UK Statutory Instrument
2018
United Kingdom
The A19/A184 Testo's Junction Alteration Development Consent Order 2018
At a glance
What's here
1 compliance obligation
What this Act requires
Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.
Schedules
Browse 73 other Schedules — structural / supplementary
Work No. 9 — The diversion of 5 no. electric...
Work No. 10 — The construction of a drainage attenuation...
Work No. 11 — The construction of a new private...
Work No. 12 — Improvement to existing private means of...
Work No. 13 — The upgrade of the existing B27...
Work No. 14 — The construction of a new bridleway...
Work No. 15 — The construction of a new footpath...
Work No. 16 — The construction of a perimeter security...
Work No. 17 — The construction of a new footway...
In the administration area of South Tyneside
Work No. 18 — The construction of a widened and...
Work No. 19 — The construction of an improved section...
Work No. 20 — The construction of a pedestrian crossing...
Work No. 21 — The construction of a new footway...
Work No. 22 — The alteration and realignment of Testo's...
Work No. 23 — Environmental mitigation works at Boldon Lake....
Work No. 24 — The diversion of a Northumbrian Water...
Work No. 25 — The diversion of British Telecommunications cables...
Work No. 26 — The diversion of a Northern Gas...
Work No. 27 — The stopping up of the B28...
A nationally significant infrastructure project as defined in sections 14...
Work No. 28 — The construction of a new northbound...
Work No. 29 — The construction of a new southbound...
Work No. 30 — The construction of a drainage attenuation...
Work No. 31 — The main site compound to include,...
In connection with the construction of any of those works,...
Work No. 1 — The construction of a new cantilever...
Work No. 2 — The construction of a new section...
Work No. 3 —The construction of a new southbound A19...
Work No. 4 — The construction of a new cycle-track...
Work No. 5 — The construction of a new northbound...
Work No. 6 — The construction and realignment of a...
Work No. 7 — The construction of a new southbound...
Interpretation
Traffic management
Amendments to approved details
Fencing
Applications made under requirements
Further information
Register of requirements
Anticipatory steps towards compliance with any requirement
Time limits
Detailed design
Construction and handover environmental management plans
Landscaping
Contaminated land and groundwater
Protected species
Surface and foul water drainage
Archaeological remains
The enactments for the time being in force with respect...
(1) Without limitation on the scope of paragraph 1, the...
(1) Without limitation on the scope of paragraph 1, the...
Part 1 (compulsory purchase under Acquisition of Land Act 1946)...
(1) The modification referred to in paragraph 4(a) are as...
For the protection of the utility undertakers referred to in...
(1) Subject to the following provisions of this paragraph, the...
(1) Subject to sub-paragraphs (2) and (3), if by reason...
Where in consequence of the proposed construction of any part...
Nothing in this Part of this Schedule affects the provisions...
For the protection of any operator, the following provisions have...
In this Part of this Schedule— “the 2003 Act” means...
The exercise of the powers conferred by article 31 (statutory...
(1) Subject to sub-paragraphs (2) to (4), if as the...
In this Part of this Schedule— “alternative apparatus” means alternative...
This Part of this Schedule does not apply to apparatus...
(1) Where any street is stopped up under article 13...
The undertaker, in the case of the powers conferred by...
Regardless of any provision in this Order or anything shown...
(1) If, in the exercise of the powers conferred by...
(1) Where, in accordance with the provisions of this Part...
(1) Not less than 28 days before starting the execution...
The reference to a document in the table with a...
Authority to survey and investigate the land
- Grant access for surveying, trial holes and archaeological investigations on your land
Browse 41 other sections — procedural / definitional / commencement
Citation and commencement
Interpretation
Development consent etc. granted by the Order
Maintenance of authorised development
Maintenance of drainage works
Limits of deviation
Benefit of Order
Consent to transfer benefit of Order
Application of the 1991 Act
Construction and maintenance of new, altered or diverted streets
Classification of roads, etc.
Temporary stopping up and restriction of use of streets
Permanent stopping up and restriction of use of streets and private means of access
Access to works
Clearways
Traffic regulation
Discharge of water
Protective work to buildings
Compulsory acquisition of land
Compulsory acquisition of land – incorporation of the mineral code
Time limit for exercise of authority to acquire land compulsorily
Compulsory acquisition of rights and restrictive covenants
Private rights over land
Modification of Part 1 of the 1965 Act
Application of the 1981 Act
Acquisition of subsoil or airspace only
Rights under or over streets
Temporary use of land for carrying out the authorised development
Temporary use of land for maintaining the authorised development
Statutory undertakers
Apparatus and rights of statutory undertakers in stopped up streets
Recovery of costs of new connections
Felling or lopping of trees and removal of hedgerows
Trees subject to tree preservation orders
Application of landlord and tenant law
Operational land for purposes of the Town and Country Planning Act 1990
Defence to proceedings in respect of statutory nuisance
Protection of interests
Certification of documents, etc.
Service of notices
Arbitration