Pay or challenge a street works penalty

Find out whether you have a fixed penalty notice or an overrun charge, and how to pay or challenge it. The law gives no appeal against a fixed penalty notice, and an unpaid one can lead to prosecution.

UK-wide

Two different demands can reach a works promoter in England. Where the works are carried out under a statutory right or licence, the promoter is the undertaker. A fixed penalty notice offers a way to discharge liability to conviction for a listed offence by paying a penalty. An overrun charge is payable to the highway authority when works run over time. It is a charge under section 74 of the New Roads and Street Works Act 1991 (the 1991 Act), not a fine or a penalty notice.

The fixed penalty amounts and periods, the permit scheme offences and the overrun charge regulations apply in England. Wales has its own fixed penalty regulations and its own overrun charge regulations, the Street Works (Charges for Unreasonably Prolonged Occupation of the Highway) (Wales) Regulations 2009.

Who can be given a fixed penalty notice

An authorised officer of a street authority, or of a Permit Authority (the authority that runs a permit scheme) for the permit offences, may give a notice if the officer has reason to believe a person is committing or has committed the offence.

For the 1991 Act notice offences, the person liable is the undertaker: the holder of the statutory right or street works licence to carry out the works or, for works under a street works permit, the person the permit allows to carry them out. The two permit offences also reach a person contracted to act on the undertaker's behalf, so a contractor can be liable too. The Department for Transport's code of practice for the co-ordination of street and road works (March 2026), called the code here, is guidance. It says an authority gives the notice to the promoter executing the works, not to the contractor.

From 10 April 2026 the permit offences apply to an undertaker. That includes a person entitled by a street works permit to carry out charge point street works. Before that date they applied to a statutory undertaker.

The code adds that a notice may be given only for the street, or section of street, where the works take place. It cannot be given for authority works for road purposes unless separate contractual arrangements provide for penalties, or for optional permits.

No notice can be given for a street that is not a maintainable highway. No 1991 Act notice can go to a director, manager, secretary or similar officer personally. Offences committed by virtue of section 166 of the 1991 Act are not fixed penalty offences. Such an officer, or someone purporting to act as one, can still be prosecuted if the company's offence was committed with their consent or connivance, or is attributable to their neglect.

Fixed penalty offences

Schedule 4A to the 1991 Act lists the fixed penalty offences under Part 3 of the Act. The permit regulations add two more.

Fixed penalty offences

Offence What it covers Committed by
s.54(5) of the 1991 Act Failure to comply with duties under s.54 (advance notice of certain works) An undertaker
s.55(5) Beginning to execute works in contravention of s.55 (notice of starting date) An undertaker
s.55(9) Failure to give notice in accordance with s.55(8) (notice to be given when a s.55 notice ceases to have effect) An undertaker
s.57(4) Failure to give notice in accordance with s.57 (notice of emergency works) An undertaker
s.70(6), failing to comply with s.70(3) or (4A) Failure to comply with the requirements to give notice of completion of reinstatement An undertaker
An offence created by regulations under s.74(7B) Failure to give a notice required by regulations under s.74 (charge where works unreasonably delayed) An undertaker
An offence created by regulations under s.74A(11) Failure to give a notice required by regulations under s.74A (charge determined by reference to duration of works) An undertaker
Regulation 19 of the Traffic Management Permit Scheme (England) Regulations 2007 Undertaking specified works in a specified street without a permit, except to the extent that a permit scheme says the requirement does not apply An undertaker or a person contracted to act on its behalf
Regulation 20 of the same regulations Breaching a permit condition An undertaker or a person contracted to act on its behalf

On conviction in the magistrates' court, these offences carry a fine of up to level 4:

  • the offences under ss.54(5), 55(5), 55(9) and 57(4);
  • the s.70(6) offence of failing to comply with s.70(3) or (4A);
  • the offence of failing, without reasonable cause, to give a notice required by the 2009 England overrun charge regulations;
  • an offence created by regulations under s.74A(11), which the Act caps at level 4; and
  • breaching a permit condition.

Level 4 is £2,500 for an offence committed on or after 1 October 1992. Working without a permit carries a fine of up to level 5, which is unlimited for an offence committed on 12 March 2015 or later.

Check the notice

A notice must identify the offence and give reasonable particulars of the circumstances alleged. It must also state the penalty and its payment period, and the discounted amount and its period. It must say whom to pay and how, where to send representations, and the consequences of not paying in time.

A notice may not be given more than 91 days after the offence, counting the day of the offence as the first day. The code adds "unless otherwise agreed between both parties", but the regulations contain no such exception.

A 1991 Act fixed penalty notice, and a notice withdrawing one, must be given through the Department for Transport's digital service for planning and managing roadworks, known as Street Manager. If a notice cannot be given that way, the regulations allow another means of electronic communication. The code says a notice is deemed given on the date and time recorded in Street Manager. A notice under Schedule 4B to the 1991 Act given after 4.30 p.m. on a working day is treated as given on the next working day.

Pay a fixed penalty notice

Payment periods

Amount Period for payment Extension
Discounted amount Before the end of the 29 days beginning with the day the notice is given. If the last day is not a working day, the period runs to the end of the next working day. None beyond the next working day. The code allows an authority to agree more only in exceptional circumstances.
Full amount 36 days beginning with the day the notice is given. The authority may extend the period in any particular case if it considers that appropriate.

Paying in time stops proceedings. No proceedings may start before the full payment period ends. None may start or continue if the penalty is paid before that period ends, or if the authority accepts payment after it. The discounted amount counts only if you pay it within the discount period. After that, the full amount is payable.

Pay the person at the address, and by the method, stated on the notice. The code recommends sending a list of the notice references and values being paid, marked as discounted or full. In proceedings, a certificate signed for the authority's finance officer is evidence of whether a payment was received by a stated date.

Challenge a fixed penalty notice

The law gives no statutory appeal against a fixed penalty notice, no time limit for representations and no list of grounds. The notice must say where to send representations. The authority must consider them and decide whether to withdraw the notice. If it does not withdraw the notice and prosecutes, you defend the case in the magistrates' court.

The code is guidance. It says there is no set time for making representations, but strongly recommends making them within four weeks of receiving the notice. It advises trying to resolve the matter informally first with the officer who served the notice. If that fails, it advises formal written representations to the nominated official named on the notice. It also says the authority may extend the full payment period while it considers representations, up to six months.

Withdrawal differs between the two routes. For a 1991 Act notice, if the street authority considers that the notice ought not to have been given, it may give a notice withdrawing it. For a permit scheme notice, if the Permit Authority considers that the notice ought not to have been given, it shall give a withdrawal notice. On withdrawal the authority must repay any penalty paid. For a 1991 Act notice, no proceedings may then start or continue.

The code says the authority should provide enough evidence with the notice, such as a works inspection report, and share evidence where requested. It also says a notice should be withdrawn, and any payment repaid, if the authority considers no offence was committed at any point after issue.

If a fixed penalty is not paid

Once the payment period has ended, the authority may bring proceedings in the magistrates' court. It does not have to. The code adds that an authority may prosecute instead of offering a notice. It also says paying a notice does not exempt you from other prosecutions or charges under the 1991 Act, such as an overrun charge.

Unless an enactment says otherwise, a magistrates' court cannot try an information laid more than six months after the offence. The time before the notice is given and the payment period both count towards those six months.

Overrun charges

An undertaker executing street works in a maintainable highway in England pays the highway authority a charge for each day, or part of a day, by which the duration of the works exceeds the longer of the prescribed period and a reasonable period. The prescribed period is two working days, starting on the date the works begin.

A reasonable period is the period the authority and the undertaker agree is reasonable or, failing agreement, the period an arbitrator determines.

From 5 January 2026 the charge applies to every day of overrun, including weekends and bank holidays. Before that date only working days were charged.

The duration of the works ends only when the undertaker has completed interim or permanent reinstatement, removed all signing, lighting and guarding, removed all remaining spoil, unused materials and plant, and returned the highway fully to public use.

The regulations apply to every maintainable highway except a footpath, a bridleway, a highway with a pedestrian planning order in force, and a highway whose use by vehicular traffic is prohibited by a traffic order. That last exception does not apply if the prohibition operates only at particular times.

The charge does not apply to:

  • works that do not involve breaking up the street or tunnelling or boring under it, if they take place in a street that is neither traffic-sensitive nor protected, in the footway of a traffic-sensitive street at a traffic-sensitive time, in the footway of a protected street at any time, or in a traffic-sensitive street other than at a traffic-sensitive time;
  • works consisting only of creating holes of less than 3 centimetres in diameter for investigatory purposes;
  • replacing poles, lamp columns or signs in the same location; or
  • pole testing.

A charge is payable only if the highway authority has:

  • given the undertaker a notice that the works are overrunning, within two working days beginning with the date it became aware that they were exceeding the longer of the prescribed period and a reasonable period; and
  • given the undertaker an account setting out the charges, not later than three months after receiving the works closed notice.

The first requirement does not apply if the authority became aware of the overrun more than two months after receiving a works closed notice.

Overrun charge amounts

Regulation 9 of the 2009 Regulations sets the daily amounts. The description of the street is taken on the date the undertaker first gave notice of the works under s.54(1), 55(1) or 57(2), or notification under paragraph 2(1)(d) of Schedule 3A to the 1991 Act, or first applied for provisional advance authorisation or a permit.

If the works take place in any part of the carriageway during the overrun, the first two amount columns apply. If they do not at any time, the last column applies for each day.

Daily overrun charges

Street Carriageway works: each of the first three days Carriageway works: each later day No carriageway works: each day
Traffic-sensitive or protected street not in road category 2, 3 or 4 £5,000 £10,000 £2,500
Other street not in road category 2, 3 or 4 £2,500 £2,500 £2,500
Traffic-sensitive or protected street in road category 2 £3,000 £8,000 £2,000
Other street in road category 2 £2,000 £2,000 £2,000
Traffic-sensitive or protected street in road category 3 or 4 £750 £750 £250
Other street in road category 3 or 4 £250 £250 £250

The charge is a single payment of £100 where all of these apply:

  • the undertaker has completed interim or permanent reinstatement, endeavoured to remove all signing, lighting and guarding, and removed all remaining spoil, unused materials and plant;
  • the works would not otherwise have exceeded the longer of the prescribed and reasonable periods, but not more than five items of signing, lighting or guarding remain on the highway;
  • the authority has told the undertaker the identity and location of those items and asked for their removal; and
  • the undertaker removes them by the end of the next working day after receiving the request.

The highway authority may reduce the amount of a charge or waive it in any particular case, in classes of case, or in all cases. The code treats the table amounts as maximum charges. It says an authority should use these powers reasonably and should consider genuine, non-repeated errors on their merits.

Challenge an overrun charge

The 2009 Regulations set no appeal route and no deadline for objecting to a charge. Failing without reasonable cause to give a notice the regulations require is an offence, and a fixed penalty offence.

  1. Discuss the charge before the account is issued

    The code says promoters may query a charge or its level, and recommends discussing it before the account is issued. Issuing an account does not prevent further negotiation before the invoice is issued.

  2. Settle the reasonable period

    If you and the authority cannot agree it, an arbitrator determines it under s.74(2) and s.99 of the 1991 Act. The authority's view is acted on until the arbitrator decides. A single arbitrator is appointed by agreement or, failing agreement, by the President of the Institution of Civil Engineers.

  3. Check whether the charge applies at all

    The code says s.74 does not apply where there has been a reasonable attempt to complete or replace reinstatement, markings or special surfaces, but on inspection they fail the performance specification in the Specification for the Reinstatement of Openings in Highways. The code's inspections procedure applies instead. This holds only if no part of the highway is obstructed or unavailable for the normal passage of traffic, including pedestrians, for any reason connected with the works, apart from legitimately parked vehicles.

  4. Use the code's dispute procedure

    If agreement cannot be reached locally, the code says the dispute should go for review. The chairs of the regional HAUC (highways authority and utilities committee) review straightforward issues, and HAUC (England) reviews complex ones, normally within ten working days of referral or other agreed time. The code recommends accepting the result as binding. If review fails, it says the dispute should go to independent adjudication. The adjudicator's decision is deemed final, and costs are shared equally unless a party presented a frivolous case. Disputes under s.74(2) may instead be settled by arbitration under s.99, and either party may refer an important point of principle or a particularly expensive scheme to arbitration.

Wales

Official guidance