UK Statutory Instrument 2013 United Kingdom

The Network Rail (Redditch Branch Enhancement) Order 2013

At a glance

What's here

1 compliance obligation

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

s.sch010

(1) Subject to sub-paragraphs (2) to (4), if as the...

  • Notify Network Rail before settling a claim for damage or service interruption
Browse 57 other Schedules — structural / supplementary
s.sch001

Archaeology

s.sch001

Ecological Management

s.sch001

Mitigation of effects on protected species

s.sch001

Trees

s.sch001

Trees – removal of crowns and other alterations

s.sch001

Temporary fencing

s.sch001

Drainage

s.sch001

Contaminated land and groundwater

s.sch001

Footpath diversions – implementation plan

s.sch001

Requirement for written approval

s.sch001

Time limits

s.sch001

Development in accordance with approved details

s.sch001

Construction Environmental Management Plan

s.sch001

Landscaping

s.sch001

Implementation and maintenance of landscaping

s.sch001

Re-use of excavated materials

s.sch001

Highway accesses

s.sch001

Car parking at Alvechurch station

s.sch007

The enactments for the time being in force with respect...

s.sch007

(1) Without limitation on the scope of paragraph 1, the...

s.sch007

(1) The 1965 Act has effect with the modifications necessary...

s.sch007

For section 7 of the 1965 Act (measure of compensation...

s.sch007

(1) For section 8 of the 1965 Act (provisions as...

s.sch007

The following provisions of the 1965 Act (which state the...

s.sch007

(1) Section 11 of the 1965 Act (powers of entry)...

s.sch007

Section 20 of the 1965 Act (protection for interests of...

s.sch007

Section 22 of the 1965 Act (interests omitted from purchase)...

s.sch010

For the protection of the undertakers referred to in this...

s.sch010

Nothing in this Part of this Schedule affects the provisions...

s.sch010

(1) For the protection of any operator, the following provisions,...

s.sch010

The exercise of the powers of article 25 (statutory undertakers)...

s.sch010

This Part of this Schedule does not apply to—

s.sch010

Nothing in this Part of this Schedule affects the provisions...

s.sch010

(1) For the protection of CRT the following provisions of...

s.sch010

(1) Network Rail must not in the exercise of the...

s.sch010

Network Rail must not use any land or property of...

s.sch010

Where so required by the engineer Network Rail must to...

s.sch010

In this Part of this Schedule— “alternative apparatus” means alternative...

s.sch010

(1) Before the commencement of the initial construction of any...

s.sch010

(1) Network Rail must before commencing construction of any specified...

s.sch010

Without affecting its obligations under the provisions of this Part...

s.sch010

Network Rail must give to the engineer 30 days’ notice...

s.sch010

(1) Any specified or protective works must, when commenced, be...

s.sch010

Network Rail must not in the course of constructing a...

s.sch010

(1) Network Rail on being given reasonable notice must—

s.sch010

If at any time after the completion of a specified...

s.sch010

Network Rail must repay to CRT all fees, costs, charges...

s.sch010

(1) If any detriment is caused by the construction or...

s.sch010

This Part of this Schedule does not apply to apparatus...

s.sch010

Any difference arising between Network Rail and CRT under this...

s.sch010

Regardless of any provision in this Order or anything shown...

s.sch010

(1) If, in the exercise of the powers conferred by...

s.sch010

(1) Where, in accordance with the provisions of this Part...

s.sch010

(1) Not less than 28 days before starting the execution...

s.sch010

(1) Subject to the following provisions of this paragraph, Network...

s.sch010

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.schedule/1/part/1/paragraph/1

In the county of Worcestershire, district of Bromsgrove

Browse 40 other sections — procedural / definitional / commencement
s.art001

Citation and commencement

s.art002

Interpretation

s.art003

Incorporation of the Railway Clauses Acts

s.art004

Development consent

s.art005

Maintenance of authorised development

s.art006

Limits of deviation

s.art007

Benefit of Order

s.art008

Street works

s.art009

Public rights of way

s.art010

Application of the

s.art011

Access to works

s.art012

Agreements with street authorities

s.art013

Discharge of water

s.art014

Authority to survey and investigate land

s.art015

Compulsory acquisition of land

s.art016

Time limit for exercise of authority to acquire land compulsorily

s.art017

Compulsory acquisition of rights

s.art018

Private rights

s.art019

Application of Compulsory Purchase (Vesting Declarations) Act 1981

s.art020

Acquisition of subsoil or airspace only

s.art021

Acquisition of part of certain properties

s.art022

Rights under or over streets

s.art023

Temporary use of land for carrying out the authorised development

s.art024

Temporary use of land for maintaining authorised development

s.art025

Statutory undertakers and electronic communications code network operators

s.art026

Recovery of costs of new connections

s.art027

Operation and use of railways

s.art028

Felling or lopping of trees

s.art029

Operational land for purposes of the

s.art030

Defence to proceedings in respect of statutory nuisance

s.art031

Traffic regulation

s.art032

Application of the Land Compensation Act 1973

s.art033

Certification of plans, etc.

s.art034

Service of notices

s.art035

Arbitration

s.art036

Procedure in relation to further approvals, etc., other than under Part 2 of Schedule 1

s.art037

Further provisions, as to approvals,

s.art038

Protective provisions

s.art039

Saving for regulated rights, etc.

Explore more

Browse legislation

Find other UK business legislation with related guidance.