UK Statutory Instrument 2020 United Kingdom

The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020

At a glance

What's here

1 compliance obligation

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch016

(1) Subject to sub-paragraphs (2) to (4), if as the...

  • Notify Network Rail of damage claims and do not settle without consent
Browse 32 other Schedules — structural / supplementary
s.sch013

The enactments for the time being in force with respect...

s.sch013

(1) Without limitation on the scope of paragraph 1, the...

s.sch013

(1) Without limitation on the scope of paragraph 1, the...

s.sch013

Part 1 (compulsory purchase under Acquisition of Land Act 1946)...

s.sch013

(1) The modifications referred to in paragraph 4(a) are as...

s.sch015

(1) Sections 271 to 274 (power to extinguish rights of...

s.sch015

(1) Where a street is stopped up under article 8...

s.sch016

Application

s.sch016

Damage to apparatus: costs, losses, etc.

s.sch016

Enactments and agreements

s.sch016

(1) For the protection of any operator, the following provisions...

s.sch016

This Part of this Schedule does not apply toβ€”

s.sch016

Nothing in this Part of this Schedule affects the provisions...

s.sch016

(1) The following provisions of this Part of this Schedule...

s.sch016

(1) Before beginning to construct any specified work, Network Rail...

s.sch016

Without limitation on the scope of paragraph 17, the requirements...

s.sch016

(1) Subject to sub-paragraph (2), any specified work, and all...

s.sch016

The provisions of paragraph 1 of Schedule 15 (provisions relating...

s.sch016

(1) Subject to sub-paragraph (5) Network Rail must from the...

s.sch016

Subject to paragraph 23, if by reason of the construction...

s.sch016

(1) Network Rail must take all such measures as may...

s.sch016

Nothing in paragraphs 19(4), 20(3), 21, 22(3) and (4) authorises...

s.sch016

Network Rail must indemnify the drainage authority in respect of...

s.sch016

(1) Without affecting the other provisions of this Part of...

s.sch016

The fact that any work or thing has been executed...

s.sch016

This Part of this Schedule does not apply to apparatus...

s.sch016

Interpretation

s.sch016

Acquisition of apparatus

s.sch016

Alternative apparatus

s.sch016

(1) Where, in accordance with the provisions of this Part...

s.sch016

Existing apparatus: protection and access

s.sch016

Expenses

Browse 46 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Incorporation of the Railway Clauses Acts

s.art004

Application of the 1991 Act

s.art005

Disapplication of legislative provisions

s.art006

Power to construct and maintain works

s.art007

Power to deviate

s.art008

Closure of road level crossings

s.art009

Replacement and closure of footpath level crossings

s.art010

Accommodation crossings

s.art011

Power to alter layout etc. of streets

s.art012

Power to execute street works

s.art013

Stopping up of streets

s.art014

Temporary stopping up of streets

s.art015

Construction and maintenance of new or altered highways

s.art016

Access to works

s.art017

Agreements with street authorities

s.art018

Construction of bridges

s.art019

Discharge of water

s.art020

Protective works to buildings

s.art021

Power to survey and investigate land

s.art022

Power to acquire land

s.art023

Application of Part 1 of the 1965 Act

s.art024

Application of the 1981 Act

s.art025

Power to acquire new rights

s.art026

Power to acquire subsoil or airspace only

s.art027

Rights under or over streets

s.art028

Temporary use of land for construction of works

s.art029

Temporary use of land for maintenance of works

s.art030

Temporary use of land for access

s.art031

Disregard of certain interests and improvements

s.art032

Extinction or suspension of private rights of way

s.art033

Time limit for exercise of powers of acquisition

s.art034

Power to transfer undertaking

s.art035

Defence to proceedings in respect of statutory nuisance

s.art036

Power to lop trees overhanging the authorised works

s.art037

Power to operate and use railway

s.art038

Planning Permission

s.art039

Obstruction of construction of authorised works

s.art040

Disclosure of confidential information

s.art041

Statutory undertakers etc.

s.art042

Certification of plans etc.

s.art043

Service of notices

s.art044

Protection of interests

s.art045

No double recovery

s.art046

Arbitration