Retained EU Law 2017 United Kingdom

Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance)

At a glance

What's here

10 compliance obligations

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

s.art024

Availability of TSO's means, tools and facilities

  • TSO must ensure availability and reliability of key tools and facilities
s.art028

Obligations of SGUs concerning voltage control and reactive power management in system operation

  • Manage voltage control and reactive power in line with TSO requirements
s.art039

Dynamic stability management

  • Manage dynamic stability of the transmission system
s.art040

Organisation, roles, responsibilities and quality of data exchange

  • Agree and publish data exchange roles and quality standards
s.art045

Structural data exchange

  • Provide structural data to the Transmission System Operator
s.art046

Scheduled data exchange

  • Provide scheduled operational data to the Transmission System Operator
s.art047

Real-time data exchange

  • Provide real-time data to the transmission system operator
s.art053

Data exchange between TSOs and distribution-connected demand facilities or third parties participating in demand response

  • Provide scheduled and real-time data to the TSO and DSO for demand response
s.art054

Responsibility of the SGUs

  • Notify TSO/DSO of changes, disturbances, test schedules and comply with testing requests
s.art191

Amendments to contracts and general terms and conditions

  • Ensure contracts and general terms comply with system operation regulation
Browse 188 other sections — procedural / definitional / commencement
s.annex iii para.1

Frequency quality defining parameters referred to in Article 127:

s.annex iii para.2

Frequency quality target parameters referred to in Article 127:

s.annex ii para.1

Voltage ranges referred to in Article 27:

s.annex iv para.1

FRCE target parameters referred to in Article 128:

s.annex vi para.1

Limits and requirements for the exchange of FCR referred to...

s.annex v para.1

FCR technical minimum requirements referred to in Article 154:

s.art001

Subject matter

s.art002

Scope

s.art003

Definitions

s.art004

Objectives and regulatory aspects

s.art005

Terms and conditions or methodologies of TSOs

s.art006

Approval of terms and conditions or methodologies of TSOs

s.art007

Amendments to the terms and conditions or methodologies of TSOs

s.art008

Publication on internet

s.art009

Recovery of costs

s.art010

Stakeholder involvement

s.art011

Public consultation

s.art012

Confidentiality obligations

s.art013

Agreements with TSOs not bound by this Regulation

s.art014

Monitoring

s.art015

Annual report on operational security indicators

s.art016

Annual report on load-frequency control

s.art017

Annual report on regional coordination assessment

s.art018

Classification of system states

s.art019

Monitoring and determination of system states by TSOs

s.art020

Remedial actions in system operation

s.art021

Principles and criteria applicable to remedial actions

s.art022

Categories of remedial actions

s.art023

Preparation, activation and coordination of remedial actions

s.art025

Operational security limits

s.art026

Security plan for critical infrastructure protection

s.art027

Obligations of all TSOs regarding voltage limits

s.art029

Obligations of all TSOs concerning voltage control and reactive power management in system operation

s.art030

Short-circuit current

s.art031

Short-circuit current calculation and related measures

s.art032

Power flow limits

s.art033

Contingency lists

s.art034

Contingency analysis

s.art035

Contingency handling

s.art036

General requirements on protection

s.art037

Special protection schemes

s.art038

Dynamic stability monitoring and assessment

s.art041

Structural and forecast data exchange

s.art042

Real-time data exchange

s.art043

Structural data exchange

s.art044

Real-time data exchange

s.art048

Structural data exchange

s.art049

Scheduled data exchange

s.art050

Real-time data exchange

s.art051

Data exchange between TSOs and DSOs concerning significant power generating modules

s.art052

Data exchange between TSOs and transmission-connected demand facilities

s.art055

Tasks of TSOs regarding system operation

s.art056

Purpose and responsibilities

s.art057

Performing operational tests and analysis

s.art058

Training program

s.art059

Training conditions

s.art060

Training coordinators and trainers

s.art061

Certification of system operator employees in charge of real-time operation

s.art062

Common language for communication between the system operator employees in charge of real time operation

s.art063

Cooperation between TSOs on training

s.art064

General provisions regarding individual and common grid models

s.art065

Year-ahead scenarios

s.art066

Year-ahead individual grid models

s.art067

Year-ahead common grid models

s.art068

Updates of year-ahead individual and common grid models

s.art069

Week-ahead individual and common grid models

s.art070

Methodology for building day-ahead and intraday common grid models

s.art071

Quality control for grid models

s.art072

Operational security analysis in operational planning

s.art073

Year-ahead up to and including week-ahead operational security analysis

s.art074

Day-ahead, intraday and close to real-time operational security analysis

s.art075

Methodology for coordinating operational security analysis

s.art076

Proposal for regional operational security coordination

s.art077

Organisation for regional operational security coordination

s.art078

Regional operational security coordination

s.art079

Common grid model building

s.art080

Regional outage coordination

s.art081

Regional adequacy assessment

s.art082

Outage coordination objective

s.art083

Regional coordination

s.art084

Methodology for assessing the relevance of assets for outage coordination

s.art085

Lists of relevant power generating modules and relevant demand facilities

s.art086

Update of the lists of relevant power generating modules and relevant demand facilities

s.art087

Lists of relevant grid elements

s.art088

Update of the list of relevant grid elements

s.art089

Appointment of outage planning agents

s.art090

Treatment of relevant assets located in a distribution system or in a closed distribution system

s.art091

Variations to deadlines for the year-ahead outage coordination

s.art092

General provisions on availability plans

s.art093

Long-term indicative availability plans

s.art094

Provision of year-ahead availability plan proposals

s.art095

Year-ahead coordination of the availability status of relevant assets for which the outage planning agent is not a TSO taking part in an outage coordination region, nor a DSO or a CDSO

s.art096

Year-ahead coordination of the availability status of relevant assets for which the outage planning agent is a TSO taking part in an outage coordination region, a DSO or a CDSO

s.art097

Provision of preliminary year-ahead availability plans

s.art098

Validation of year-ahead availability plans within outage coordination regions

s.art099

Final year-ahead availability plans

s.art100

Updates to the final year-ahead availability plans

s.art101

Management of the ‘testing’ status of relevant assets

s.art102

Procedure for handling forced outages

s.art103

Real-time execution of the availability plans

s.art104

Forecast for control area adequacy analysis

s.art105

Control area adequacy analysis

s.art106

Control area adequacy ...

s.art107

Control area adequacy in day-ahead and intraday

s.art108

Ancillary services

s.art109

Reactive power ancillary services

s.art110

Establishment of scheduling processes

s.art111

Notification of schedules within scheduling areas

s.art112

Coherence of schedules

s.art113

Provision of information to other TSOs

s.art114

General provisions for ENTSO for Electricity operational planning data environment

s.art115

Individual grid models, common grid models and operational security analysis

s.art116

Outage coordination

s.art117

System adequacy

s.art118

Synchronous area operational agreements

s.art119

LFC block operational agreements

s.art120

LFC area operational agreement

s.art121

Monitoring area operational agreement

s.art122

Imbalance netting agreement

s.art123

Cross-border FRR activation agreement

s.art124

Cross-border RR activation agreement

s.art125

Sharing agreement

s.art126

Exchange agreement

s.art127

Frequency quality defining and target parameters

s.art128

FRCE target parameters

s.art129

Criteria application process

s.art130

Frequency quality evaluation data

s.art131

Frequency quality evaluation criteria

s.art132

Data collection and delivery process

s.art133

Synchronous area monitor

s.art134

LFC block monitor

s.art135

Information on load and generation behaviour

s.art136

Ramping period within the synchronous area

s.art137

Ramping restrictions for active power output

s.art138

Mitigation

s.art139

Basic structure

s.art140

Process activation structure

s.art141

Process responsibility structure

s.art142

Frequency containment process

s.art143

Frequency restoration process

s.art144

Reserve replacement process

s.art145

Automatic and manual frequency restoration process

s.art146

Imbalance netting process

s.art147

Cross-border FRR activation process

s.art148

Cross-border RR activation process

s.art149

General requirements for cross-border control processes

s.art150

TSO notification

s.art151

Infrastructure

s.art152

System states related to system frequency

s.art153

FCR dimensioning

s.art154

FCR technical minimum requirements

s.art155

FCR prequalification process

s.art156

FCR provision

s.art157

FRR dimensioning

s.art158

FRR minimum technical requirements

s.art159

FRR prequalification process

s.art160

RR dimensioning

s.art161

RR minimum technical requirements

s.art162

RR prequalification process

s.art163

Exchange of FCR within a synchronous area

s.art164

Sharing of FCR within a synchronous area

s.art165

General requirements for the exchange of FRR and RR within a synchronous area

s.art166

General requirements for sharing FRR and RR within a synchronous area

s.art167

Exchange of FRR within a synchronous area

s.art168

Sharing of FRR within a synchronous area

s.art169

Exchange of RR within a synchronous area

s.art170

Sharing of RR within a synchronous area

s.art171

General requirements

s.art172

Frequency coupling between synchronous areas

s.art173

Exchange of FCR between synchronous areas

s.art174

Sharing of FCR between synchronous areas

s.art175

General requirements for sharing of FRR and RR between synchronous areas

s.art176

Exchange of FRR between synchronous areas

s.art177

Sharing of FRR between synchronous areas

s.art178

Exchange of RR between synchronous areas

s.art179

Sharing of RR between synchronous areas

s.art180

Cross-border activation process for FRR/RR

s.art181

Time control process

s.art182

Reserve providing groups or units connected to the DSO grid

s.art183

General transparency requirements

s.art184

Information on operational agreements

s.art185

Information on frequency quality

s.art186

Information on the load-frequency control structure

s.art187

Information on FCR

s.art188

Information on FRR

s.art189

Information on RR

s.art190

Information on sharing and exchange

s.art192

Entry into force