Unless an extension is agreed, the BSR takes up to 12 weeks to assess a building control application for a new higher-risk building, and up to 8 weeks for work to an existing one. Build these periods, and a contingency, into your programme.
Milestone 2 of 6
New higher-risk building development compliance
Plan for the three gateways
Gateway 2 is building control approval before work starts; Gateway 3 is the completion certificate before occupation.