Develop offshore wind projects and secure seabed leases
How to develop offshore wind projects in UK waters, from securing seabed rights through Crown Estate leasing rounds …
How to connect electricity generation projects to the UK grid. Understand the difference between DNO and National Grid routes, the G99 connection standard, and the April 2025 Ofgem reforms that promise £5 billion in savings and faster connection timelines.
You need a grid connection agreement to export electricity from your project. Smaller projects (under 50MW) connect via your local DNO, larger ones via National Grid. New rules since April 2025 aim to shorten wait times and save costs.
How to develop offshore wind projects in UK waters, from securing seabed rights through Crown Estate leasing rounds …
How to register for the Smart Export Guarantee (SEG) to receive payment for renewable electricity you export to …
Businesses supplying electricity to consumers in Great Britain require a Supply Licence from Ofgem.
All electricity generators connecting to the GB electricity network require a connection agreement with either NESO (National Energy …
A confirmation checklist for energy businesses. Work through the cross-cutting duties every energy business shares, then the section …
Connecting to the electricity grid is a critical milestone for any electricity generation project. Whether you're developing a wind farm, solar array, or hydrogen production facility with electrolysis, you cannot export power without a grid connection agreement.
The path you take depends on your project's capacity: smaller projects (typically under 50 MW) connect via your local Distribution Network Operator (DNO), while larger projects connect to the transmission network via National Grid ESO.
In April 2025, Ofgem approved major reforms to the electricity connections process. The 'First Ready, First Connected' (TM04+) process came into force in January 2025 for new transmission connection applications, with reforms expected to deliver significant savings across the industry and significantly reduce connection wait times.
Key changes include:
These reforms are designed to clear the 700GW+ connection queue - over four times the installed capacity needed by 2050 - and accelerate the transition to clean energy.
Once you've accepted a connection offer and paid your deposit, you'll work with the network operator to design the connection infrastructure, agree protection settings, and schedule commissioning tests.
For transmission connections, you must also execute a Connection and Use of System Code (CUSC) agreement, which governs ongoing use of the transmission network and includes charges for system operation.
Allow several months between securing your connection agreement and energisation for design work, construction of grid infrastructure, and compliance with Grid Code or Distribution Code technical requirements.