What it requires

Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.

12 other provisions — procedural and definitional
s.art001 Citation and commencement
s.art002 Interpretation
s.art003 Incorporation of Railways Clauses Consolidation Act
s.art004 Permanent stopping up of streets
s.art005 Agreement with the street authority
s.art006 Power to operate, use and maintain the new railway
s.art007 Maintenance of approved works
s.art008 Service of notices
s.art009 No double recovery
s.art010 Arbitration
s.art011 Provision of level crossings over new highway
s.art012 Provision for abandonment of redundant railway
Schedules

Schedules

1 of 14 shown
s.sch002 When one or other of the key switches mentioned in... Regulated
  • Follow safe crossing procedures: stop at stop boards, sound whistle, and do not proceed without white light or shunter directionOperator
13 other schedules
s.sch002 In this Schedule: (a) All references to a regulation are...
s.sch002 An advance warning board of standard railway design shall be...
s.sch002 In this Part— “class I retroreflecting material” is material which...
s.sch002 Visual indicators shall be provided in each primary control point....
s.sch002 The undertaker shall give notice in writing to the Secretary...
s.sch002 There shall be a road traffic light controller to provide...
s.sch002 A lamp which when illuminated shows a light signal of...
s.sch002 The road traffic light signal controller mentioned in paragraph 2...
s.sch002 The special phase mentioned in paragraph 4 above shall be...
s.sch002 There shall be a primary control point on each rail...
s.sch002 There shall be a secondary control point on each rail...
s.sch002 A driver’s indicator shall be provided on each railway approach...
s.sch002 A stop board of standard railway design displaying the words...