UK Statutory Instrument SI 2024/564 United Kingdom

The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Operator1 Any Person1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Operator — also bound by 746 other Acts
Any Person — also bound by 2340 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

sch. 14 para. 4 sch. 14 para. 4 Regulated
  • Notify undertaker of claims and do not settle without consentOperator
84 other provisions — procedural and definitional
sch. 10 para. 8 sch. 10 para. 8
sch. 11 para. 8 sch. 11 para. 8
sch. 12 para. 9 sch. 12 para. 9
sch. 13 para. 10 sch. 13 para. 10
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Development consent granted by the Order
s.art004 Maintenance of the authorised project
s.art005 Benefit of Order
s.art006 Disapplication and modification of legislative provisions
s.art007 Defence to proceedings in respect of statutory nuisance
s.art008 Street works
s.art009 Application of the 1991 Act
s.art010 Temporary closure of streets
s.art011 Temporary closure of public rights of way
s.art012 Access to works
s.art013 Agreements with street authorities
s.art014 Discharge of water
s.art015 Protective work to buildings
s.art016 Authority to survey and investigate land
s.art017 Compulsory acquisition of land
s.art018 Time limit for exercise of authority to acquire land compulsorily
s.art019 Compulsory acquisition of rights
s.art020 Private rights over land
s.art021 Application of the 1981 Act
s.art022 Acquisition of subsoil or airspace only
s.art023 Modification of Part 1 of the 1965 Act
s.art024 Rights under or over streets
s.art025 Temporary use of land for carrying out the authorised project
s.art026 Temporary use of land for maintaining the authorised project
s.art027 Statutory undertakers
s.art028 Recovery of costs of new connections
s.art029 Operation of generating station
s.art030 Deemed marine licences under the 2009 Act
s.art031 Application of landlord and tenant law
s.art032 Operational land for purposes of the 1990 Act
s.art033 Felling or lopping of trees and removal of hedgerows
s.art034 Trees subject to tree preservation orders
s.art035 Saving provisions for Trinity House
s.art036 Crown rights
s.art037 Certification of plans and documents, etc.
s.art038 Abatement of works abandoned or decayed
s.art039 Funding
s.art040 Protective provisions
s.art041 Service of notices
s.art042 Arbitration
s.art043 Procedure in relation to approvals, etc. under requirements
s.art044 Modification of DOW section 36 consent
s.art045 Compensation
Schedules

Schedules

1 of 118 shown
s.sch015 Procedure Regulated
  • Keep arbitration documents concise and within 30-page limitAny Person
117 other schedules
s.sch008 Compensation enactments
s.sch008 (1) Without limitation on the scope of paragraph 1, the...
s.sch008 (1) Without limitation on the scope of paragraph 1, the...
s.sch008 Application of Part 1 of the 1965 Act
s.sch008 (1) The modifications referred to in paragraph ‎4(a) are as...
s.sch010 Aviation safety
s.sch010 Chemicals, drilling and debris
s.sch010 Force majeure
s.sch010 Pre-construction plans and documentation
s.sch010 Site Integrity Plan
s.sch010 Approval of programmes, statements etc
s.sch010 Offshore safety management
s.sch010 Reporting of engaged agents, contractors and vessels
s.sch010 Pre-construction monitoring and surveys
s.sch010 Construction monitoring and surveys
s.sch010 Post-construction monitoring and surveys
s.sch010 Reporting of scour and cable protection
s.sch010 Completion of construction
s.sch010 Sediment Sampling
s.sch010 Collaboration
s.sch010 Obstacle free zone for navigational safety
s.sch011 Aviation safety
s.sch011 Chemicals, drilling and debris
s.sch011 Force majeure
s.sch011 Pre-construction plans and documentation
s.sch011 Site Integrity Plan
s.sch011 Approval of programmes, statements etc
s.sch011 Offshore safety management
s.sch011 Reporting of engaged agents, contractors and vessels
s.sch011 Pre-construction monitoring and surveys
s.sch011 Construction monitoring and surveys
s.sch011 Post-construction monitoring and surveys
s.sch011 Reporting of scour and cable protection
s.sch011 Completion of construction
s.sch011 Sediment Sampling
s.sch011 Collaboration
s.sch011 Obstacle free zone for navigational safety
s.sch012 Force majeure
s.sch012 Pre-construction plans and documentation
s.sch012 Site Integrity Plan
s.sch012 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch012 Offshore safety management
s.sch012 Reporting of engaged agents, contractors and vessels
s.sch012 Pre-construction monitoring and surveys
s.sch012 Construction monitoring and surveys
s.sch012 Post-construction monitoring and surveys
s.sch012 Reporting of scour and cable protection
s.sch012 Completion of construction
s.sch012 Sediment Sampling
s.sch012 Collaboration
s.sch012 Seasonal Restriction
s.sch012 Obstacle free zone for navigational safety
s.sch013 Pre-construction plans and documentation
s.sch013 Site Integrity Plan
s.sch013 (1) Each programme, statement, plan, protocol or scheme required to...
s.sch013 Offshore safety management
s.sch013 Reporting of engaged agents, contractors and vessels
s.sch013 Pre-construction monitoring and surveys
s.sch013 Construction monitoring and surveys
s.sch013 Post-construction monitoring and surveys
s.sch013 Reporting of scour and cable protection
s.sch013 Completion of construction
s.sch013 Sediment Sampling
s.sch013 Collaboration
s.sch013 Seasonal Restriction
s.sch013 Obstacle free zone for navigational safety
s.sch014 In relation to any dispute arising under this part of...
s.sch015 Primary objective
s.sch015 Time periods
s.sch015 Timetable
s.sch015 Arbitrator’s powers
s.sch015 Costs
s.sch015 Confidentiality
s.sch017 In this Part— “Defra” means the Department for Environment, Food...
s.sch017 The Sandwich Tern CIMP approved under this Schedule includes any...
s.sch017 In the event of any conflict of inconsistency between the...
s.sch017 In this Part— “Defra” means the Department for Environment, Food...
s.sch017 The offshore works may not be commenced until a plan...
s.sch017 Following consultation with the KCSG the Kittiwake CIMP must be...
s.sch017 The Kittiwake CIMP must be based on the strategy for...
s.sch017 The undertaker shall not be required to undertake the artificial...
s.sch017 The undertaker must implement the measures set out in the...
s.sch017 The undertaker shall notify the Secretary of State of completion...
s.sch017 Results from the monitoring scheme must be submitted at least...
s.sch017 The offshore works may not be commenced until a plan...
s.sch017 The compensation measures implemented under the Kittiwake CIMP must not...
s.sch017 The Kittiwake CIMP approved under this Schedule includes any amendments...
s.sch017 In the event of any conflict or inconsistency between the...
s.sch017 In this Part— “Defra” means the Department for Environment, Food...
s.sch017 The offshore works may not be commenced until a plan...
s.sch017 Following consultation with the GCSG the Guillemot CIMP must be...
s.sch017 The Guillemot CIMP must be based on the strategy for...
s.sch017 The undertaker shall not be required to undertake the bycatch...
s.sch017 The undertaker must carry out the measures set out in...
s.sch017 The undertaker shall notify the Secretary of State of completion...
s.sch017 Following consultation with the STCSG the Sandwich Tern CIMP must...
s.sch017 Results from the monitoring scheme must be submitted at least...
s.sch017 The Guillemot CIMP approved under this Schedule includes any amendments...
s.sch017 In the event of any conflict or inconsistency between the...
s.sch017 In this Part— “Defra” means the Department for Environment, Food...
s.sch017 The licenced activities may not be commenced until a plan...
s.sch017 Following consultation with the MEEB steering group the MIMP must...
s.sch017 No laying of any cables or cable protection works may...
s.sch017 The undertaker shall not be required to undertake the oyster...
s.sch017 Subject to paragraph 43 of this Part, the undertaker must...
s.sch017 The undertaker is not required to implement the MIMP if...
s.sch017 (1) The Sandwich Tern CIMP must be based on the...
s.sch017 The undertaker shall notify the Secretary of State of completion...
s.sch017 Results from the monitoring scheme must be submitted at least...
s.sch017 Once the measures have been implemented the undertaker shall provide...
s.sch017 The MIMP approved under this Schedule includes any amendments that...
s.sch017 In the event of any conflict or inconsistency between the...
s.sch017 The undertaker shall not be required to undertake the nesting...
s.sch017 The undertaker must implement the measures set out in the...
s.sch017 The undertaker shall notify the Secretary of State of completion...
s.sch017 Results from the monitoring scheme must be submitted at least...
s.sch017 The compensation measures implemented in accordance with the Sandwich Tern...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.