine licence and other consents
  • Smaller projects under 100MW use different rules (Section 36)
  • Judicial review must start within 6 weeks of the decision
On this page

Development Consent Order (DCO)

Offshore wind farms exceeding 100MW and other Nationally Significant Infrastructure Projects (NSIPs) require a Development Consent Order from …

Grid Connection Agreement

All electricity generators connecting to the GB electricity network require a connection agreement with either NESO (National Energy …

When you need a DCO for offshore wind

Offshore wind farms are classified as Nationally Significant Infrastructure Projects (NSIPs) under the Planning Act 2008 if they exceed capacity thresholds. The DCO process provides all necessary consents for construction and operation in a single application.

Understanding the DCO process

The DCO examination process is rigorous and involves multiple stages of consultation, environmental assessment, and public scrutiny. Understanding these stages helps you plan timelines and resource requirements.

Alternative planning routes

The DCO route applies to larger offshore wind projects in England. Smaller projects and those in devolved nations follow different planning frameworks.

Key milestones and dependencies

The DCO process has critical dependencies:

  • You must secure an Agreement for Lease from The Crown Estate before submitting your DCO application
  • Evidence of grid connection progress (Gate 2 milestone) is required to demonstrate project deliverability
  • Financial close typically requires DCO consent before investors commit funding

Plan for 3-4 years from pre-application to DCO decision, with a further 12-18 months to financial close.