Milestone 2 of 6 Managing CDM Regulations compliance on construction projects

Notify HSE if the project is notifiable

Larger projects must be notified to HSE before the construction phase begins.

A project is notifiable if construction work on site is scheduled to last longer than 30 working days with more than 20 workers working at the same time at any point, or to exceed 500 person days. The client must notify HSE in writing as soon as is practicable before the construction phase begins, and display the notice in the site office where workers can read it.

Submit F10 notification to HSE

How to complete and update the F10 notice.