UK Statutory Instrument SI 2008/1261 United Kingdom

The London Gateway Port Harbour Empowerment Order 2008

Status
In Force
Penalty ceiling
Regulated

Does it bind you?

Business-side roles with duties under this instrument.

Trader1 Any Person1

Other Acts binding the same actors

If a role above is yours, these are the other instruments that most often bind it.

Trader — also bound by 825 other Acts
Any Person — also bound by 2340 other Acts

What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

s.art008 Jurisdiction of the Harbour Authority Regulated
  • Comply with conflict resolution notices from PLA or Harbour MasterAny Person
s.art069 Certification of plans, etc. Regulated
  • Submit certified copies of deposited plans and sections to the Secretary of StateTrader
67 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Incorporation of the Harbours, Docks and Piers Clauses Act 1847
s.art004 Byelaws
s.art005 Application of the Local Government Act 1972
s.art006 Application of the New Roads and Street Works Act 1991
s.art007 Incorporation of the Railways Clauses Consolidation Act 1845
s.art009 Agreements entered into by
s.art010 Power to construct, etc., works
s.art011 Power to construct, etc., pontoons and jetties
s.art012 Further mitigation and compensation works
s.art013 Power to dredge
s.art014 Power to deviate
s.art015 Fine for obstructing works
s.art016 Tidal works not to be constructed without approval of the Secretary of State
s.art017 Provision against danger to navigation
s.art018 Lights on tidal works, etc.
s.art019 Stopping up, diversion, provision and upgrading of footpaths and bridleways
s.art020 Power to alter layout of streets, etc.
s.art021 Power to execute street works
s.art022 Temporary stopping up of streets
s.art023 Agreements with street authorities
s.art024 Construction of bridges
s.art025 Level crossings
s.art026 Application of permitted development rights
s.art027 Defence to proceedings in respect of statutory nuisance
s.art028 Power to acquire land
s.art029 Application of Part 1 of the Compulsory Purchase Act 1965
s.art030 Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art031 Disregard of certain interests and improvements
s.art032 Extinction of private rights of way
s.art033 Time limit for exercise of powers of acquisition
s.art034 Duty of the Harbour Authority
s.art035 Power to make charges
s.art036 Power to enter vessels
s.art037 Recovery and enforcement of charges
s.art038 Time when charges are payable and their recovery
s.art039 Security for charges
s.art040 Disputes concerning rates
s.art041 Objection and arbitration in relation to charges
s.art042 Power to appropriate berths, etc.
s.art043 Power to remove goods
s.art044 Power to operate and use railways
s.art045 Saving for regulated rights, etc.
s.art046 Powers of disposal
s.art047 Conservation
s.art048 Obstruction of officers
s.art049 Arrangements with Her Majesty’s Revenue and Customs
s.art050 Agreements with
s.art051 Power to establish a police force
s.art052 Incorporation of Police and Criminal Evidence Act 1984
s.art053 Refusal of a landing place, etc.
s.art054 Power to discharge surface water into
s.art055 Harbour Authority not to be a local lighthouse authority
s.art056 Harbour Authority not to be a port health authority
s.art057 Crown rights
s.art058 For the protection of the local highway authority
s.art059 For the protection of Thurrock Borough Council and others
s.art060 For the protection of Network Rail
s.art061 For the protection of the Port of London Authority
s.art062 For the protection of the
s.art063 For the protection of the Environment Agency
s.art064 For the protection of National Grid Gas plc and other statutory undertakers
s.art065 No double recovery
s.art066 Arbitration
s.art067 Defence of due diligence
s.art068 Local inquiries
Schedules

Schedules

0 of 121 shown
121 other schedules
s.sch001 In this Schedule— (a) “Chainage Reference” means the relevant chainage...
s.sch001 The works referred to in article 10(1) are— Work No....
s.sch002 In this Schedule, “building” does not include any form of...
s.sch002 In the area cross-hatched on the planning restrictions plan, railway...
s.sch002 Only in the area cross-hatched on the planning restrictions plan...
s.sch002 No flood lighting columns shall be constructed within 50 metres...
s.sch002 No more than five entry and exit complexes with associated...
s.sch002 No more than one multi-storey car storage facility is permitted...
s.sch002 No more than one multi-storey car park is permitted with...
s.sch002 Once constructed— (a) no part of the water frontage of...
s.sch002 Construction plant, concrete batching plant, temporary grading, washing and weighing...
s.sch002 Storage of fuels including diesel, petroleum or liquid petroleum gas...
s.sch002 The underground storage and pumping of storm, surface and waste...
s.sch002 Within the port premises, containers may not be stacked above...
s.sch002 The construction and operation of electricity sub-stations is only permitted...
s.sch002 No signage is permitted within the port premises other than...
s.sch002 No relocation, reconstruction or improvement of the existing bitumen and...
s.sch002 Subject to paragraph 24, the area of jurisdiction shall not...
s.sch002 Paragraph 23 shall not preclude— (a) the permanent use of...
s.sch002 The provisions of this Schedule shall be deemed to be...
s.sch002 Within the port premises, gantry cranes used for stacking or...
s.sch002 Quayside container cranes may only be used in the area...
s.sch002 Quayside equipment other than container cranes, such as general cargo...
s.sch002 Subject to paragraph 10, in the area washed in yellow...
s.sch002 In the area washed in blue on the planning restrictions...
s.sch002 Material dredged pursuant to article 13 (power to dredge) may...
s.sch002 Within the port premises, internal harbour security fencing shall not...
s.sch003 In this Schedule— (a) “Coordinates Reference” means the relevant coordinates...
s.sch003 The works referred to in article 13(1) are as follows—...
s.sch005 (1) In their application to any development authorised by this...
s.sch005 (1) Any change of use of the port premises to...
s.sch005 Subject to paragraph 4, regulation 60(1) of the Habitats Regulations...
s.sch005 If and to the extent that any development authorised by...
s.sch006 The following provisions of this Schedule shall have effect for...
s.sch006 No more than the following combinations of B1(b), B1(c), B2...
s.sch006 No more than 157,000m2 of B1(b), B1(c), B2 and B8...
s.sch006 No more than 167,000m2 of B1(b), B1(c), B2 and B8...
s.sch006 No more than the following combinations of B1(b), B1(c), B2...
s.sch006 (1) In circumstances where the related development is not materially...
s.sch006 None of the authorised works shall be brought into beneficial...
s.sch006 Prior to bringing into beneficial use any of the authorised...
s.sch006 (1) The Harbour Authority and the appropriate authority shall agree...
s.sch006 Construction of the authorised works shall not be commenced until...
s.sch006 Notwithstanding the provisions of the 1995 Order any oil and...
s.sch006 (1) In this Schedule— “the A13 Lakeside Link” means that...
s.sch006 The provisions of this Schedule shall be deemed to be...
s.sch006 In circumstances where the related development is materially implemented and...
s.sch006 None of the B1(b), B1(c), B2 or B8 uses or...
s.sch006 (1) This paragraph shall apply unless the Highways Agency acting...
s.sch006 No more than the following combinations of B1(b), B1(c), B2...
s.sch006 No more than the following combinations of B1(b), B1(c), B2...
s.sch006 No more than the following combinations of B1(b), B1(c), B2...
s.sch006 No more than 100,000m2 of the B1(b), B1(c), B2 and...
s.sch007 (1) The provisions of this Schedule shall, unless otherwise agreed...
s.sch007 Any specified work and any protective works to be constructed...
s.sch007 The Harbour Authority shall— (a) at all times afford reasonable...
s.sch007 Network Rail shall at all times afford reasonable facilities to...
s.sch007 (1) If any alterations or additions, either permanent or temporary,...
s.sch007 The Harbour Authority shall repay to Network Rail all reasonable...
s.sch007 If at any time after the completion of a specified...
s.sch007 The Harbour Authority shall not provide any illumination or illuminated...
s.sch007 Any additional expenses which Network Rail may reasonably incur in...
s.sch007 The Harbour Authority shall pay to Network Rail all reasonable...
s.sch007 Network Rail shall give to the Harbour Authority reasonable notice...
s.sch007 The Harbour Authority shall not, under the powers conferred by...
s.sch007 (1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
s.sch007 (1) The sums payable by the Harbour Authority under paragraph...
s.sch007 The provisions of article 32 (extinction of private rights of...
s.sch007 The exercise by the Harbour Authority against Network Rail of...
s.sch007 Where Network Rail is asked to give its consent pursuant...
s.sch007 The Harbour Authority shall before commencing construction of the specified...
s.sch007 The approval of the engineer under paragraph 6 shall not...
s.sch007 If by the end of the period of 56 days...
s.sch007 (1) When signifying his approval of the plans the engineer...
s.sch008 (1) The provisions of this Schedule shall, unless otherwise agreed...
s.sch008 On completion of the construction of any part of a...
s.sch008 (1) If any tidal work— (a) is constructed otherwise than...
s.sch008 (1) If any tidal work or any other work of...
s.sch008 (1) The Harbour Authority shall not in the exercise of...
s.sch008 (1) Before the commencement of construction of the first tidal...
s.sch008 (1) This paragraph applies if any part of the river...
s.sch008 (1) The Harbour Authority shall be responsible for and make...
s.sch008 (1) Before dedicating or designating any land under article 47...
s.sch008 (1) Subject to article 4(3) and this paragraph, any function...
s.sch008 (1) Section 72 of the 1968 Act (vesting of embanked...
s.sch008 (1) Before— (a) submitting any plans and sections for any...
s.sch008 Notwithstanding paragraph 3, and unless otherwise agreed in writing between...
s.sch008 For the avoidance of doubt, section 73 of the 1968...
s.sch008 (1) The Harbour Authority shall pay to the PLA for...
s.sch008 (1) Before exercising any power under section 252 of the...
s.sch008 Any dispute arising between the Harbour Authority and the PLA...
s.sch008 Subject to paragraph 21, no tidal work shall be subject...
s.sch008 Any operations for the construction of any tidal work approved...
s.sch008 (1) The Harbour Authority shall not without the consent of...
s.sch008 The Harbour Authority shall not, in exercise of the powers...
s.sch008 If any pile, stump or other obstruction to navigation becomes...
s.sch008 If— (a) by reason of the construction of any tidal...
s.sch008 In addition to any requirement under article 18 (lights on...
s.sch009 The provisions of this Schedule shall, unless otherwise agreed in...
s.sch009 Nothing in this Order shall prejudice or derogate from any...
s.sch009 (1) The Harbour Authority shall be responsible for and reimburse...
s.sch010 (1) The provisions of this Schedule shall, unless otherwise agreed...
s.sch010 (1) The Harbour Authority shall indemnify the Agency in respect...
s.sch010 The fact that any work or thing has been executed...
s.sch010 (1) For the purposes of section 109 of the Water...
s.sch010 (1) Provided the Harbour Authority and the Agency agree, any...
s.sch010 In this Schedule— “accumulation” means any accumulation of silt or...
s.sch010 (1) At the same time as submitting any plans and...
s.sch010 (1) Before beginning to construct any specified work other than...
s.sch010 Before commencing the construction of a specified work liable to...
s.sch010 (1) Subject to sub-paragraph (2), the Harbour Authority shall, from...
s.sch010 If, by reason of the construction of a specified work...
s.sch010 (1) If, during the construction of a specified work or...
s.sch010 (1) The Harbour Authority shall take all such measures as...
s.sch011 (1) Subject to the following provisions of this paragraph, sections...
s.sch011 (1) For the protection of the undertaker referred to in...
s.sch011 (1) If, in the exercise of any of its powers...
s.sch011 (1) Where, in accordance with the provisions of this Schedule,...
s.sch011 (1) Not less than 56 days before commencing the construction...
s.sch011 (1) Subject to the following provisions of this paragraph, the...
s.sch011 (1) Subject to sub-paragraphs (2) and (3), if by reason...

Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.