Under construction: We're building this service in the open. Set your business context to see how personalised content will work.
Excuse our dust — things may change. Changes are saved to your session and the page will reload.
â—‰
Content Graph
7 reusable snippets referenced
COMAH Compliance for Energy Facilities
Grid Connection Agreement
Environmental Permit - Part A(1) Installation
Environmental Permit - Medium Combustion Plant
Apply for Electricity Generation Licence (Northern Ireland)
Apply for Electricity Generation Licence (Great Britain)
How to determine if you need an electricity generation licence from Ofgem (GB) or the Utility Regulator (NI). Covers licensing thresholds, exemptions, environmental permits, grid connections, and COMAH compliance for larger energy facilities.
UK-wide
Check if you need an electricity generation licence. You must have one if your capacity is 50MW or more. Smaller generators under 50MW may be exempt. Operating without a required licence can lead to unlimited fines.
Check if your capacity is 50MW or more
Apply to Ofgem (GB) or Utility Regulator (NI) if needed
Small generators under 50MW may be exempt
Licence application fee: £350 to £1,050
Minimum annual licence fee: £500
Penalty for unlicensed generation: unlimited fines
Environmental permits needed for combustion plants
Grid connection requirements apply
COMAH compliance needed for hazardous storage
Enforcement time limit: 5 years
If you generate electricity in the UK, you may need a licence from the energy regulator. Operating without a required licence is a criminal offence with unlimited fines.
Most small and medium generators are exempt under the Class Exemptions Order. This guide explains:
When you need a generation licence (50MW threshold)
Differences between Great Britain and Northern Ireland
Environmental permits for combustion plant
Grid connection requirements
COMAH compliance for hydrogen and hazardous storage
Do you need a generation licence?
The Electricity Act 1989 prohibits unlicensed generation. However, the Class Exemptions Order provides automatic exemptions for smaller generators.
Key exemption points
You are exempt from licensing if:
Your declared net capacity is under 50MW
You generate under 10MW under the alternative small generator exemption
You consume all electricity on-site (no export)
You need a licence if:
Your capacity is 50MW or above
You don't meet Class Exemption conditions
You export to the grid above exemption thresholds
Applying for a licence in Great Britain
In England, Scotland, and Wales, Ofgem is the licensing authority for electricity generation.
What happens after you get a licence
Licence holders must comply with Standard Licence Conditions on an ongoing basis. These include:
Grid Code compliance
Distribution Code compliance (if connecting to distribution network)
Connection and Use of System Code (CUSC) compliance
Financial reporting to Ofgem
Information provision on request
Breaching licence conditions can result in enforcement action with penalties up to 10% of turnover.
Applying for a licence in Northern Ireland
Northern Ireland has a separate regulatory system. The Utility Regulator (NIAUR) is the licensing authority, not Ofgem.
Northern Ireland differences
Key differences from Great Britain:
Different application process and forms
Participates in Single Electricity Market (SEM) with Republic of Ireland
Northern Ireland Renewables Obligation (NIRO) rather than GB RO schemes
Smaller market with different commercial dynamics
Environmental permits for combustion plant
If you operate combustion plant (boilers, engines, turbines, CHP), you need environmental permits in addition to any generation licence.
Large combustion plant (50MW+)
Larger installations require more rigorous permitting as Part A(1) installations.
Decarbonisation readiness (from February 2026)
New electricity generating stations will need to demonstrate readiness for decarbonisation when applying for environmental permits. This includes feasibility assessments for:
Carbon capture and storage (CCS)
Conversion to hydrogen firing
Plan for this requirement if you're developing new generation capacity.
Grid connection requirements
All generators connecting to the electricity network need a connection agreement. The current connections queue is severely backlogged with over 700GW of projects waiting.
Navigating the connections queue
From January 2025, the 'First Ready, First Connected' (TM04+) process applies to new transmission connection applications. Key points:
Gate 1: Submit application during open window for indicative connection date
Gate 2: Provide evidence of planning progress and land rights for firm offer
Milestones: Must meet designated milestones or risk offer termination
For smaller projects connecting via distribution networks, apply directly to your local DNO. Timelines are generally shorter but still depend on reinforcement requirements.
COMAH compliance for energy facilities
If your energy facility stores hazardous substances (including hydrogen for hydrogen-ready plant), you may need to comply with Control of Major Accident Hazards (COMAH) regulations.
Even below COMAH thresholds, DSEAR (Dangerous Substances and Explosive Atmospheres Regulations) applies to all facilities handling flammable substances.
Steps to set up electricity generation
Determine if you need a licence
Calculate your declared net capacity. Under 50MW (or under 10MW for alternative exemption), you're likely exempt. Check the specific Class Exemption conditions apply to your situation.
Choose your regulator (GB vs NI)
Great Britain generators apply to Ofgem. Northern Ireland generators apply to the Utility Regulator. Different processes and forms apply.
Apply for environmental permits
MCP (1-50MW) or Part A(1) (50MW+) permits from Environment Agency (England), SEPA (Scotland), or NRW (Wales). Apply well before construction as permits take 3-18 months.
Secure grid connection
Apply for transmission (NESO) or distribution (DNO) connection during open application windows. Allow 1-5+ years depending on reinforcement needs.
Assess COMAH requirements
If storing hydrogen or hazardous substances, determine your COMAH tier and notify the Competent Authority (HSE/EA or HSE/SEPA).
Apply for generation licence (if required)
Submit Ofgem application with technical specifications, financial information, and evidence of ability to comply with licence conditions. Allow 3-6 months.
How to register for the Smart Export Guarantee (SEG) to receive payment for renewable electricity you export to the grid. Covers solar PV, wind, and other small-scale renewables up to 5MW.
How to develop offshore wind projects in UK waters, from securing seabed rights through Crown Estate leasing rounds to obtaining Section 36 consent, safety zones, and grid connections. Covers England, Wales, Scotland, and Northern Ireland with differences in consenting regimes and landlords.
All electricity generators connecting to the GB electricity network require a connection agreement with either NESO (National Energy System Operator) (transmission) or a Distribution Network Operator (DNO).
Offshore wind projects over 100MW in English territorial waters require a Development Consent Order from the Secretary of State. Understand the specific thresholds, fees, timelines and 7-stage process for offshore wind NSIPs.
Type to search across guides, journeys, regulators, legislation, and topics.
Compliance Assistant
Ask about UK business regulations
Running in limited mode — some features may be unavailable
I can help you navigate UK business regulations using our knowledge graph of official government guidance. My answers aren't legal advice — I'll link you to the authoritative sources so you can verify anything that matters.
Ask me about compliance obligations, tax thresholds, sector regulations, or anything else about running a business in the UK.